Management of Construction Processes and Techniques
1/03/2022
1
SARENS NOTHING TOO HEAVY, NOTHING TOO HIGH
STRUCTURE OF THE PRESENTATION
Introduction
1. Who are Sarens?
2. Who am I?
3. Aim of the Presentation.
4. Why do we need cranes?
Lecture 1: Mobile Cranes
1. Types of Mobile Cranes
2. Planning Factors
3. Planning The Operation
4. Consequences of Poor Planning
5. Understanding Lift Plans
INTRODUCTION
2
Lecture 2: Tower Cranes
1. Types of Tower Cranes
2. Tower Crane Components
3. Planning Factors
4. Tower Crane vs. Mobile Crane
Conclusion
1. Aim of the Presentation
2. Additional Resources
1
2
1/03/2022
2
WHO ARE SARENS?
Sarens is an international heavy lift and transport company.
At Sarens, we have the noble mission to be the reference in crane rental services, heavy lifting, and engineered transport for our clients.
To do this, we deploy our 5 unwavering values:
Dedication to Safety
Zeal for Excellence
Love for Tradition
Brilliant Solutions
Global Spirit
INTRODUCTION
3
4
Source: Sarens, 2017
3
4
1/03/2022
3
WE ARE AN INTERNATIONAL COMPANY INTRODUCTION
9 Geographical Regions, 67 Countries, 100 Offices
5
OUR MAIN SECTORS INTRODUCTION
Oil and Gas Mining Infrastructure Offshore & Module Yards
Solar On-Shore and Offshore Wind Forwarding General Industry
Maintenance and Installation Thermal and Nuclear Power Plants
6
5
6
1/03/2022
4
OUR FLEET AND EQUIPMENT
CRANES TRANSPORT SPECIAL EQUIPMENT
Hydraulic Cranes
Lattice Boom Cranes
Heavy Luffing Tower Cranes
Conventional Trailers
Modular Trailers
Self-propelled Modular Trailers
Barges
Gantries
Jacking
Strand Jacks
Twin Barges
Modular Barges
Skidding
INTRODUCTION
7
WHO AM I?
Andrew Cockshoot EngTech TMIET
– Loughborough University Graduate
– Sarens Project Engineer
– Engineering Technician of the Institution of Engineering and Technology
Education:
– Civil Engineering Higher National Degree 2013 - 2016
– Construction Engineering Management BSc 2017 – 2021
Work Experience
– Sir Robert McAlpine, Lift Planning CAD Technician 2012 - 2017
– Sarens UKTS, Project Engineer 2019 - Present
INTRODUCTION
8
7
8
1/03/2022
5
AIM OF THIS PRESENTATION
By the end of this presentation you should be able to:
…understand the different types of cranes.
…identify the components of mobile and tower cranes.
…recognise common constraints inherent in crane operations.
…read and understand crane schemes.
…understand where mobile cranes and tower cranes are the suitable option.
If you have any questions during this presentation, please feel free to ask at any time!
INTRODUCTION
9
THE USE OF CRANES INTRODUCTION
10
Question:
Why do we use cranes?
9
10
1/03/2022
6
THE USE OF CRANES INTRODUCTION
11
Crane provide vertical and horizontal movement to materials / loads.
Cranes enable us to be build bigger and higher structures.
They are an essential part of modern construction.
Their need is further expanding with the increased use of pre-fabrication.
THE FUNDAMENTALS OF MOBILE CRANE PLANNING Lecture 1 of 2
11
12
1/03/2022
7
TYPES OF MOBILE CRANES The Fundamentals of Mobile Crane Planning
TYPES OF MOBILE CRANES TYPES OF MOBILE CRANES
14
Question:
What types of mobile cranes are there?
13
14
1/03/2022
8
TYPES OF MOBILE CRANES
1. All-Terrain Crane
2. Lattice Boom Crawler Crane
3. Telescopic Boom Crawler Crane
4. Self-Erecting Mobile Tower Crane
5. Lattice Boom Truck Crane
6. Telescopic Truck-Mounted Crane
7. Rough Terrain Crane
8. Pick and Carry Crane
TYPES OF MOBILE CRANES
Crane types you are most likely to encounter in the UK.
15
ALL-TERRAIN CRANES
Telescopic main boom.
High level of mobility; able to drive on public roads.
Short mobilisation and set-up time (dependent on configuration).
Versatile due to the wide variety of lifting accessories.
Capacities from 5 to 1,200Te.
Higher capacity all-terrain cranes may need to travel without the boom attached.
TYPES OF MOBILE CRANES
16
15
16
1/03/2022
9
LATTICE BOOM CRAWLER CRANES
Transported by truck and assembled on site.
Suitable for the heaviest of loads.
Boom length can be adjusted by the addition and removal of boom sections – requires an additional support crane to do so.
Can have a relatively compact footprint for the capacities offered.
Can track (travel) with a load.
