answer the survey Quations .short 3 answers
Solutions to Practice Problems—Project Management
3.
Activity Slack (weeks)
1 0
2 1
3 0
4 10
5 1
6 0
7 9
8 0
9 11
Paths: 1 → 3 → 7
4 + 8 + 2 = 14
1 → 3 → 6 → 8
4 + 8 + 5 + 6 = 23*
1 → 4 → 8
4 + 3 + 6 = 13
2 → 5 → 8
7 + 9 + 6 = 22
2 → 9
7 + 5 = 12
9.
Activity Time ES EF LS LF Slack
1 8 0 8 4 12 4
2 12 0 12 0 12 0
3 3 0 3 9 12 9
4 9 12 21 12 21 0
5 3 3 6 18 21 15
6 2 3 5 19 21 16
7 12 21 33 40 52 19
8 7 21 28 46 53 25
9 30 21 51 23 53 2
10 21 21 42 21 42 0
11 20 33 53 52 72 19
12 5 51 56 53 58 2
13 16 42 58 42 58 0
14 17 58 75 58 75 0
15 5 58 63 70 75 12
16 6 53 59 72 78 19
17 3 75 78 75 78 0
Critical path = 2 − 4 − 10 − 13 − 14 − 17
Project completion time = 78 wk.
Activity
Time
ES
EF
LS
LF
Slack
Standard
Deviation
Project 23 1.70
a 3 0 3 0 3 0 0.667
b 3.167 0 3.167 7.667 10.833 7.667 0.5
c 4.167 0 4.167 6.667 10.833 6.667 0.833
d 2.833 3 5.833 3 5.833 0 0.5
e 5 5.833 10.833 5.8333 10.833 0 1
f 1.833 10.833 12.667 15.167 17 4.333 0.167
g 5.833 10.833 16.667 10.833 16.667 0 0.833
h 3.833 12.667 16.5 17 20.833 4.333 0.5
i 4.167 16.667 20.833 16.667 20.833 0 0.5
j 2.167 20.833 23 20.833 23 0 0.5
Critical path = a − d − e − g − i − j = 23 days
What is the probability for the project to be completed in 21 days?
21 23 1.18
1.7
x Z
Z
− =
− = = −
P(x ≤ 21) = .119