finamce
Phase 1
| Capital Expenditure Planning & Budgeting for Universal Parts Company | ||||||||
| Universal Parts Company - Estimated Cash Flows (CF) for Projects A & B (in thousands of dollars): | ||||||||
| Year | CFA | CFB | Assumme that tax effects, depreciation, salvage values, and all operating costs have been included in the cash flows | |||||
| 0 | ($1,000) | ($1,000) | ||||||
| 1 | $100 | $700 | ||||||
| 2 | $600 | $500 | ||||||
| 3 | $800 | $200 | ||||||
| Net Present Value (NPV) | ||||||||
| (1) Determine each project’s NPV. | ||||||||
| WACC = | 10.00% | Activity: Choose both projects if two projects are independent, and their NPVs are positive | ||||||
| Activity: Choose the project with the higher positive NPV if the two projects are mutually exclusive | ||||||||
| NPVA = | $187.83 | |||||||
| NPVB = | $199.85 | |||||||
| Internal Rate of Return (IRR) | ||||||||
| (1) Determine each project’s IRR. | ||||||||
| The internal rate of return (IRR) is that discount rate which forces the NPV of a project to equal zero. | ||||||||
| Activity: Double-click on the equation to find out how you can insert an equation. | ||||||||
| The solution to this equation can be found using Excel's IRR function. | ||||||||
| IRRA = | 18.1% | Activity: Choose both projects if two projects are independent, and their IRRs are higher than the WACC | ||||||
| IRRB= | 23.6% | Activity: Choose the project with the higher IRR in excess of WACC if the projects are mutually exclusive | ||||||
| Crossover Rate | ||||||||
| (1) Draw NPV profiles for Projects A and B. At what discount rate do the profiles cross? | ||||||||
| Project | Project | |||||||
| WACC | A | B | ||||||
| $187.83 | $199.85 | |||||||
| 0% | 500.00 | 400.00 | ||||||
| 5% | 330.53 | 292.95 | ||||||
| 10% | 187.83 | 199.85 | ||||||
| 15% | 66.66 | 118.27 | ||||||
| 20% | -37.04 | 46.30 | ||||||
| 25% | -126.40 | -17.60 | ||||||
| Year | CFDifference | |||||||
| 0 | $0 | |||||||
| 1 | ($600) | |||||||
| IRR = crossover rate = | 8.68% | 2 | $100 | |||||
| 3 | $600 | |||||||
| Modified Internal Rate of Return (MIRR) | ||||||||
| (1) Find the MIRRs for Projects A and B. | ||||||||
| Activity: MIRR is the internal rate of return for a series of a project’s cash flows, taking into account the cost of investment and interest on reinvestment of cash. | ||||||||
| Activity: Projects A and B's modified IRRs can be solved for by using Excel's MIRR function, entering their cash flows and using the WACC as both the discount rate and the reinvestment rate. | ||||||||
| MIRRA = | 16.5% | By the MIRR criteria, Project B is preferred to Project A, which is consistent with the NPV decision. | ||||||
| MIRRB = | 16.9% | |||||||
| Payback Period | ||||||||
| (1) Find the paybacks for Projects A and B. | ||||||||
| Payback Calculations | ||||||||
| Project A | Years | 0 | 1 | 2 | 3 | |||
| | | | | | | | | |||||
| Cash Flow | -1,000 | 100 | 600 | 800 | ||||
| Cumulative Cash Flow | -1,000 | -900 | -300 | 500 | ||||
| Payback A = 2 + 300/800 = | 2.4 | |||||||
| Project B | Years | 0 | 1 | 2 | 3 | |||
| | | | | | | | | |||||
| Cash Flow | -1,000 | 700 | 500 | 200 | ||||
| Cumulative Cash Flow | -1,000 | -300 | 200 | 400 | ||||
| Payback B = 1 + 300/500 = | 1.6 | |||||||
NPV Profiles
$187.83 0 0.05 0.1 0.15000000000000002 0.2 0.25 500 330.52586113810594 187.82870022539419 66.655708062792883 -37.037037037036953 -126.39999999999998 $199.85 0 0.05 0.1 0.15000000000000002 0.2 0.25 400 292.94892560198673 199.8497370398195 118.27073230870405 46.296296296296532 -17.600000000000023WACC
NPV ($)
Sheet2
Sheet3
å
=
+
=
=
n
t
t
t
IRR
CF
0
)
1
(
$0
NPV
n
t
t
t
IRR
CF
0
)1(
$0 NPV