Capacities range from 50 to 3,200Te.
TYPES OF MOBILE CRANES
17
TELESCOPIC CRAWLER CRANES
Crane on crawlers with telescopic boom.
Combines the advantages of a hydraulic boom with the stability and manoeuvrability of a crawler crane.
Can track while carrying a load.
Capacities range from 16 to 220Te.
Can self-rig or use support cranes for initial set up.
TYPES OF MOBILE CRANES
18
17
18
1/03/2022
10
LATTICE BOOM TRUCK CRANE
Road-going substructure consists of the slewing ring and a partial superstructure and derrick mast.
The rest of the crane is delivered by additional truck transport
Requires support cranes for rigging.
Combines the mobility of all-terrain cranes with the capacity range of crawler cranes.
Capacities range from 130 to 1,200Te.
TYPES OF MOBILE CRANES
19
SELF-ERECTING MOBILE TOWER CRANES
A tower crane that can drive on public roads.
Self-erecting, can erect itself in approximately 15mins.
Taxi crane, no additional support vehicles are required.
Best-suited for when reach is more important than capacity.
Can be operated remotely or by a height-adjustable operating cab.
Capacities range from 5 to 18Te.
TYPES OF MOBILE CRANES
20
19
20
1/03/2022
11
TELESCOPIC TRUCK-MOUNTED CRANES
Telescopic boom superstructure fitted to a conventional truck chassis.
Efficient road transport and fast mobilisation makes these perfect taxi cranes.
Designed for frequent and long distance travel.
Capacities range from 30 to 80Te
TYPES OF MOBILE CRANES
21
ROUGH TERRAIN CRANES
Designed to operate in the roughest conditions.
Compact and versatile.
Excellent gradeability.
Can drive with small suspended loads.
Capacities range from 12 to 150Te.
TYPES OF MOBILE CRANES
22
21
22
1/03/2022
12
PICK AND CARRY CRANES
Designed to be able to pick up and travel with a suspended load.
Work ready, no outriggers are required.
Typically used in industrial contexts rather than construction projects.
Capacities range from 5 to 40Te.
TYPES OF MOBILE CRANES
23
PLANNING FACTORS The Fundamentals of Mobile Crane Planning
23
24
1/03/2022
13
HEAVY LIFT PLANNING FUNCTIONAL MODEL PLANNING FACTORS
25
(Adapted from Hornaday et al., 1993)
INPUTS
Inputs relate to the physical aspects of the operation including the crane, load and site.
Inputs can be categorised into:
– Crane data sourced from CAD models, manufacturer manuals and websites.
– Load data is defined by manufacturer shop drawings.
– Site details are described by architectural and engineering drawings.
PLANNING FACTORS
26
(Adapted from Hornaday et al., 1993)
25
26
1/03/2022
14
INPUTS
Crane Data:
– Physical dimensions.
– Crane capacities.
– Cost.
– Availability.
– Reliability.
– Service record.
PLANNING FACTORS
27
(Adapted from Hornaday et al., 1993)
INPUTS
Load Data:
– Dimensions and shape.
– Weight.
– Centre of gravity location.
– Fabrication and delivery schedule.
└ these establish a work window.
PLANNING FACTORS
28
(Adapted from Hornaday et al., 1993)
27
28
1/03/2022
15
INPUTS
Site Data:
– Spatial layout and dimensions.
– Ground conditions.
– Changes in onsite structures over time:
└ Permanent structures.
└ Mobile structures (scaffold etc.).
PLANNING FACTORS
29
(Adapted from Hornaday et al., 1993)
CONTROLS
Controls relate to aspects of the operation that constrain the planning scope and dictates how the operation can be undertaken.
Controls can be categorised into:
– Spatial constraints defining the space for the operation.
– Structural constraints strength of the crane, site and load.
– Schedule constraints describes when the project needs to be done and the variance of the spatial and structural constraints.
PLANNING FACTORS
30
(Adapted from Hornaday et al., 1993)
29
30
1/03/2022
16
CONTROLS
Spatial Constraints
– Volume of work.
– Access / egress from site.
– Space for the crane.
– Space for the load to move (lift path).
– Pinch points.
└ Minimum clearance defined to accommodate for boom deflection, settlement and on-site inaccuracies in positioning.
PLANNING FACTORS
31
(Adapted from Hornaday et al., 1993)
CONTROLS
Structural Constraints
– Determine the required strength of:
└ The crane
└ The site
└ The load
– The load’s ability to accommodate the forces imparted into it during the lift operation is the client’s responsibility.
– Client should calculate and define the ground’s allowable bearing pressures.
PLANNING FACTORS
32
(Adapted from Hornaday et al., 1993)
31
32
1/03/2022
17
CONTROLS
Schedule Constraints
– Become more powerful as the operation date gets closer.
– Other construction operations may be taking place at the same time.
– Interfering structures may be constructed before or after the operation.
– Critical activities may need completing before the lift can be undertaken (foundations etc.).
