Discussion Forum

profileamal89
SEU_MGT530_Module13_PPT_Ch121.pptx

MRP and ERP

Chapter 12

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

You should be able to:

LO 12.1 Describe the conditions under which MRP is most appropriate

LO 12.2 Describe the inputs, outputs, and nature of MRP processing

LO 12.3 Explain how requirements in a master production schedule are translated into material requirements for lower-level items

LO 12.4 Discuss the benefits and requirements of MRP

LO 12.5 Describe some of the difficulties users have encountered with MRP

LO 12.6 Describe MRP II and its benefits

LO 12.7 Explain how an MRP system is useful in capacity requirements planning

LO 12.8 Describe ERP, what it provides, and its hidden costs

Chapter 12: Learning Objectives

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Dependent vs. Independent Demand

LO 12.1

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

MRP

Material requirements planning (MRP):

A computer-based information system that translates master schedule requirements for end items into time-phased requirements for subassemblies, components, and raw materials

The MRP is designed to answer three questions:

What is needed?

How much is needed?

When is it needed?

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Overview of MRP

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Master schedule:

One of three primary inputs in MRP; states which end items are to be produced, when these are needed, and in what quantities

Managers like to plan far enough into the future so they have reasonable estimates of upcoming demands

The master schedule should cover a period that is at least equivalent to the cumulative lead time

Cumulative lead time

The sum of the lead times that sequential phases of a process require, from ordering of parts or raw materials to completion of the final assembly

MRP Inputs: Master Schedule

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Cumulative Lead Time

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

MRP Inputs: Bill of Materials

Bill of Materials (BOM)

A listing of all of the assemblies, subassemblies, parts, and raw materials needed to produce one unit of a product

Product structure tree

A visual depiction of the requirements in a bill of materials, where all components are listed by levels

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Assembly Diagram and Product Structure Tree

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Low-level coding

Restructuring the bill of materials so that multiple occurrences of a component all coincide with the lowest level at which the component occurs

Low-Level Coding

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

X

B(2)

D(3)

E

C

E(2)

Level 0

Level 1

Level 2

F(2)

Level 3

E(4)

Inventory records

Includes information on the status of each item by time period, called time buckets

Information about

Gross requirements

Scheduled receipts

Expected amount on hand

Other details for each item such as

Supplier

Lead time

Lot size policy

Changes due to stock receipts and withdrawals

Canceled orders and similar events

MRP Inputs: Inventory Records

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Assembly Time Chart

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Primary Outputs

Planned orders

A schedule indicating the amount and timing of future orders

Order releases

Authorizing the execution of planned orders

Changes

Revisions of the dates or quantities, or the cancellation of orders

MRP Outputs: Primary

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Secondary Outputs

Performance-control reports

Evaluation of system operation, including deviations from plans and cost information

e.g., missed deliveries and stockouts

Planning reports

Data useful for assessing future material requirements

e.g., purchase commitments

Exception reports

Data on any major discrepancies encountered

e.g., late and overdue orders, excessive scrap rates, requirements for nonexistent parts

MRP Outputs: Secondary

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

MRP processing takes the end item requirements specified by the master schedule and “explodes” them into time-phased requirements for assemblies, parts, and raw materials offset by lead times

MRP Processing

LO 12.3

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

MRP Record

Gross requirements

Total expected demand

Scheduled receipts

Open orders scheduled to arrive

Projected Available

Expected inventory on hand at the beginning of each time period

Week Number 1 2 3 4 5 6
Gross Requirements
Scheduled Receipts
Projected on hand
Net requirements
Planned-order-receipt
Planned-order release

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

MRP Record (cont.)

Week Number 1 2 3 4 5 6
Gross Requirements
Scheduled Receipts
Projected on hand
Net requirements
Planned-order-receipt
Planned-order release

Net requirements

Actual amount needed in each time period

Planned-order receipts

Quantity expected to received at the beginning of the period offset by lead time

Planned-order releases

Planned amount to order in each time period

LO 12.2

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

MRP: Development

The MRP is based on the product structure tree diagram

Requirements are determined level by level, beginning with the end item and working down the tree

The timing and quantity of each “parent” becomes the basis for determining the timing and quantity of the “children” items directly below it

The “children” items then become the “parent” items for the next level, and so on

LO 12.3

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Example MRP

LO 12.3

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Shutter

Frames (2)

Wood sections (4)

Example MRP (cont.)

LO 12.3

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Pegging

The process of identifying the parent items that have generated a given set of material requirements for an item

Using the MRP

LO 12.3

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

An MRP is not a static document

As time passes

Some orders get completed

Other orders are nearing completion

New orders will have been entered

Existing orders will have been altered

Quantity changes

Delays

Missed deliveries

Updating the System

LO 12.3

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Updating the System (cont.)

Two basic systems

Regenerative system

Approach that updates MRP records periodically

Essentially a batch system that compiles all changes that occur within the time interval and periodically updates the system

A revised production plan is developed in the same way the original plan was developed

Net-change system

Approach that updates MRP records continuously

The production plan is modified to reflect changes as they occur

Only the changes are exploded through the system

LO 12.3

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Other MRP Considerations: Safety Stock

Safety Stock

Theoretically, MRP systems should not require safety stock

Variability may necessitate the strategic use of safety stock

A bottleneck process or one with varying scrap rates may cause shortages in downstream operations

Shortages may occur if orders are late or fabrication or assembly times are longer than expected

When lead times are variable, the concept of safety time is often used

Safety time

Scheduling orders for arrival or completions sufficiently ahead of their need so that the probability of shortage is eliminated or significantly reduced

LO 12.3

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Other MRP Considerations: Lot Sizing Rules

Lot-for-Lot (L4L) ordering

The order or run size is set equal to the demand for that period

Minimizes investment in inventory

It results in variable order quantities

A new setup is required for each run

Economic Order Quantity (EOQ)

Can lead to minimum costs if usage of item is fairly uniform

This may be the case for some lower-level items that are common to different ‘parents’

Less appropriate for ‘lumpy demand’ items because inventory remnants often result

Fixed Period Ordering

Provides coverage for some predetermined number of periods

LO 12.3

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Enables managers to easily

Determine the quantities of each component for a given order size

To know when to release orders for each component

To be alerted when items need attention

Additional benefits

Low levels of in-process inventories

The ability to track material requirements

The ability to evaluate capacity requirements

A means of allocating production time

The ability to easily determine inventory usage via backflushing

Exploding an end item’s BOM to determine the quantities of the components that were used to make the item

MRP Benefits

LO 12.4

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

To implement an effective MRP system requires:

A computer and the necessary software to handle computations and maintain records

Accurate and up-to-date

Master schedules

Bills of materials

Inventory records

Integrity of data files

MRP Requirements

LO 12.4

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Consequence of inaccurate data

Missing parts

Ordering incorrect numbers of items

Inability to stay on schedule

Other problems

Assumptions of constant lead times

Products being produced differently from the BOM

Failure to alter a BOM when customizing a product

Inaccurate forecasts

MRP Difficulties

LO 12.5

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

MRP II

Manufacturing resources planning (MRP II)

Expanded approach to production resource planning, involving other areas of the firm in the planning process and enabling capacity requirements planning

Most MRP II systems have the capability of performing simulation to answer a variety of “what if” questions so they can gain a better appreciation of available options and their consequences

LO 12.6

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

MRP II: Overview

LO 12.6

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Closed Loop MRP

When MRP II systems began to include feedback loops, they were referred to as Closed Loop MRP

Closed Loop MRP

Systems evaluate a proposed material plan relative to available capacity

If a proposed plan is not feasible, it must be revised

This evaluation is referred to as capacity requirements planning

LO 12.6

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Capacity requirements planning (CRP)

The process of determining short-range capacity requirements.

Inputs to capacity requirement planning

Planned-order releases for the MRP

Current shop loading

Routing information

Job time

Key outputs

Load reports for each work center

Capacity Requirements Planning

LO 12.7

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Using MRP to Assist in CRP

LO 12.7

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Load Reports

Load reports

Department or work center reports that compare known and expected future capacity requirements with projected capacity availability

LO 12.7

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Enterprise Resource Planning

Enterprise resource planning (ERP)

ERP was the next step in an evolution that began with MRP and evolved into MRPII

ERP, like MRP II, typically has an MRP core

ERP provides a system to capture and make data available in real time to decision makers and other users throughout an organization

ERP systems are composed of a collection of integrated modules

LO 12.8

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

Overview of ERP Software Modules

Module Brief Description
Accounting/Finance A central component of most ERP systems. It provides a range of financial reports, including general ledger, accounts payable, accounts receivable, payroll, income statements, ad balance sheets
Marketing Supports lead generation, target marketing, direct mail, and sales
Human Resources Maintains a complete data base of employee information such as date of hire, salary, contact information, performance evaluations, and other pertinent information
Purchasing Facilitates vendor selection, price negotiation, making purchasing decisions, and bill payment
Production Planning Integrates information on forecasts, orders, production capacity, on-hand inventory quantities, bills of material, work in process, schedules, and production lead times
Inventory Management Identifies inventory requirements, inventory availability, replenishment rules, and inventory tracking
Distribution Contains information on third-party shippers, shipping and delivery schedules, delivery tracking
Sales Information on orders, invoices, order tracking, and shipping
Supply Chain Management Facilitates supplier and customer management, supply chain visibility, and event management

LO 12.8

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

The ‘big bang’

Companies cast off all of their legacy systems at once and implement a single ERP system across the entire company

The most ambitious and difficult implementation approach

Franchising strategy

Independent ERP systems are installed in each business unit of the enterprise while linking common processes across the enterprise

Suits large or diverse companies that do not share many common processes across business units

Slam dunk

ERP dictates the process design where the focus is on a few key processes

More appropriate for smaller companies expecting to grow into ERP

ERP Project Organization

LO 12.8

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›

ERP Considerations

How can ERP improve a company’s business performance?

How long will an ERP implementation project take?

How will ERP affect current business processes?

What is the ERP total cost of ownership?

What are the hidden costs of ERP ownership?

LO 12.8

Copyright ©2018 McGraw-Hill Higher Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education

12-‹#›