1. Backup old data
a. 15 minutes/workstation
2. Deployment times
a. When the user is available… Lunch? Break? Weekend? Evenings?
b. How are we deploying these? Big bang deployment or staggered?
i. Create your timeline….
1. Week1 – 10 PCs at night
2. Week2 – 10 PCs at night
3. Week3 – 25 PCs at night
Baseline
Backup – 15 minutes
Workstation removal – 15 minutes
OS – 1 hour
Configuration – 30 minutes
Application installation – 10 minutes
Disposal – 10 minutes
Training - ???
2 hours and 20 minutes/workstation = 140 minutes
140 minutes * 100 workstations = 14000 minutes
233 hours * $25/hour
$5,825