Project Schedule

Project Schedule
Project Management Improvement Project – Phase 1 Start Date Finish Date Duration
1 Initiate Project
1.1 Develop Project Charter
1.1.1 Define Scope 8/25/19 8/27/19 2
1.1.2 Define Requirements 8/27/19 8/29/19 2
1.1.3 Identify High-Level Roles 8/29/19 8/31/19 2
1.1.4 Develop High-Level Budget 9/1/19 9/3/19 2
1.1.5 Identify High-Level Control Strategies 9/3/19 9/4/19 1
1.1.6 Draft Charter and Gain Approvals 9/5/19 9/7/19 2
1.1.6.1 Consolidate and Publish Project Charter 9/7/19 9/8/19 1
1.1.6.2 Hold Review Meeting 9/9/19 9/10/19 1
1.1.6.3 Revise Project charter 9/11/19 9/12/19 1
1.1.6.4 Gain approvals 9/3/19 9/4/19 1
2 Plan Project
2.1 Develop Work Plan
2.1.1 Develop Work Breakdown Structure 9/4/19 9/5/19 1
2.1.2 Develop Project Staffing Plan 9/5/19 9/7/19 2
2.1.3 Develop Project Schedule 9/7/19 9/8/19 1
2.1.4 Develop Project Budget 9/7/19 9/9/19 2
2.2 Develop Project Control Plan
2.2.1 Develop Communication Plan 9/25/19 9/26/19 1
2.2.2 Develop Quality Management Plan 9/27/19 9/28/19 1
2.3 Finalize Project Plan and Gain Approvals
3 Execute and Control Project
3.1 Design Framework
3.1.1 Define framework stages and activities 9/29/19 9/30/19 1
3.1.2 Design framework content formats 10/1/19 10/3/19 2
3.1.3 Design web framework delivery tool 10/3/19 10/4/19 1
3.2 Build the Framework
3.2.1 Write the framework content 10/5/19 10/6/19 1
3.2.2 Review framework content for quality 10/7/19 10/9/19 2
3.2.3 Build web tool prototype 10/9/19 10/10/19 1
3.3 Test the Framework
3.3.1 Test usability of web tool 10/11/19 10/13/19 2
3.3.2 Test usability of content 10/13/19 10/15/19 2
3.3.3 Adjust framework based on user feedback 10/15/19 10/16/19 1
3.4 Implement Framework
3.4.1 Move framework to production environment 10/17/19 10/18/19 1
3.4.2 Announce availability of framework 10/19/19 10/21/19 2
4 Close the Project
4.1 Conduct Post-Project Review 10/21/19 10/23/19 2
4.2 Celebrate 10/23/19 10/24/19 1
Start Date Define Scope Define Requirements Identify High-Level Roles Develop High-Level Budget Identify High-Level Control Strategies Draft Charter and Gain Approvals Consolidate and Publish Project Charter Hold Review Meeting Revise Project charter Gain approvals Plan Project Develop Work Plan Develop Work Breakdown Structure Develop Project Staffing Plan Develop Project Schedule Develop Project Budget Develop Project Co ntrol Plan Develop Communication Plan Develop Quality Management Plan Finalize Project Plan and Gain Approvals Execute and Control Project Design Framework Define framework stages and activities Design framework content formats Design web framework delivery tool Build the Framework Write the framework content Review framework content for quality Build web tool prototype Test the Framework Test usability of web tool Test usability of content Adjust framework based on user feedback Implement Framework Move framework to production environment Announce availability of framework Close the Project Conduct Post-Project Review Celebrate 43702 43704 43706 43709 43711 43713 43715 43717 43719 43711 43712 43713 43715 43715 43733 43735 43737 43739 43741 43743 43745 43747 43749 43751 43753 43755 43757 43759 43761 Duration Define Scope Define Requirements Identify High-Level Roles Develop High-Level Budget Identify High-Level Control Strategies Draft Charter and Gain Approvals Consolidate and Publish Project Charter Hold Review Meeting Revise Project charter Gain approvals Plan Project Develop Work Plan Develop Work Breakdown Structure Develop Project Staffing Plan Develop Project Schedule Develop Project Budget Develop Project Control Plan Develop Communication Plan Develop Quality Management Plan Finalize Project Plan and Gain Approvals Execute and Control Project Design Framework Define framework stages and activities Design framework content formats Design web framework delivery tool Build the Framework Write the framework content Review framework content for quality Build web tool prototype Test the Framework Test usability of web tool Test usability of content Adjust framework based on user feedback Implement Framework Move framework to production environment Announce availability of framework Close the Project Conduct Post-Project Review Celebrate 2 2 2 2 1 2 1 1 1 1 1 2 1 2 1 1 1 2 1 1 2 1 2 2 1 1 2 2 1

WBS

WORK BREAKDOWN STRUCTURE
Consolidate and Publish Charter
Hold Review Meeting
Revise Project Charter
Gain Approvals

VOIP Phone System

Initiate Project

Develop Project Charter

Plan Project

Develop Work Plan

Develop Project Control Plan

Finalize Project Plan and Gain Approvals

Develop Work Breakdown Structure

Develop Project Staffing Plan

Develop Project Schedule

Develop Project Budget

Develop Quality Management Plan

Define Scope

Define Requirements

Define High-Level Roles

Define High-Level Budget

Identify High-Level Control Strategies

Finalize Charter

Develop Communication Plan

Execute and Control Project

Design Content formats

Build the Framework

Test the Framework

Implement the Framework

Close the Project

Design the Framework

Define stages and activities

Design web Delivery Tool

Write the content

Review content for quality

Build web tool prototype

Test web tool usability

Test content usability

Adjust tool and content based on feedback

Move web tool to production environment

Announce Tool availability

Conduct post project review

Celebrate