pmgt 699 - rfp

profileiamgroot_1992
RFPdocument.docx

RFP

1. Project Initiation Phase

The purpose of the RFP document is to define all procurement related activities for implementing Oracle for Tesla motors. This document will outline all the procurement management activities and resources that are required for implementing the software.

2. Procurement Statement

Below are the list of items that must be procured in order to successfully start the project.

Item/Service

Justification

Needed By

Cost

Rack server for the software implementation

This is an inventory item that needs to be procured for implementing the new software (Oracle R12) for the company

01/01/2018

$5000

Printer and scanner

Need printer/ scan to print out the documentation

01/5/2018

$2000

Table

Need computer tables for consultants to work on implementation

01/15/2018

$1000

Chair

Need desk chairs for consultants to implement the application

01/15/2018

$1000

Car

Need a car for consultant’s usage

01/15/2018

$10,000

Laptops

Laptops are needed for consultants to work on

01/15/2018

$5000

Office supplies

These are office supplies that are required by the implementation partner

01/15/2018

$2000

Consultants service

Consultant service is required to implement the Oracle software.

01/15/2018

$404,617.60

Vendor selection: The vendor selection process is very straight forward as most of the vendors are have had good relations with real tech. The entire consultant team are offered by Real Tech itself. The office supplies are procured by the vendor name Staples. Finally, the laptops are procured by tech systems. The vendors are carefully analyzed by the buyers and are listed on the buyer’s approved vendor list of vendors. The vendors are rated based on the price, delivery time and quality of the products.

3. Selection Process & Criteria

The hardware and office supplies are based on the planned purchase order contract with the vendor. The consultants are interviewed before hand before onboarding the resources into the team.

4. Project Procurement Team

All procurement activities must initially get approval from the immediate manager and then the approval of the project manager. The project manager must document justify the need in a form of a document and present it to the project sponsors.

5.Contract Type:

The procurement strategy used by Tesla is called Fixed- Price Contract. This type of contract is also called Lump- sum contract. The reason for choosing this contract is that there is no uncertainty in the scope of the project. The purchasing module in the Oracle ERP software will help improve the procure to pay cycle in the organization. The ERP implementation partner is bound to finish the implementation within one year at the cost of $350,000.

6.Contract Standards:

All procurement must follow the  ISO 9001:2015 standards.

7.Vandor Management/ Perforance

This section describes the metrics to be used for procurement activities associated with the project. These metrics may include but not be limited to: methods to ensure the project stays on schedule regarding procurement activities, and methods used to compile data on the performance of various vendors in order to assist with future procurement activities.

Vendor

Quantity ordered vs quantity received

1

Delivery on time

2

The accuracy of advanced shipment notices

3

Rate of return

4

Ordered price vs invoiced price

5

Vendor #1

3

3

4

3

2

Vendor #2

2

1

2

2

2

Points are given on the basis of performance 1 being the least and 5 being the highest. The total score can be produced by the sum of criteria 1+2+3+4+5.

The time line for submittal proposal-

Process

Completion time

Responsible party

Submitting the contract

6 days

Buyers

Reviewing the contract

5 days

Procument manager

Completing the contract

1 day

Procurement manager and legal team

Procurement process and timeline-

· The buyers and the supplier quality and engineering team will review the vendor list.

· The statement of work and cost and time is requested form the selected vendors.

· Vendors have 1 day to respond to the request for information.

· The procurmemt team will submit the contract within 6 days.

· The negotians if any are handled by the buyers.