Project Charter            Project Serial Number: 0001  Title of Project:  Work Shop  Start Date:  January 19, 2015

Finish Date:  March 20, 2015 

Project Manager:  x  Total Cost (+/‐ 10%):  $12,000 

ROI (+/‐ 10%):  27%  Payback Point (+/‐ 10%):  < 2 years 

Project Purpose or Justification:  The purpose of this project is to increase revenue through increased productivity.   Providing a larger workspace for multiple tasks will reduce or eliminate downtime between projects and reduce mistakes  and losses due to overcrowding of work areas. 

Measurable Project Objectives:  The objectives of this project are to increase revenue by 100% the first year of operation  with an approximate 20% increase annually.  A reduction of insurance rates for increased workplace safety may also be  realized but is not a requirement as a measurable objective for the success of this project. 

High‐Level Requirements:  The deadline for each stage must be met in order to progress to the next stage.  There must be  a team member for every aspect of this project to assure each contractor stays on schedule.  A list of the team members  and their roles are listed below. 

Summary of Milestones: 

The milestones for this project will consist of seven categories.  Even though some categories may have one or more  sub‐categories, the sub‐categories themselves are not considered milestones to this project.  For example, the  ‘Foundation’ milestone will have two sub‐categories, site prep and footings, which both must be complete in order to  move to the next stage. Therefore, only the deliverables below will be considered as milestones. 

Please Note: Meeting each milestone by the deadline listed is crucial to the next milestone completion date. 

Deliverable  Deadline Who is responsible

Foundation   January 21, 2015 x

Framing  February 18, 2015 x

Electrical  March 2, 2015 x

Rough‐In Inspection  March 3, 2015 x

Roofing and Siding  March 18, 2015 x

Flooring  March 19, 2015 x

Final Inspection  March 20, 2015 x

Success Criteria (Sponsor Acceptance Criteria):  This project will be successful if a 75% increase in revenue is realized after  one year of operation.  This project should also meet all regulatory requirements of both County and State regulating  bodies.  Success of project must include a finishing time of 2 months. 

High‐level risks: 

Risk  Mitigation Strategy 

Possibility of needing higher priced suppliers.  Arrange bulk discount deals with multiple suppliers.

Unknown price fluctuations of various wood species. Offer in‐stock specials until prices become stable.

Page 2 of 4 

Budget Summary:  The budget for this project is broken down into a seven individual categories as listed belowx. will not be responsible for  the resource allocation of each contractor.  It is the responsibility of each contractor to determine how their own budget is  used to meet their specific project requirements.  For example, the foundation, which is the responsibility of x., has a cost  of $2,000 and requires two stages, site prep and footings.  How this money is allocated, between site prep and footings, is  the sole responsibility of x Inc. and shall not exceed the total of the excepted estimate of $2,000 unless there is a change  order that has been approved by the Project Manager. 

Budget Category  Source Cost 

Foundation 

 Site prep  Footings

x  $2,000

Framing 

 Sub Floor  Structure

x  $3,150

Electrical 

 Service Panel  Interior Wiring  Receptacles and Switches

x  $2,000

Rough‐In Inspection 

 Framing Rough  Electrical Rough

x  $110

Roofing and Siding 

 Roof Dry‐in  Siding

x  $4,500

Flooring  x  $150

Final Inspection  $110

Key Stakeholder List: 

Name  Role  Position Contact Info  MBTI Type

x  Champion  Co‐Owner x ISTJ 

x  Sponsor  Co‐Owner x ESFP 

Project Team Members: 

For a complete list of roles and responsibilities for each team member please see  x – Communication Plan) 

Name  Role  Position Contact Info  MBTI Type

x  Project Manager  Co‐Owner ISTJ 

x  Schedule Leader  Sales ISTJ 

x  Budget Leader  Accounting ESTP 

Quality Leader  Inspection ISTJ 

Safety Team  Assembly ESFJ 

Safety Team  Assembly ISTP 

x  After Hours Contact  Office Manager ESTP 

Funding Sponsor: (VP accountable for project)  x

Sponsor Signature: x 

Attachment A: 

