Good start on the risk register. Here are my initial comments. I only looked at the risks because there is no point looking at the other columns if the risks are not correct. So, start by getting the risks correct and then we can work on the rest.

Risk Event Description  What is the event?

Prof Allen Comments

The union workers may go on a strike or slow down the work owing to their glitches with the project management team or the project sponsor

Development

 machines tools fail on their promise

Grammer not correct - risk is unclear.

dekay on material delivery

Spelling incorrect -risk not clear. Materials do not decay that quickly.

The occurrence of major earth quake in the city during the venture period.

Act of god and no way to mitigate, I would not include this, I would accept this.

Non- Adherence of the team members to the processes of PMP

Unclear what your worried about, PMP is a certification. If you are referring to PMBOK processes, there are 40+ processes  - this statement is too broad to effectively manage as a single risk.

Difficulty in allocating roles and responsibilities to the team members

Not clear - what part is difficult?

The site condition is not favorable since the soil is not considered to facilitate for the construction

Lack of Communication between the project manager and the team

bad Weather

Too general. Construction projects plan for poor weather - such as rain. Youmust be more specific such as: Inclimate weather days exceeds planned number of inclimate weather days resulting in a schedule delay and cost overrun.