project management assignment # 11
Good start on the risk register. Here are my initial comments. I only looked at the risks because there is no point looking at the other columns if the risks are not correct. So, start by getting the risks correct and then we can work on the rest.
|
Risk Event Description What is the event? |
|
||
|
The union workers may go on a strike or slow down the work owing to their glitches with the project management team or the project sponsor
|
Development |
||
|
machines tools fail on their promise
|
|
||
|
dekay on material delivery
|
|
||
|
The occurrence of major earth quake in the city during the venture period.
|
|
||
|
Non- Adherence of the team members to the processes of PMP
|
|
||
|
Difficulty in allocating roles and responsibilities to the team members
|
|
||
|
The site condition is not favorable since the soil is not considered to facilitate for the construction
|
|
|
Lack of Communication between the project manager and the team
|
|
|
bad Weather
|
Too general. Construction projects plan for poor weather - such as rain. Youmust be more specific such as: Inclimate weather days exceeds planned number of inclimate weather days resulting in a schedule delay and cost overrun.
|