ACQ 203 Part B
|
Course |
ACQ203V_20313-Virtual Instructor-Led Training; ACQ 203V Intermediate Systems Acquisition, Part B |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Question 1
0 out of 1 points
|
|
|
|||||||||||||
|
|
For questions 1 through 5 (worth 1 point each), use the data (In $Millions) below from the latest Integrated Program Management Report (IPMR) from your contractor:
Calculate the Cost Variance (CV) and the Schedule Variance (SV) then pick the true statement from the answers below: |
|
|
|
||||||||||
|
|
|
|
|
|
· Question 2
0 out of 1 points
|
|
|
|||||||||||||
|
|
Use the IPMR data (In $Millions) to answer the question below.
Calculate the Schedule Performance Index (SPI). Based on the SPI: |
|
|
|
||||||||||
|
|
|
|
|
|
· Question 3
1 out of 1 points
|
|
|
|||||||||||||
|
|
Use the data (In $Millions) below from the latest Integrated Program Management Report (IPMR) from your contractor:
Calculate the Cost Performance Index (CPI). Based on the CPI: |
|
|
|
||||||||||
|
|
|
|
|
|
·
Question 4
0 out of 1 points
|
|
|
|||||||||||||
|
|
Use the data (In $Millions) below from the latest Integrated Program Management Report (IPMR) from your contractor:
Pick the true statement from the answers below:
|
|
|
|
||||||||||
|
|
|
|
|
|
·
·
· Question 5
0 out of 1 points
|
|
|
|||||||||||||
|
|
Use the data (In $Millions) below from the latest Integrated Program Management Report (IPMR) from your contractor:
Based on the IPMR data on this component, what should we tell the Program Manager? |
|
|
|
||||||||||
|
|
|
|
|
|
· Question 6
0 out of 3 points
|
|
|
|||||||||||
|
|
The program office for a Navy shipboard communications system early in the TMRR phase just conducted an affordability analysis of their key performance parameters. The program can save 10% on overall life cycle cost by trading 5% of point to point surface communications range KPP for greater component reliability. The Navy CDD sponsor agreed to include the requirements change as part of staffing for the CDD-V. For questions 6 through 9 (worth 3 points each), choose the greatest potential impact of the changed requirements on the given functional area (i.e., which is the greatest impact on Logistics, on T&E, on Funds Management etc.): The greatest impact on Logistics will be: |
|
|
|
||||||||
|
|
|
|
|
|
· Question 7
3 out of 3 points
|
|
|
|||||||||||
|
|
The program office for a Navy shipboard communications system early in the TMRR phase just conducted an affordability analysis of their key performance parameters. The program can save 10% on overall life cycle cost by trading 5% of point to point surface communications range KPP for greater component reliability. The Navy CDD sponsor agreed to include the requirements change as part of staffing for the CDD-V. For questions 6 through 9 (worth 3 points each), choose the greatest potential impact of the changed requirements on the given functional area (i.e., which is the greatest impact on Logistics, on T&E, on Funds Management etc.): The greatest impact on Test and Evaluation will be: |
|
|
|
||||||||
|
|
|
|
|
|
· Question 8
3 out of 3 points
|
|
|
|||||||||||
|
|
The program office for a Navy shipboard communications system early in the TMRR phase just conducted an affordability analysis of their key performance parameters. The program can save 10% on overall life cycle cost by trading 5% of point to point surface communications range KPP for greater component reliability. The Navy CDD sponsor agreed to include the requirements change as part of staffing for the CDD-V. For questions 6 through 9 (worth 3 points each), choose the greatest potential impact of the changed requirements on the given functional area (i.e., which is the greatest impact on Logistics, on T&E, on Funds Management etc.): The greatest impact on Systems Engineering will be: |
|
|
|
||||||||
|
|
|
|
|
|
· Question 9
0 out of 3 points
|
|
|
|||||||||||
|
|
The program office for a Navy shipboard communications system early in the TMRR phase just conducted an affordability analysis of their key performance parameters. The program can save 10% on overall life cycle cost by trading 5% of point to point surface communications range KPP for greater component reliability. The Navy CDD sponsor agreed to include the requirements change as part of staffing for the CDD-V. For questions 6 through 9 (worth 3 points each), choose the greatest potential impact of the changed requirements on the given functional area (i.e., which is the greatest impact on Logistics, on T&E, on Funds Management etc.): The greatest impact on Contracting will be: |
|
|
|
||||||||
|
|
|
|
|
|
·
· Question 10
3 out of 3 points
|
|
|
|||||||||||
|
|
If any task on a project’s critical path increases, this means…? |
|
|
|
||||||||
|
|
|
|
|
|
·
· Question 11
0 out of 3 points
|
|
|
|||||||||||
|
|
A recent ACQ 203 graduate touring a contractor facility stops to speak with a worker on the manufacturing floor. “Any chance you could make that widget a little bigger?” She asks the worker. “Sure, no problem,” says the worker and he makes the widget bigger. The contracting officer receives an invoice for the widget a few weeks later that is significantly higher than she expected. This is an example of a/an…? |
|
|
|
||||||||
|
|
|
|
|
|
·
· Question 12
3 out of 3 points
|
|
|
|||||||||||
|
|
Cybersecurity planning activities, including writing the Cybersecurity Strategy annex to the Program Protection Plan, should begin____________________. |
|
|
|
||||||||
|
|
|
|
|
|
·
· Question 13
0 out of 3 points
|
|
|
|||||||||||
|
|
Consider the program structure chart when answering the questions 13 – 15 Which of the following changes should be made to the phases and decisions depicted on the program schedule? |
|
|
|
||||||||
|
|
|
|
|
|
·
· Question 14
0 out of 3 points
|
|
|
|||||||||||
|
|
Which of these program events is scheduled too early in the lifecycle? |
|
|
|
||||||||
|
|
|
|
|
|
·
· Question 15
0 out of 3 points
|
|
|
|||||||||||
|
|
Which one of the following changes should be made to program funding? |
|
|
|
||||||||
|
|
|
|
|
|