PLANNING FACTORS
33
(Adapted from Hornaday et al., 1993)
MECHANISMS
Mechanisms are the factors that bring a lift plan into existence; i.e., the exchange of information.
Mechanisms can be categorised into:
– Constructor provides information about the site and / or load to the lift planner.
– Engineering Consultants provides information as per their role to the lift planner (i.e. ground investigation studies etc.).
– The Owner has final ownership of the project information, and therefore must ensure sufficient information is provided to the lift planner to enable them to safely plan the operation.
The final execution of the lift plan is the responsibility of the Lift Planner.
PLANNING FACTORS
34
(Adapted from Hornaday et al., 1993)
33
34
1/03/2022
18
OUTPUTS
The interaction of the inputs, controls and mechanisms will define the outputs of the planning activity.
Outputs can change as a reaction to a change in the inputs, controls and mechanisms.
Outputs can exist in three forms:
– Preliminary: to confirm the feasibility of the operation.
– Detailed: to represent the optimisation of the preliminary output.
– Final: the final scheme for execution.
The output will be in the form of a single or a series of technical drawings detailing the operation with associated risk and method statements (RAMS).
PLANNING FACTORS
35
(Adapted from Hornaday et al., 1993)
HEAVY LIFT FUNCTIONAL MODEL
A simple model to understand the interaction of factors in lift planning.
Was originally developed to describe lifts in industrial settings (oil and gas) so not all outputs need to be considered for every lift operation.
Overlap between controls, inputs and mechanisms since they are not undertaken in isolation.
The interaction of controls, inputs and mechanisms defines the operation, its feasibility and its optimum form.
36
(Adapted from Hornaday et al., 1993)
PLANNING FACTORS
35
36
1/03/2022
19
37
TYPES OF MOBILE CRANES TYPES OF MOBILE CRANES
38
Question:
Can you identify what controls were in the previous video?
37
38
1/03/2022
20
PLANNING THE OPERATION The Fundamentals of Mobile Crane Planning
HEAVY LIFT PLANNING STEPS
STEP-1: Determine load radius
STEP-2: Determine minimum hook height (minimum boom length) └ Min. Hook Height = Elevation + Clearance + Load Height + Tackle Height + Chandelier Height
STEP-3: Define an approximate boom length requirement
STEP-4 Determine total load └ Total Load = Net Load + Tackle + Hook block
STEP-5: Propose an initial crane.
STEP-6: Check proposed crane’s capacity.
STEP-7: Calculate outrigger loads
STEP-8: Optimise the preliminary proposal.
PLANNING THE OPERATION
40
39
40
1/03/2022
21
STEP-1: DETERMINE LOAD RADIUS
What is the maximum radius you need to reach?
Where can the crane be cited in relation to the load?
– Available space on site.
– Current plant onsite.
– Storage areas on site.
– Sufficient bearing capacities.
– Voids / trenches.
– Proximity to structures.
PLANNING THE OPERATION
41
STEP-2: DETERMINE MIN. HOOK HEIGHT
Elevation + Clearance + Load Height + Tackle Height + Chandelier Height └ Elevation = difference between the level of the
crane and the load (-’ve if load is lower than the crane).
└ Clearance = allowance for clearance to obstructions.
└ Chandelier height = minimum distance between the head sheave and the hook block.
PLANNING THE OPERATION
42
41
42
1/03/2022
22
STEP-3: DETERMINE HOOK HEIGHT
Using Step 1 and 2 an approximate boom length can be calculated.
C = (𝐴 +𝐵 )
Where:
(A) = Min. Hook Height
(B) = Load Radius
This will give an approximate boom length.
PLANNING THE OPERATION
43
(C)
(B)
(A)
Example: C = ( 3900 + 10450 + 11120) + 12000 C = 28,155mm (~28m Boom)
STEP-4: DETERMINE TOTAL LOAD WEIGHT
Net Load + Tackle + Hook Block
Everything underneath the sheave needs to be considered in the load weight.
PLANNING THE OPERATION
44
43
44
1/03/2022
23
STEP-5: PROPOSE AN INITIAL CRANE
With the results of stages 1-4 in mind a preliminary crane can be defined.
A lift weight, lift radius and approximate boom length is the minimum information you need to define a crane.
Online crane calculators, specialist lift planning software (Liebherr Crane Planner 2.0) or engineering experience can be used to speed up the process.
Trial and error is also an option.
45
PLANNING THE OPERATION
STEP-5: PROPOSE AN INITIAL CRANE
Crane choice can be dictated by a number of external factors: – Availability: is the crane you need
available, do you need to substitute for a larger crane?
– Cost: is the crane within the clients budget?
– Reliability: is the proposed crane reliable, subject to regular breakdowns?
– Reputation: is the company supplying the crane you want reliable? Is it available from other crane rental companies with a better reputation?
