Mgt400
Q1. Based on “ Cultural and Heritage City of Kuwait ” Project (Previously submitted in Group Assessment-1) prepare the Communication Plan ; use at least 5 items on the plan related to project.
Q2. Prepare the Responsibility Matrix based on the WBS of “ Cultural and Heritage City of Kuwait ” Project (Previously submitted in Group Assessment-1).
Q3. Answer the following questions with given project network data (40 points).
a) Draw the network diagram (Use the data box for each activity)
b) Calculate Forward, Backward, Slack, CPM duration (weeks)
c) List the all paths and calculate durations for each (show the CPM path)
Q4. Prepare task identification table according to Q3 results (10 points).
Q5. What are the rules for developing a project network diagram? Why those are important? (10 points).
ActivityPredecessorDuration
A-10
B-15
C-9
DA,B17
EC12
FC13
GD, E19
HF, G11
ID,G,H14
ActivityDurationESEFLSLFSlack
A
B
C
D
E
F
G
H
I