BaseLine plan
Request for Proposal
statement of purpose
The goal of the project is to make a mobile application that lets users learn and practice judging yoyo freestyles. The application must be able to be used on mobile devices. The objectives for the app are
· To help those who want to learn to judge yoyo freestyles for competitions (rules set by the IYYF).
· To be used as a tool for clicking and tabulating scores
· To compare your scores with others
background information
“The International Yo-Yo Federation (IYYC) is a nonprofit organization dedicated to developing and promoting yo-yoing as a sport on a global level.” We are the governing body of all state, regional, national, and world level yoyo contests. We work to have our contests run smoothly and in a uniform way with the same judging system across all events. According to our studies, over half of the people who actively watch, compete, and play yoyo do not understand the rules to the contests they are watching.
This project will be handled by someone who loves working in team, enjoys yoyoing and likes to get work done on time.
scope of work
The scope of this project includes:
· The app itself
· The ability for a clicker function (described in detail later)
· Ability to save scores for free styles
· Ability to share their scores and compare to others of the same freestyles
Out of scope for the project includes but limited to:
· Website
· Registration for yoyo contests
· Streaming videos for judging
outcome & performance standards
The targeted outcome from this project is a design for the mobile application to be made, not a fully functioning app. This project needs to be done on time with the collaboration of the whole team. We will be monitoring by checkups via email. Our process for corrective actions are 2 formal warnings and then removal from the team.
deliverables
All products will be delivered by the schedule set below. These deliverables schedules are subject to change.
|
Date |
Deliverable |
Date |
Deliverable |
|
9/10 |
Request for Proposal |
11/5 |
Prototype 3 |
|
9/17 |
Baseline Plan |
11/12 |
Final Report |
|
9/24 |
Prototype 1 |
12/8 |
Finnish Project conclusion |
|
10/15 |
Prototype 2 |
|
|
term of contract
Contract will be executed on September 12th, and go until December 8th. No options for renewal at this time.
payments, incentives and penalties
If the contract is competed by the previously mentioned date team members will be rewarded with burritos or something of similar or equal value. If performance is stellar (meaning high scoring) you may even get a drink of your choice.
contractual terms and conditions
These are what assurances that we need from stakeholders:
· Commitment to the schedule
· Ability to communicate regularly with the team
· Coming to Thursdays work meetings
process schedule
Attending Thursdays classes are necessary in supplement to the above schedule in part 5.
points of contact
Max Kelly
Ryan Savard
?