46
PLANNING THE OPERATION
45
46
1/03/2022
24
STEP-6: CHECK PROPOSED CRANE’S CAPACITY
First, consult crane capacity charts.
Use manufacturer provided capacity charts.
Maximum utilisation should ideally not exceed 90% └ Maximum utilisation = ( lift weight ÷ ( capacity –
deductions ) ) x 100
└ Generally work to a 10% safety factor.
The glossy brochures provided by crane manufacturers do not provide a complete representation of a crane’s capacities.
PLANNING THE OPERATION
47
STEP-6: CHECK PROPOSED CRANE’S CAPACITY
The glossy brochure only considers best case capacity at a defined radius for a boom length. However, each boom length has multiple hydraulic configurations with different capacities.
41.3m [00, 92, 92, 92, 92] └ 17.4Te at 7.0m
41.3m [46, 46, 92, 92, 92] └ 17.9Te at 7.0m
41.3m [46, 92, 92, 92, 46] └ 20.9Te at 7.0m
41.3m [92, 92, 92, 46, 46] └ 22.4Te at 7.0m
PLANNING THE OPERATION
48
47
48
1/03/2022
25
STEP-6: CHECK PROPOSED CRANE’S CAPACITY
It is very common for crane capacities to be subject to deductions.
– External factors (site constraints).
– Internal factors (crane specific).
Neither the glossy brochure or the manufacturers literature will include deductions in their capacities; the latter will define what the deductions should be.
PLANNING THE OPERATION
49
STEP-6: CHECK PROPOSED CRANE’S CAPACITY
Internal sources affecting crane capacities: – Lifting with the fixed fly stowed on the main
boom.
– Lifting with the TY-frame stowed on the main boom.
Exact capacity deductions will depend on length of main boom and the crane model.
Components can be removed to negate the deductions but tends to be avoided if possible.
PLANNING THE OPERATION
50
49
50
1/03/2022
26
STEP-6: CHECK PROPOSED CRANE’S CAPACITY
External factors affecting crane capacities:
– Operating in sensitive areas (i.e. nuclear) where higher safety factors are required.
– Operating in proximity to Network Rail assets (in accordance with CPA-1801).
– Client request.
Common deduct is 25% of rated capacity.
PLANNING THE OPERATION
51
STEP-7: CALCULATE OUTRIGGER LOADS
The crane will impart load into the ground via the outriggers.
This load from the outriggers is dictated by the lift weight, lift radius and the configuration of the crane.
The ground must be checked to ensure it can accommodate the anticipated loads.
Outrigger loads can be distributed through the use of outrigger mats to reduce the bearing pressures.
PLANNING THE OPERATION
52
51
52
1/03/2022
27
STEP-8: OPTIMISE THE PRELIMINARY PROPOSAL
Go back through the operation, can the crane be made smaller from the current proposal?
What can be done to make the crane smaller?
What risks can be avoided?
Reduced counterweight requirements or the use of a main boom only configuration can reduce the required transport.
Check the crane plan against all new information
53
PLANNING THE OPERATION
CONSQUENCES OF POOR PLANNING The Fundamentals of Mobile Crane Planning
53
54
1/03/2022
28
MODES OF FAILURE
Crane accidents can be categorised as either:
– Structural failure
– Stability failure
A multitude of factors can cause a structural or stability failure.
Commonly, a crane accident can be linked to insufficient or incorrect planning.
55
CONSEQUENCES OF POOR PLANNING
STABILITY AND STRUCTURAL FAILURE
Stability or structural failure.
– Exceeding the crane’s rated capacity.
– Pulling or dragging a load.
– Excessive swinging the load due to improper control of the crane
– Operating in excessive wind conditions.
– Lifting submerged loads.
Failure by structural failure can also be a result of poor maintenance.
56
CONSEQUENCES OF POOR PLANNING
55
56
1/03/2022
29
FAILURE DUE TO GROUND CONDITIONS
Insufficient distance from trenches or underlying voids (basements etc.).
The ground does not have sufficient bearing capacity to carry the weight / loading of the crane.
Ground is not level or within the acceptable incline that the crane is rated for.
57
CONSEQUENCES OF POOR PLANNING
FAILURE DUE TO CLASHES
Collision with street furniture.
Collision with permeant or mobile structures.
Contact with overhead services.
Contact with a leading edge.
58
CONSEQUENCES OF POOR PLANNING
57
58
1/03/2022
30
OTHER FAILURES
Not all failures of planning lead to an accident / incident.
Other outcomes can include:
– Failure of the crane to fit on-site (access / egress).
– Clashes between the crane and ground-based obstructions (street furniture etc.)
– Becoming jib bound.
– Crane becomes unavailable.
59
CONSEQUENCES OF POOR PLANNING
UNDERSTANDING LIFT PLANS The Fundamentals of Mobile Crane Planning
59
60
1/03/2022
31
WHAT IS A LIFT PLAN?
61
UNDERSTANDING LIFT PLANS
A document that collates all information about a proposed lift into a single (or series) of drawings.
It is a living document, even during the operation in some cases.
A ‘simulation’ of the proposed lift to identify areas of concern / risk.
A means of communicating a visual representation of the operation to the client and operational team.
INFORMATION REQUIRED FOR A LIFT PLAN
A lift plan requires the following: – Information / layout of the site.
– Sections / elevations of any obstruction / surrounding structures.
– Local ground levels.
– Local underlying services.
– Local street furniture
– Access / egress route restrictions.
– Load weight and load dimensions.
– Lifting points on the load.
– Location of site obstructions (storage areas, trenches, scaffolding etc.)
– Pickup and laydown positions of the load.
– Available resources on site (existing matting etc.)
62
Preferably in a useable CAD format if available.
UNDERSTANDING LIFT PLANS
61
62
1/03/2022
32
CONSTITUENT PARTS OF A LIFT PLAN
A lift plan details the following: – Crane manufacturer and model
– Crane configuration
– Lift weight
– Deductions considered.
– Lift radius
– Crane capacities (capacity utilisation)
– Hook block type
– Crane mat requirements
– Outrigger loads (bearing pressures)
– Plan and Section
– Relevant warnings / risks identified.
63
UNDERSTANDING LIFT PLANS
EXAMPLE LIFT PLAN UNDERSTANDING LIFT PLANS
63
64
1/03/2022
33
THE FUNDAMENTALS OF TOWER CRANE PLANNING Lecture 2 of 2
TYPES OF TOWER CRANES The Fundamentals of Tower Crane Planning
65
66
1/03/2022
34
TYPES OF TOWER CRANES TYPES OF TOWER CRANES
67
Question:
What types of tower cranes are there?
TYPES OF TOWER CRANES
Tower cranes are usually categorised by what type of jib they utilise:
1. Saddle Jib (Hammerhead)
2. Luffing Jib
3. Topless (Flat Top)
4. Articulated
5. Self-Erecting
TYPES OF TOWER CRANES
68
67
68
1/03/2022
35
SADDLE JIB (HAMMERHEAD) TOWER CRANES
Horizontal jib that can be erected in several lengths, commonly 30 – 70m
The trolley travels along the jib to change the lifting radius (aka. racking).
Suitable where oversailing issues are not a critical factor.
Interaction between other cranes need to be carefully planned as they affect a large airspace.
Oversailing a major concern with this type of tower crane.
TYPES OF TOWER CRANES
69
LUFFING JIB TOWER CRANES
The jib can be luffed up and down to reduce or increase the lifting radius.
Larger minimum radius than flat-jib alternatives.
Can utilise several jib lengths, commonly 30 – 60m
When left out-of-service the crane can reduce its radius to minimise oversailing issues.
Reduced out of service also enables closer spacing of tower cranes.
Ideal for congested sites.
TYPES OF TOWER CRANES
70
69
70
1/03/2022
36
TOPLESS (FLAT TOP) TOWER CRANES
Similar in operation to a Saddle Jib tower crane.
No A-frame and associated tie-bars for neighbouring cranes to clear, resulting in overall lower tower heights for all site cranes.
Ideal for congested sites.
Jib can be installed piecemeal instead of needing to be installed as fully constructed jib.
Typically offer lower capacities than Saddle Jib alternatives.
TYPES OF TOWER CRANES
71
ARTICULATED TOWER CRANES
Specially designed for inner-city sites where air space restrictions are the driving factor.
The out-of-service radius is the smallest out of all available tower crane types.
Minimised tail-swing.
Capacities are more limited, maximum of ~8.0Te.
Minimised base loadings and component weights.
– Possible to fix these cranes to slipform rigs.
TYPES OF TOWER CRANES
72
71
72
1/03/2022
37
SELF ERECTING TOWER CRANES
Smaller, lower capacity alternatives to traditional tower cranes best suited for smaller projects.
Transported to site as a single unit plus counterweight and able to erect itself.
Minimal foundation requirements.
Can be easily relocated around site as needed.
Horizontal jib will require detailed planning for oversailing and interface with other cranes on site.
TYPES OF TOWER CRANES
73
TOWER CRANE COMPONENTS The Fundamentals of Tower Crane Planning
73
74
1/03/2022
38
COMMON TOWER CRANE COMPONENTS TOWER CRANE COMPONENTS
75
Mast
Base and Foundation
Counter jib
Trolley Slewing Ring
Jib
A-Frame
Operators Cab
Base and Foundation
Mast
Slewing Ring Operators Cab
Jib
Counter jib
A-Frame
Saddle Jib Tower Crane Luffing Jib Tower Crane
TOWER CRANE FOUNDATIONS
Tower cranes can have a variety of base types, each type will affect:
– Free-standing height
– Spatial implications of the base.
