Scheduling Assignment Submission

What are you required to do:

Using the Sample Project perform the following tasks:

1. Use the List of Activities to develop AON/CPM/Network Diagram for the Sample Project by hand (sketch it on piece of paper).

2. Complete the Critical Path Method (CPM) computations on the diagram developed in Step 1 above to determine the Critical Path, Activity Dates and Total Float for activities

3. Now using Mircosoft Project or Project Libre (if both do not work use Excel) to develop the Network Diagram for the Sample Project (assume project starts on July 1, 2020)

4. Add Resource Information to your schedule using the Resources Needed table provided for the Sample Project

5. Perform Resource Leveling on your Project

What will you Submit:

The following documents can be assembled into a single PDF file and uploaded:

1. Scan the network diagram with the calculations (see step 1 and step 2 above)

2. Print the Gantt Chart from Mircosoft Project or Project Libre (after adding resources in step 4 but without performing Resource Leveling)

3. Print the Gantt Chart from Mircosoft Project or Project Libre (after performing Resource Leveling listed in Step 5 above)

4. One-page conclusions including--project start date and end date; project duration and critical path calculated

Sample Project

We will use a sample project (provided by https://www.open.edu/openlearn/money-business/business-strategy-studies/planning-project/content-section-6.3#fig001-010 (Links to an external site.) ) to complete this assignment. The sample project is designed to print and distribute a directory (who prints a directory anymore!).

List of Activities

Activity

Activity Name

Type

Duration (weeks)

Predecessor

1

Directory Project

Summary Task

2

Funds Secured

Task

0

-

3

Negotiate with other agencies

Task

4

2

4

Form advisory group

Task

4

3

5

Establish data collection plan

Task

6

4

6

Collect data

Task

4

5

7

Write directory text

Task

4

6

8

Identify printer

Task

2

4

9

Agree print contract

Task

2

8

10

Print directory

Task

4

7,9

11

Agree distribution plan

Task

12

4

12

Organise distribution

Task

4

11

13

Distribute directory

Task

2

10,12

Resources Needed

Activity

Activity Name

Resource Name

1

Directory Project

2

Funds Secured

PM

3

Negotiate with other agencies

PM

4

Form advisory group

PM

5

Establish data collection plan

Editor

6

Collect data

Editor

7

Write directory text

Editor

8

Identify printer

Contract Specialist

9

Agree print contract

Contract Specialist

10

Print directory

Printer

11

Agree distribution plan

PM

12

Organise distribution

Editor

13

Distribute directory

PM

Rubric

Scheduling Assignment Rubric

Scheduling Assignment Rubric

Criteria

Ratings

Pts

This criterion is linked to a Learning OutcomeNetwork diagram with the calculations (step 1 and step 2)

5.0 to >4.0 pts

Above expectations

4.0 to >3.0 pts

Meets expectations

3.0 to >0 pts

Below expectations

5.0 pts

This criterion is linked to a Learning OutcomeGantt Chart from Mircosoft Project or Project Libre (step 4)

5.0 to >4.0 pts

Above expectations

4.0 to >3.0 pts

Meets expectations

3.0 to >0 pts

Below expectations

5.0 pts

This criterion is linked to a Learning OutcomeResource leveled gantt Chart from Mircosoft Project or Project Libre (Step 5)

5.0 to >4.0 pts

Above expectations

4.0 to >3.0 pts

Meets expectations

3.0 to >0 pts

Below expectations

5.0 pts

This criterion is linked to a Learning OutcomeOne-page summary

5.0 to >4.0 pts

Above expectations

4.0 to >3.0 pts

Meets expectations

3.0 to >0 pts

Below expectations

5.0 pts

Total Points: 20.0

Previous Next