TechDrivers presentation
1
To:
From:
Date: August 30th, 2020
Subject: Status Report
The purpose of this report is to highlight the status and progress of the implementation of the proposed information system at Techdrivers. Techdrivers, a logistics company, seeks to implement the Splunk IT solution in order to address its challenges of cyber-attacks, and log file management.
Project Task for this week:
· Identifying the necessary resources to implement the project
· Conducting a feasibility study to determine its chances of success or failure
· Consulting stakeholders on the best approach to implement the system
· Drawing timelines for implementation
Project Task accomplished this week:
· Managed to identify necessary resources
· Conducted a feasibility study that established the effectiveness of the Splunk system
· Drew timelines for project implementation
· Consulted stakeholders on the best approach to use in implementing the system
Project Issues:
· Inadequate resources for implementation
· Opposition from some staff
Project tasks planned for next week:
· Creating collaboration between staff from Techdrivers and Splunk company
· Conducting staff training on running of the Splunk system
· Phased implementation of the system into Techdrivers operations.
· Identifying gaps in the implementation process
· Risk analysis