Keanu
Dr X Shen©2020Dr X Shen©2020
Term 3, 2020 CVEN9723 DESIGN OF CONSTRUCTION OPERATIONS
Instructor: Dr X Shen
Date: 21 September 2020
Earthwork Estimating
Dr X Shen©2020
What Have We Learned?
• What is the typical estimating process?
• How to conduct the conceptual cost estimating?
• How to estimate the cost of Labour and Equipment?
2
Dr X Shen©2020
Handling and Transporting Material
3
(Courtesy: andysearthmovers)
Dr X Shen©2020
Learning Objectives
• How to estimate time and cost for earthmoving construction projects? • What’s quantity take-off in construction? • How to use mass diagram for grading plan? • Any technical innovations?
4
(Courtesy: Minesurveyor)
Dr X Shen©2020
What’s Earthmoving?
Earthmoving is the process of moving soil or rock from one location to another and processing it so that it meets construction requirements of location, elevation, density, moisture content, etc.
5
Dr X Shen©2020
Typical Earthmoving Operations
6
Haul, Loaded
Return, Empty
Dr X Shen©2020
Soil Volume-Change Characteristics
Soil Conditions – Bank: natural state before disturbance
• Referred to as: “in-place” or “in-situ” • Unit: bank cubic meter (BCM)
– Loose: material that has been excavated or loaded
• Unit: loose cubic meter (LCM) – Compacted: material after compaction
• Unit: compacted cubic meter (CCM)
7
Dr X Shen©2020
Soil Volume-Change Characteristics
8
Bank Loose Compacted (Courtesy: Nunnally 2011)
1 BCM 1.25 LCM 0.9 CCM
Dr X Shen©2020
Load Factor
A conversion factor to simplify the conversion of loose volume to bank volume
9
Weight/loose unit volume
Weight/bank unit volume Load factor =
Dr X Shen©2020
Shrinkage Factor
A factor used for the conversion of bank volume to compacted volume
10
Weight/bank unit volume
Weight/compacted unit volume Shrinkage factor =
Dr X Shen©2020
Soil Volume-Change Characteristics
11
(Courtesy: Nunnally 2011)
Dr X Shen©2020
Earthmoving Operations
12
Dr X Shen©2020
Earthmoving Estimate
Cycle Time for Transporting Material – Loading Time – Traveling Time (haul, loaded) – Unloading Time – Returning Time (empty)
The time required for each element should be determined for cost estimate
13
Dr X Shen©2020
Earthmoving Estimate
Production Rate – The number of units of work produced by a
unit of equipment or a person in a specified unit of time, e.g. m3/hour
Efficient Factor – A machine or a worker may work only 45 min
in an hour – Actual production rate is 0.75 of maximum
14
Dr X Shen©2020
Earthmoving Estimate
• Production rates are crucial to estimate the time and cost of the projects • The total project time is determined by dividing the total quantity of work by the production rate • Cost of labour and equipment can be determined by multiplying the total time by the hourly rate of labour and equipment
15
Dr X Shen©2020
Estimation Procedures
Step 1: Quantity of Work Step 2: Cycle Time Step 3: Production Rate Step 4: Project Time Step 5: Total Cost Step 6: Unit Cost
16
Dr X Shen©2020
Example 1 A total 120 m3 of clay has to be transported to a job site 15 km away using a 10 m3 dump truck. A tractor loader is used to load the truck at a rate of 80 m3/hour. The travel times for haul and return of the truck are 32 minutes and 25 minutes, respectively. It takes 3 minutes to dump the load. The cost of the truck is $ 42 /hour, the truck driver is $ 28 /hour. The cost of the loader is $ 55 /hour, the loader operator is $ 32 /hour. The average working time is 45 minutes in one hour. Determine the total time, total cost, and the cost/unit of transporting the clay.
17
Dr X Shen©2020
Productivity Improvement?
• How to improve the loading efficiency? • What is the difference using labour or a loader for loading? • How to match the number of the loader and the haul trucks?
18
Total Cycle Time Load Time
No. of Trucks =
Dr X Shen©2020
Example 2
Using the data in Example 1, determine the economical number of trucks such that the load time and transport time balance.
19
Dr X Shen©2020
Productivity Improvement?