Common foundation types are:
– Cast-in Concrete foundations
– Ballasted Bases
– Grillages
76
TOWER CRANE COMPONENTS
75
76
1/03/2022
39
TOWER CRANE FOUNDATIONS
Tower crane bases are the main factor affecting stability.
Bases need to be able to effectively resist:
– Vertical Reactions (V).
– Horizontal Forces (Hx, Hy).
– Moments (My, Mx).
– Torque (Mt).
77
TOWER CRANE COMPONENTS
TOWER CRANE FOUNDATIONS
Cast-In Concrete Bases
– Specific designs vary but are based around casting in a set of threaded bars or a frame into a concrete base to which the tower crane fixing angles are connected to.
– Depending on ground conditions and the specific crane the base will be supporting, the concrete base can either:
• be a simple concrete pad where the self weight of the concrete provides stability, i.e., a gravity base
• or may require piles
These types of bases can enable higher crane free-standing heights.
78
TOWER CRANE COMPONENTS
77
78
1/03/2022
40
TOWER CRANE FOUNDATIONS
Cast-In Concrete Bases
– Concrete bases can be relatively compact enabling them to be constructed within the building.
– If effectively planned, the crane can take advantage of the permanent structure’s foundations.
– When decommissioning the tower crane the base can either be broken out or simply left in place and covered.
79
TOWER CRANE COMPONENTS
TOWER CRANE FOUNDATIONS
Ballasted Bases
– Sometimes also referred to as ‘Gravity Bases’.
– Ballasted bases rely on the weight of ballast to provide stability to the crane.
– These bases can either be founded on the engineered ground, on a concrete foundation or on rails.
– The amount of counterweight required depends on the crane and will be specified by the manufacturer.
– Loads exerted by the base are purely compressive – no tension.
80
TOWER CRANE COMPONENTS
79
80
1/03/2022
41
TOWER CRANE FOUNDATIONS
Grillages
– A steel frame to which a tower crane is connected to.
– Commonly used when positioning a crane on top of a building’s core.
– Can be either ballasted or tied into the building structure.
– May affect the design of the core (the permanent structure) due to the increased tension loads imparted by the crane.
81
TOWER CRANE COMPONENTS
MAST
The mast gives the crane its height and strength.
All mast will be of a lattice structure.
Common mast dimensions:
– 1.6m Square
– 2.0m Square
– 2.5m Square
– 4.5m Square
– 5.0m Square
82
TOWER CRANE COMPONENTS
5.0m or 10.0m height
81
82
1/03/2022
42
MAST
Masts can be of three main types:
– Standard
– Climbing
– Reinforced
A crane can be designed to take advantage of a variety of mast types to maximise its free-standing height.
– I.e., the use of dimensionally larger or reinforced sections at the base of the tower.
83
TOWER CRANE COMPONENTS
2.45m2
Adapter
Base
2.00m2
SLEWING RING
This component enables the top assembly of the crane to slew (rotate).
The slewing ring contains the gear and motors to enable rotation.
Commonly one of the heaviest individual components.
84
TOWER CRANE COMPONENTS
83
84
1/03/2022
43
OPERATORS CABIN
Where all the crane controls are located.
Room for a single operator.
Cranes can be remote controlled in some situations, albeit this is uncommon on construction sites.
85
TOWER CRANE COMPONENTS
COUNTER JIB
The counter jib is a structural element that contains both winches and counterweight.
The winches operate the trolley, jib and hoist line.
The counterweight balances the crane by offsetting the weight of the jib and thus enables the tower crane to pick up and move loads.
86
TOWER CRANE COMPONENTS
85
86
1/03/2022
44
A-FRAME
The A-Frame supports both the jib and counter jib by way of the fore and rear pendants.
A-Frames are not present on topless tower cranes.
87
TOWER CRANE COMPONENTS
JIB
The working arm of the crane that provides the necessary reach needed for the project.
Commonly a modular, lattice-based structure.
Increasing the length of a boom will typically reduce the capacity of the crane.
Allowable jib lengths are defined by the crane manufacturer.
Can be either luffing or static.
88
TOWER CRANE COMPONENTS
87
88
1/03/2022
45
TROLLEY
Since the jib on saddle and topless tower cranes is stationary, the lifting radius is modified by the horizontal movement of a trolley.
89
TOWER CRANE COMPONENTS
PLANNING FACTORS The Fundamentals of Tower Crane Planning
89
90
1/03/2022
46
TOWER CRANE HEIGHT PLANNING FACTORS
91
Question:
What factors on site will affect the choice, position and height of a tower crane?
PLANNING FACTORS PLANNING FACTORS
Tower Crane Scheme
Interface w/ other Cranes
Surrounding Structures
Tower Crane Erection / Dismantle
Wind Restrictions
Interface with Permanent Structure
Capacity Requirements
Oversailing RestrictionsOut-of-Service Conditions
Type of Tower Crane
Number of Cranes Req’d
Cost of Hire
Availability
Reliability
Coverage Requirements
91
92
1/03/2022
47
INTERFACE WITH OTHER CRANES
The interface between cranes needs to be carefully planned to ensure that they cannot clash when out-of- service.
Luffing jib tower cranes can be cited closer together as they have lower out-of-service radii. – Luffing Jib Tower Crane Out-of-Service
= Out-of-Service Radius
– Hammerhead / Flat Top Tower Cranes Out-of-Service = Full Jib Length
PLANNING FACTORS
93
SURROUNDING STRUCTURES
Surrounding structures will affect the height to tower cranes on a project.
High surrounding buildings will force higher tower crane heights.
Allowable clearances will be dependent on the owners of the surrounding buildings.
PLANNING FACTORS
94
93
94
1/03/2022
48
WIND RESTRICTIONS
The wind will have a significant affect on tower crane heights.
The UK has two main wind categories:
– C25: 28m/s Storm Wind with a 25-year reoccurrence
– D25: 32m/s storm wind with a 25-year reoccurrence.
PLANNING FACTORS
95
WIND RESTRICTIONS
What this means is that cranes in a D25 area will, when compared to the same crane in a C25 area, have:
– Lower maximum free-standing heights.
– Requirement for stronger tower sections.
– Higher base loads and moments.
– Higher requirements for ballasting
– Increased base strength / sizes.
PLANNING FACTORS
96
95
96
1/03/2022
49
INTERFACE WITH THE PERMENANT STRUCTURE
Tower cranes can be positioned both internally and externally to a building.
Tower crane position is primarily defined by required coverage.
A crane located centrally within a building can provide more effective coverage than externally located tower cranes.
PLANNING FACTORS
97
INTERFACE WITH THE PERMENANT STRUCTURE PLANNING FACTORS
98
Question:
Why might you position a crane within a building’s footprint rather than outside it?
97
98
1/03/2022
50
INTERFACE WITH THE PERMENANT STRUCTURE PLANNING FACTORS
99
INTERFACE WITH THE PERMENANT STRUCTURE
When citing a crane within a building the following needs to be considered:
– Size of the void needed (deflection)
– Affect on completion of units
– Waterproofing
PLANNING FACTORS
100
99
100
1/03/2022
51
INTERFACE WITH THE PERMENANT STRUCTURE
Size of the of void needed:
– Minimum size of the void should be the mast size plus 1.0m X, Y (0.5m clearance off each face) as a rule of thumb.
– Needs to be checked against anticipated mast deflection.
– Cranes will naturally deflect when in operation and out of service.
– Deflection will be can be calculated by the manufacturer on an as-requested basis.
– Deflections for standard mast configurations may also be given.
PLANNING FACTORS
101
INTERFACE WITH THE PERMENANT STRUCTURE
Affect on completion of units:
– Cannot complete areas where the crane mast penetrates.
– May require the temporary omission of structural members.
– Common to try and site tower cranes in areas that will have the least impact, i.e., atriums or courtyards.
– Possible to locate cranes within lift shafts also if space permits.
PLANNING FACTORS
102
101
102
1/03/2022
52
INTERFACE WITH THE PERMENANT STRUCTURE
Waterproofing:
– Voids created by cranes means water can enter the unfinished building.
– Materials subject to water damage should not be installed in areas where the crane penetrates the building.
– Area around the crane cannot be completed until the crane is removed.
PLANNING FACTORS
103
CAPACITY REQUIREMENTS PLANNING FACTORS
104
Question:
For what anticipated load would you design your crane scheme around?
– Heaviest?
– Average?
– Other?
103
104
1/03/2022
53
CAPACITY REQUIREMENTS
An important planning decision.
Do you plan for:
– the most common load weight and hire in additional craneage to lift heavier loads
– …or do you plan for the tower crane to be able to lift all anticipated loads?
Project dependent since weights will vary project to project.
PLANNING FACTORS
105
COVERAGE REQUIREMENTS
Tower cranes should be able to cover as much of the building as needed.
Multiple cranes may be required to cover the building.
Cranes must be able to reach both the building and any loading areas to minimise double handling.
PLANNING FACTORS
106
105
106
1/03/2022
54
OUT OF SERVICE CONDITIONS
All tower cranes have an out-of- service radius, albeit some smaller than others.
When out-of-service the crane must be allowed to freely slew with the wind.
Failure to do so can cause the crane to fail and potentially collapse.
Out-of-service conditions are defined in the manufacturer literature.
PLANNING FACTORS
107
OVERSAILING RESTRICTIONS
If a crane over-sails a neighbouring property, permission from the owner of said property needs to be sought.
This can be costly or hard to get – wholly dependant on the property owner in question.
Some owners may refuse entirely.
PLANNING FACTORS
108
107
108
1/03/2022
55
109
Source: Wonkabar007, 2020
OTHER FACTORS
Cost of Hire – Transport costs
– Erection / dismantle costs
– Weekly hire rates
– Maintenance
Availability – What cranes are actually available?
