Project Schedule
| Project Schedule | |||||
| Project Management Improvement Project – Phase 1 | Start Date | Finish Date | Duration | ||
| 1 | Initiate Project | ||||
| 1.1 | Develop Project Charter | ||||
| 1.1.1 | Define Scope | 8/25/19 | 8/27/19 | 2 | |
| 1.1.2 | Define Requirements | 8/27/19 | 8/29/19 | 2 | |
| 1.1.3 | Identify High-Level Roles | 8/29/19 | 8/31/19 | 2 | |
| 1.1.4 | Develop High-Level Budget | 9/1/19 | 9/3/19 | 2 | |
| 1.1.5 | Identify High-Level Control Strategies | 9/3/19 | 9/4/19 | 1 | |
| 1.1.6 | Draft Charter and Gain Approvals | 9/5/19 | 9/7/19 | 2 | |
| 1.1.6.1 | Consolidate and Publish Project Charter | 9/7/19 | 9/8/19 | 1 | |
| 1.1.6.2 | Hold Review Meeting | 9/9/19 | 9/10/19 | 1 | |
| 1.1.6.3 | Revise Project charter | 9/11/19 | 9/12/19 | 1 | |
| 1.1.6.4 | Gain approvals | 9/3/19 | 9/4/19 | 1 | |
| 2 | Plan Project | ||||
| 2.1 | Develop Work Plan | ||||
| 2.1.1 | Develop Work Breakdown Structure | 9/4/19 | 9/5/19 | 1 | |
| 2.1.2 | Develop Project Staffing Plan | 9/5/19 | 9/7/19 | 2 | |
| 2.1.3 | Develop Project Schedule | 9/7/19 | 9/8/19 | 1 | |
| 2.1.4 | Develop Project Budget | 9/7/19 | 9/9/19 | 2 | |
| 2.2 | Develop Project Control Plan | ||||
| 2.2.1 | Develop Communication Plan | 9/25/19 | 9/26/19 | 1 | |
| 2.2.2 | Develop Quality Management Plan | 9/27/19 | 9/28/19 | 1 | |
| 2.3 | Finalize Project Plan and Gain Approvals | ||||
| 3 | Execute and Control Project | ||||
| 3.1 | Design Framework | ||||
| 3.1.1 | Define framework stages and activities | 9/29/19 | 9/30/19 | 1 | |
| 3.1.2 | Design framework content formats | 10/1/19 | 10/3/19 | 2 | |
| 3.1.3 | Design web framework delivery tool | 10/3/19 | 10/4/19 | 1 | |
| 3.2 | Build the Framework | ||||
| 3.2.1 | Write the framework content | 10/5/19 | 10/6/19 | 1 | |
| 3.2.2 | Review framework content for quality | 10/7/19 | 10/9/19 | 2 | |
| 3.2.3 | Build web tool prototype | 10/9/19 | 10/10/19 | 1 | |
| 3.3 | Test the Framework | ||||
| 3.3.1 | Test usability of web tool | 10/11/19 | 10/13/19 | 2 | |
| 3.3.2 | Test usability of content | 10/13/19 | 10/15/19 | 2 | |
| 3.3.3 | Adjust framework based on user feedback | 10/15/19 | 10/16/19 | 1 | |
| 3.4 | Implement Framework | ||||
| 3.4.1 | Move framework to production environment | 10/17/19 | 10/18/19 | 1 | |
| 3.4.2 | Announce availability of framework | 10/19/19 | 10/21/19 | 2 | |
| 4 | Close the Project | ||||
| 4.1 | Conduct Post-Project Review | 10/21/19 | 10/23/19 | 2 | |
| 4.2 | Celebrate | 10/23/19 | 10/24/19 | 1 |
WBS
| WORK BREAKDOWN STRUCTURE | ||
| Consolidate and Publish Charter | ||
| Hold Review Meeting | ||
| Revise Project Charter | ||
| Gain Approvals |
VOIP Phone System
Initiate Project
Develop Project Charter
Plan Project
Develop Work Plan
Develop Project Control Plan
Finalize Project Plan and Gain Approvals
Develop Work Breakdown Structure
Develop Project Staffing Plan
Develop Project Schedule
Develop Project Budget
Develop Quality Management Plan
Define Scope
Define Requirements
Define High-Level Roles
Define High-Level Budget
Identify High-Level Control Strategies
Finalize Charter
Develop Communication Plan
Execute and Control Project
Design Content formats
Build the Framework
Test the Framework
Implement the Framework
Close the Project
Design the Framework
Define stages and activities
Design web Delivery Tool
Write the content
Review content for quality
Build web tool prototype
Test web tool usability
Test content usability
Adjust tool and content based on feedback
Move web tool to production environment
Announce Tool availability
Conduct post project review
Celebrate