What if there are 2 loaders and 10 trucks? How to estimate the project cost?
20
(Courtesy: CYCLONE Simulation)
Dr X Shen©2020
Earthwork Quantity Take-off
21
(Courtesy: Donaldson Garrett)
Dr X Shen©2020
Earthwork Quantity Take-off
• When planning or estimating an earthmoving project, it is often necessary to estimate the volume of material to be excavated or placed (Cut vs. Fill) • Quantity take-off is a detailed measurement of earthwork volume to complete a construction project
22
Dr X Shen©2020
Earthwork Quantity Take-off
• Contractors are paid for the volume of excavation • Earthwork can be roughly estimated by counting the number of truckloads
23
(Courtesy: CAT)
Dr X Shen©2020
Pit Excavations
Small, relatively deep excavations Volume = Horizontal area × Average depth
24
(Courtesy: FictionU)
Dr X Shen©2020
Pit Excavations
Calculation – Step 1: Divide the horizontal area into a
convenient set of rectangles, triangles, or circular segments
– Step 2: Determine the total area as the sum of the segment areas
– Step 3: Calculate the average depth
25
Dr X Shen©2020
Example 3 Estimate the volume of excavation required for the basement. Values shown at each corner are depths of excavation.
26
(Courtesy: Nunnally 2011)
Dr X Shen©2020
Trench Excavations Usually constructed for utility lines
Volume = Cross-sectional area × Length
27
(Courtesy: Joyceroad)
Dr X Shen©2020
Example 4 Find the volume of excavation required for a trench 0.92 m wide, 1.83 m deep, and 152 m long. Assume that the trench sides will be approximately vertical.
28
(Courtesy: ecmweb)
Dr X Shen©2020
Large Areas Dividing the area into a grid indicating the depth of excavation or fill at each grid intersection
29
(Courtesy: wplinternational)
Dr X Shen©2020
Large Areas
30
(Courtesy: CAT)
Dr X Shen©2020
Large Areas
Average Depth – Assign the depth at each corner or segment
intersection a weight according to its location • Interior points: Weight of four • Exterior points at the intersection of two
segments: Weight of two • Corner point: Weight of one
31
Dr X Shen©2020
Large Areas
Average Depth
32
Sum of products of depth × Weight
Sum of weight =
Dr X Shen©2020
Example 5
33
Dr X Shen©2020
Mass Diagram
34
(Courtesy: ugpti.org)
Dr X Shen©2020
Mass Diagram
• A continuous curve representing the accumulated volume of earthwork plotted against the linear profile of a roadway or airfield • Prepared by highway and airfield designers
35
Dr X Shen©2020
Mass Diagram
• Used to assist in selecting an alignment which minimizes the earthwork required to construct the facility while meeting established limits of roadway grade and curvature • Very useful for construction manager
36
Dr X Shen©2020
Example 6
37 (Courtesy: Nunnally 2011)
Dr X Shen©2020
38
(Courtesy: Nunnally 2011)
Dr X Shen©2020
Innovations in Earthmoving
39
(Courtesy: aerometrex)
Dr X Shen©2020
Aerial Innovation
40
(Courtesy: THIESS)
Dr X Shen©2020
UAV Resources at UNSW
Multirotor UAVs
41
DJI Phantom 3 Professional • Weight: 1.28 Kg • Sensor: 12MP Camera • Flight time: 20 min • No. of Propellers: 4
Vulcan Heavy Lift Octocopter • Weight: 14 Kg • Sensors: LiDAR/Infrared Cam • Flight time: 1 Hour • No. of Propellers: 8
Dr X Shen©2020
UAV Resources at UNSW
Fixed Wing UAVs
42
SenseFly eBee RTK • Weight: 0.73 kg • Sensor: 12MP RGB & NIR Cams • Flight time: 40 min • Wingspan: 0.96 m
SenseFly swinglet CAM • Weight: 0.5 kg • Sensors: 12 MP Camera • Flight time: 30 min • Wingspan: 0.8 m
Dr X Shen©2020
Learning Objectives
• How to estimate time and cost for earthmoving construction projects? • What’s quantity take-off in construction? • How to use mass diagram for grading plan? • Any technical innovations?
43
(Courtesy: Minesurveyor)
Dr X Shen©2020
44
Questions?