Reliability – How reliable is the proposed crane
– Maintenance schedule
– Plan in the event of breakdown
PLANNING FACTORS
110
109
110
1/03/2022
56
ERECTION AND DISMANTLE 4. PLANNING FACTORS
111
Source: FilmSpektakel, 2014
ERECTION AND DISMANTLE PLANNING FACTORS
112
Question:
What was missing in the previous video?
111
112
1/03/2022
57
ERECTION AND DISMANTLE
Erecting the tower crane is typically easier than dismantling it.
Dismantling is more complex since the building will now be constructed and may obstruct access.
Dismantling therefore needs to be considered prior to erection to ensure the crane can be actually be dismantled.
Typically a mobile crane will be used to dismantle the tower crane but in more complex projects other methods may be utilised.
PLANNING FACTORS
113
TOWER CRANE OR MOBILE CRANE? The Fundamentals of Tower Crane Planning
113
114
1/03/2022
58
TOWER CRANE VS. MOBILE CRANES
Tower Cranes are suited for… … high-density sites due to their small footprint.
… where lifting to extreme heights is necessary.
… ’small’ repetitive lifts.
… where reach is important.
However, tower cranes… … require erection and dismantle operations,
foundations and regular on-site maintenance resulting in increased costs.
… cannot be easily relocated if the need arises.
… long preparations before the first lift (i.e. testing etc.)
TOWER CRANE OR MOBILE CRANE?
115
TOWER CRANE VS. MOBILE CRANES
Mobile cranes are suited for… … where multiple lifts from different positions are
necessary.
… singular heavy lifts
… where capacity is important.
… fast mobilisation is required.
However, mobile cranes… … require more space for rigging and operation
than tower cranes.
… operate ‘below’ obstructions so may not be able to reach all areas of a site.
… may not be cost-effective for long projects (site / project dependent).
TOWER CRANE OR MOBILE CRANE?
116
115
116
1/03/2022
59
WHAT TYPE OF CRANE SHOULD YOU USE?
Completely dependent on the project at hand.
– Construction of a tower block in a city would favour a tower crane.
• Relatively small, repetitive lifts to height.
– Constructing an oil and gas refinery would favour mobile cranes, specifically a crawler crane.
• Large, singular lifts.
– Construction of domestic houses would favour mobile cranes.
• Small singular lifts
– Construction of a large shopping complex would favour tower cranes
• Need for increased reach.
TOWER CRANE OR MOBILE CRANE?
117
WHAT TYPE OF CRANE SHOULD YOU USE?
In reality, the question isn’t to decide one- or-another, it will define your primary means of lifting.
Mobile cranes will still be needed on sites with tower cranes.
TOWER CRANE OR MOBILE CRANE?
118
117
118
1/03/2022
60
CONCLUSION The Fundamentals of Mobile Crane Planning
AIM OF THIS PRESENTATION
You should now be able to:
…understand the different types of cranes.
…identify the components of mobile and tower cranes.
…recognise common constraints inherent in crane operations.
…read and understand crane schemes.
10. CONCLUSION
120
119
120
1/03/2022
61
MOBILE CRANES: ADDITIONAL RESOURCES
Video recommendations:
– Practical Engineering: Why Cranes Collapse
• https://youtu.be/swk3IjxzZB4
– Practical Engineering: Why Things Fall Off Cranes
• https://youtu.be/swk3IjxzZB4
– Lifting accident Alphen aan den Rijn
• https://youtu.be/LJevke4_i5Y
– Waikato Crane Accident
• https://youtu.be/PhaBAMyUbdk
– Big Blue Crane Accident
• https://youtu.be/6PRk_iKdiTA
10. CONCLUSION
121
Book recommendation:
– Cranes and Derricks, 4th Edition: Lawrence and Jay Shapiro.
TOWER CRANES: ADDITIONAL RESOURCES
Video recommendations:
– Practical Engineering: Why Cranes Collapse
• https://youtu.be/swk3IjxzZB4
– Practical Engineering: Why Things Fall Off Cranes
• https://youtu.be/swk3IjxzZB4
– How to Build a Tower Crane
• https://youtu.be/UC9m3sGRlnE
– Tower Crane Erection
• https://youtu.be/yHQfEvzNeKE
– ICE District Crane Removal
• https://youtu.be/9c_K5YX2LnI
– East Tower Crane Removal
• https://youtu.be/FlMjfT2cHWY
5. CONCLUSION
122
Book recommendation:
– Cranes and Derricks, 4th Edition: Lawrence and Jay Shapiro.
Website Recommendation:
– The Do’s and Don’ts of Crane Hire
• https://www.constructionnews.co.uk/buildings/cost- effective-crane-hire-reducing-costs-and-improving- profit-margins-08-06-2020/
121
122
1/03/2022
62
Name: Andrew Cockshoot TMIET
Function: Project Engineer
E-mail: [email protected]
www.sarens.com
123