Project Communication Plan  Project Serial Number: 0001 

Title of Project:  Work Shop  Start Date: January 19, 2015 Finish Date: March 20, 2015 

Page 3 of 4 

Project Manager: x  Total Cost (+/‐ 10%): $12,000 

Project  Role 

Name  MBTI  Information Desired Method of  Delivery 

Timing or  Frequency 

Contact  Information 

Champion  x  ISTJ  Status updates Email Daily – 8:00am  x

Notes:  The project manager will be responsible for contacting and updating X of this project. 

Project  Role 

Name  MBTI  Information Desired Method of  Delivery 

Timing or  Frequency 

Contact  Information 

Sponsor  x  ESFP  Monthly status report Email 1st of the  month 

x

Notes:  X shall be informed of any changes that are not included in the latest status report. 

Project  Role 

Name  MBTI  Information Desired Method of  Delivery 

Timing or  Frequency 

Contact  Information 

Project  Manager 

x  ISTJ  Daily status report  Short meeting  Daily – 8:00am  x 

Notes: Meetings will be held daily at 8:00am to discuss progress and status of the project. 

Project  Role 

Name  MBTI  Information Desired Method of  Delivery 

Timing or  Frequency 

Contact  Information 

Budget  Team  Leader 

x  ESTP 

Billing, change orders and 

material/equipment  lists 

Email  Weekly/Each  Monday 

Notes: For insurance purposes, x will need an itemized list from each contractor for all materials and equipment  on site at the beginning of the workday each Monday. 

Important!  x. and its insurers will not be responsible for any equipment or material NOT on this list at the  beginning of each week! 

Project  Role 

Name  MBTI  Information Desired Method of  Delivery 

Timing or  Frequency 

Contact  Information 

Quality  Team  Leader 

x  ISTJ  Materials specifications  Email  Before all  material  delivery 

Notes:  All materials must be approved by x Smith before installation.  Please notify Mr. Smith of any  unscheduled deliveries as soon as possible.  Mr. Smith must also be informed immediately of any necessary changes to  material list for each contractor. 

Project  Role 

Name  MBTI  Information Desired Method of  Delivery 

Timing or  Frequency 

Contact  Information 

Schedule  Team  Leader 

x  ISTJ  Daily schedule and  number of workers on  site per contractor 

Email Each Morning  x

Notes:  Each contractor must supply Mr. xr with the number of workers that perform work on site each day.

Project  Role 

Name  MBTI  Information Desired Method of  Delivery 

Timing or  Frequency 

Contact  Information 

Safety  Team 

x  ESFJ  MSDS sheets from all  contractors for all 

Email or Fax Once/Before  contractors 

x FAX: 904‐555‐

Page 4 of 4 

Member  materials used. begin work  9989

Notes: x will need all MSDS documentation before any contractor can begin work.  This is an OSHA requirement  and there are no exceptions! 

Project  Role 

Name  MBTI  Information Desired Method of  Delivery 

Timing or  Frequency 

Contact  Information 

Safety  Team 

Member  x  ISTJ  On‐site Injuries  Phone  As needed  x 

Notes:  All injuries must be reported to x as soon as possible.  x is responsible for all incident documentation.

Project  Role 

Name  MBTI  Information Desired Method of  Delivery 

Timing or  Frequency 

Contact  Information 

After  Hours  Contact 

x  ESTP  See Note Below  Phone  As needed  x 

Notes:  If any information is needed before or after normal work hours, and there is no time to wait for a  response, this is the contact to use.  In the event of anyone not being able to contact the appropriate team member in  a reasonable amount of time, x will be the emergency contact for all parties, both internal and external.  Ms. Williams  will direct any correspondence to the appropriate person or department immediately. 

Funding Sponsor: (VP accountable for project) 

x  Sponsor Signature: