rewrite
i
A SENIOR DESIGN PROJECT TO EVALUATE
A CIVIL ENGINEERING FACILITY
NEAR GRAND FORKS, ND
CE 483
Department of Civil Engineering
University of North Dakota
Design Group ID: Group 7 Transportation Engineering
Preliminary Report
ii
Table of Contents Acknowledgements ................................................................................................................................ iv
Executive Summary ................................................................................................................................ v
1.0 Introduction .................................................................................................................... 7
1.1 Challenges During Design ................................................................................................ 7
2.0 Existing Conditions ........................................................................................................................... 9
2.1 Land Use ......................................................................................................................... 9
2.2 Existing Roadways ........................................................................................................... 9
2.3 Right of Way .................................................................................................................. 10
2.4 Utilities ......................................................................................................................... 11
2.5 Traffic ........................................................................................................................... 11
2.5.1 Average Daily Traffic ................................................................................................... 11
2.5.2 Pedestrian Facilities ................................................................................................... 12
3.1 Complete Overhaul ....................................................................................................... 14
5.0 Construction and Traffic Control ...................................................................................................... 25
5.1 Construction Stages ...................................................................................................... 25
6.0 Cost Estimates ................................................................................................................................. 29
7.0 Conclusion and Recommendations................................................................................................... 33
7.1 Conclusion ...................................................................................................................................... 33
8.0 References ....................................................................................................................................... 35
iii
List of Figures Figure 1 Project Limits ................................................................................................................... 9 Figure 2 N 3rd Street Existing Typical Section ................................................................................ 10 Figure 3 N 4th Street Existing Typical Section ................................................................................ 10 Figure 4 Gateway Drive Existing Typical Section ............................................................................ 10 Figure 5 2022 Grand Forks GIS Traffic Volumes ............................................................................. 12 Figure 6 Existing Bike Facilities .................................................................................................... 12 Figure 7 Existing Shared Use Path and Tunnel ................................................................................ 13 Figure 8 Alternative Two Gateway Drive and N 4th Street Intersection .............................................. 14 Figure 9 Alternative 2 Gateway Drive, 11th Avenue N, and N 3rd Street Intersection ........................... 15 Figure 10 Alternative 2 Gateway Drive and N 3rd Street Intersection ................................................. 15 Figure 11 Alternative 2 N 3rd Street Typical Section 3+00 to 32+00 .................................................. 16 Figure 12 Alternative 2 N 4th Street Typical Section 0+50 to 3+50, 7+00 to 37+00 ............................. 16 Figure 13 Wilder Elementary Pickup and Dropoff Zone ................................................................... 17 Figure 14 Alternative 2 N 4th Street Typical Section 3+50 to 7+00 .................................................... 18 Figure 15 Phase 1: Traffic Control Work Zones ............................................................................... 27 Figure 16 Phase 2: Traffic Control Work Zones ............................................................................... 28 Figure 17 Phase 2: Traffic Control Detour Map ............................................................................... 28 Figure 18 Phase 3: N 4th Street Detour Map ................................................................................... 29 Figure 19 Gateway Drive Traffic Control Diagram .......................................................................... 31
List of Tables Table 1 Design Alternative Comparisons ........................................................................................ 13 Table 2 Cost Estimation................................................................................................................ 30 Table 3 Traffic Control Signs by Phase ........................................................................................... 32 Table 4 NDDOT 2023 Traffic Control Specifications ....................................................................... 32
iv
Acknowledgements
The members of the University of North Dakota Civil Engineering Design Group 7
would like to extend our gratitude to Dr. Nabil Suleiman, Curt Dunn, and David Kuharenko for
serving as our advisory board. Their guidance and time have been greatly appreciated and
incredibly helpful.
v
Executive Summary
The objective of this senior design statement is to consider the conversion of N 3rd Street
and N 4th Street from one-way streets to two-way streets in Grand Forks, North Dakota. The
proposed alternatives designed for this project convert N 3rd Street and N 4th Street to two-way
streets, reconstruct the north side of Gateway Drive and N 3rd Street and 4th Street, or change
nothing. The goals for this project focus on safety, efficiency, and sustainability. This significant
urban planning initiative, encompassing the area between Gateway Drive and University
Avenue, is poised to bring about a myriad of benefits, with a particular emphasis on these
specific goals.
The conversion to two-way streets is anticipated to significantly enhance safety by
simplifying the traffic flow and minimizing complex intersection dynamics in these areas. This
aims to create a secure transportation environment for all vehicles and pedestrians in the area.
Not only do these alternatives enhance safety, but the proposed alternatives also focus on
efficiency by using a redesigned street layout. It is proposed when designing alternatives for
these streets to optimize traffic flow, reduce congestion, and offer a more streamlined
transportation experience throughout the city. This has a far-reaching implication for
convenience, productivity, and overall higher quality of life. The last of the more prioritized
goals in consideration is the sustainability factor of this conversion. With an emphasis on the
possible impact of converting from one-way streets to two-way streets, the alternatives minimize
disruption of the environment and surroundings to maximize sustainability efforts.
Other factors considered in the process of designing alternatives for the idea of
transforming N 3rd Street and N 4th Street’s one-ways are the optimization of traffic signals,
working within traffics codes, cost, and possible limitations and constraints.
The existing traffic signals and their proximity to the proposed changes are analyzed to
ensure that the signal design aligns with the City of Grand Forks traffic control standards and
guidelines. The project’s designs follow the North Dakota Department of Transportation
(NDDOT) Traffic Operations Manual in considering the need for left turn lanes, right turn lanes,
and traffic signals at intersections.
Another factor that is being investigated is the estimated costs for the three design
alternatives. The conclusion derived from the data suggests that the first alternative of changing
N 3rd Street and N 4th Street from one-way to two-way would be costly. The limitations
considered in these alternatives include restricted space surrounding the one-way streets in this
project’s scope. The impact on the existing businesses and other surrounding existing structures
are considered in preserving the right-of-way and possible implications for pedestrians and
school access.
vi
Design Recommendation
Thorough investigations were formed into multiple alternatives for the proposed two-way
street conversion project. It determined that a complete overhaul of the roadway geometry,
layout, and flow of traffic surrounding Wilder Elementary is necessary to provide the greatest
positive influence upon the school and surrounding area. This work will remove of a current
traffic light system along Gateway Dr, and 11th Avenue N and replace it with a new traffic light
at Gateway Dr, and N 4th Street. A raised median will be installed along Gateway Drive that
extends from N 3rd Street to N 4th Street. 11th Avenue N will be converted into a hammer-head
turnaround. A right turn lane for N 3rd Street will be added along Gateway Drive.
These changes will help improve, and align with the city’s goals for transportation
quality, as well as those who it directly affects. The proposed changes do not only impact
mobility, but also the overall urban experience for residents and visitors, positioning Grand
Forks as a city that embraces modern urban planning principles to prioritize the overall health of
the transportation networks of their community.
1.0 Introduction
The city of Grand Forks, North Dakota is working towards a more urbanized
development, motivated to redefine its transportation infrastructure to meet the growing demands
of a dynamic urban landscape. Part of this transformation are the proposed alternatives aimed at
the conversion of N 3rd Street and N 4th Street from their existing one-way configuration to a
two-way, spanning the stretch between Gateway Drive and University Avenue. This ambitions
initiative holds the potential to improve traffic flow and enhance accessibility within the city,
with a commitment to safety, sustainability, and efficiency driving the project forward.
The two proposed alternative designs consider minimal change to the road’s geometry
and layout against a full overhaul design of the layout and geometry surrounding Wilder
Elementary. As the demographics of Grand Forks shift and urbanization accelerates, the
initiative to optimize transportation networks becomes increasingly pronounced. The design
alternatives for the conversion project embody a proactive approach to meeting the evolving
needs of a growing city, rooted in a comprehensive understanding of the area’s traffic dynamics
and urban design. The conversion from a one-way to a two-way of N 3rd Street and N 4th Street
is discussed with a proposed idea of implementation while prioritizing the transportation
infrastructure to align with the growing city’s needs and aspirations.
1.1 Challenges During Design
Wilder Elementary School is located between N 3rd Street and N 4th Street and immediately
adjacent to Gateway Drive.
A chain link fence separates N 3rd Street from Wilder Elementary School. Additional
signs are also implemented to improve safety around the school. The pedestrian tunnel
under Gateway Drive remains intact and sees improvements and upgrades.
N 3rd Street currently has a left turn lane and a right turn lane and could not support a
southbound lane as is.
In both design alternatives, N 3rd Street only accommodates right turns from N 3rd Street
onto Gateway Drive and right turns from Gateway Drive to N 3rd Street. This provides a
safer environment and restricts Gateway Drive traffic from making a left turn onto N 3rd
Street without a traffic light.
There is an existing traffic signal at Gateway Drive and N 3rd Street and 11th Avenue N so
adding additional signals at N 3rd Street or N 4th Street would be too close to the existing
traffic signal.
Alternative one features minimal changes to the current setup and only requires new
striping of pavement markings. The traffic signal stays in its current location. In
alternative two, the traffic signal at 11th Avenue N is removed and a new traffic signal is
placed at the intersection of Gateway Drive and N 4th Street.
Currently, N 4th Street only allows parking on the west side of the road, however vehicles
dropping off and picking up school children from Wilder Frequently Park on the east side.
So, the new layout should address this concern.
In both design alternatives, a drop off and pick up section is exclusively designed for
Wilder Elementary. N 4th Street is widened between 11th Avenue N and 10th Avenue N
for the addition of this lane.
Could N 3rd Street and/or N 4th Street be realigned to better connect to the streets north of
Gateway Drive?
Alternative two realigns N 4th Street with Gateway Drive. This improves the street’s
safety and efficiency.
Could N 3rd Street be changed to a cul-de-sac and not connect to Gateway Drive?
The design team reviewed this concept but decided against it. There is enough room to
construct a cul-de-sac, but keeping both streets connected to Gateway Drive provides
better traffic flow and prevents all traffic being forced onto N 4th Street. Cul de sac is a
very possible option, but the design team prefers to keep connection of 3rd St to Gateway
Dr.
Is it feasible to purchase/relocate business if additional property is required?
Alternative two require right-of-way purchase for the hammerhead on 11th Avenue N.
The additional turn lane will also require right-of-way if one is installed.
If N 3rd Street and/or N 4th Street are realigned how does this impact the existing shared
use path?
Both alternatives do not impact the shared use path. The shared path remains in its
current location.
Project Limits:
N 3rd St & N 4th St between Gateway Drive and University Avenue in Grand Forks,
North Dakota.
Figure 1 Project Limits
2.0 Existing Conditions
2.1 Land Use
Most of the land adjacent to N 3rd Street and N 4th Street is single family residential. At each end
of the project area for N 3rd Street and N 4th Street, the land use is commercial. The land
surrounding the project area on Gateway Drive is used for commercial purposes. The impacts of
these residents and businesses will be specified.
2.2 Existing Roadways
Figures 2, 3, and 4 show the existing typical sections for N 3rd Street, N 4th Street, and Gateway
Drive.
Figure 2 N 3rd Street Existing Typical Section
Figure 3 N 4th Street Existing Typical Section
Figure 4 Gateway Drive Existing Typical Section
2.3 Right of Way
The Right of Way (ROW) for N 3rd Street varies from 44 feet wide to 73 feet wide. The
roadway width varies from 28 feet to 43 feet. The berm on each side of the roadway varies from
1 foot to 15 feet. There is a 6-foot-wide sidewalk on each side of the roadway. The ROW for N
4th Street is 66 feet wide. The roadway width is 36 feet wide. There are berm widths of 15 feet on
each side of the roadway. There is a 6-foot-wide sidewalk on each side of the roadway. The
ROW width for Gateway Drive varies from 79 feet to 99 feet. There is a 4.5-foot-wide sidewalk
that is flush to the curb on each side of the roadway. There are varying widths of berm on each
side of the roadway.
2.4 Utilities
There are underground utilities within the area of the project. There are electrical,
telephone, and fiber optic cables beneath the ground. There are also stormwater and sanitary
lines underground. These underground utilities will need to be identified to ensure they are not
damaged during construction.
2.5 Traffic
2.5.1 Average Daily Traffic
Figure 5 shows the average daily traffic (ADT) for N 3rd Street, N 4th Street, Gateway
Drive, and the surrounding streets. These values are obtained from the Grand Forks GIS and
from the year 2022. N 3rd Street has an ADT of 1,005. N 4th Street has an ADT of 400. Gateway
Drive has an ADT of 16,380.
Figure 5 2022 Grand Forks GIS Traffic Volumes
2.5.2 Pedestrian Facilities
Figure 6 shows the current off-road bike facilities. The red line intersecting Gateway
Drive is a shared use tunnel open year-round. Shown in Figure 7 is the shared use path and the
entrances to the tunnel. The path has a branch that leads directly to Wilder Elementary School.
Figure 6 Existing Bike Facilities
Figure 7 Existing Shared Use Path and Tunnel
3.0 Project Design
Two different design alternatives were analyzed. One design provided minimal change to
the road geometry and layout. The other design contained a full overhaul of the layout and
geometry surrounding Wilder Elementary School. Table 1 below highlights the total cost and
The complete overhaul alternative was proceeded with because it provided the best traffic flow
and safety around Wilder Elementary School.
Table 1 Design Alternative Comparisons
Design Total Cost Construction Feasibility
Minimal Change $351,291.00 •Simplest
•37 Construction Days
•No Road Closure
Complete Overhaul $864,045.00 •Hardest
•109 Construction Days
•Road Closure and Lane Reduction
3.1 Complete Overhaul
The second alternative proposes major changes to the N 3rd Street, N 4th Street, and
Gateway Drive intersections. A complete overhaul redesign is made to the roadway layouts and
geometries. At the intersection of N 4th Street and Gateway Drive, a new traffic light system will
be employed. A raised median will run from the intersection of N 4th Street and Gateway Drive
to the intersection of Gateway Drive and N 2nd Street. This alternative brings greater construction
costs and more time for this project to be designed, approved, and constructed. A major concern
facing this alternative is preventing unauthorized left turns onto Gateway Drive from the streets
south of the intersection.
Figure 8 Alternative Two Gateway Drive and N 4th Street Intersection
Figure 9 Alternative 2 Gateway Drive, 11th Avenue N, and N 3rd Street Intersection
Figure 10 Alternative 2 Gateway Drive and N 3rd Street Intersection
Figure 11 Alternative 2 N 3rd Street Typical Section 3+00 to 32+00
Figure 12 Alternative 2 N 4th Street Typical Section 0+50 to 3+50, 7+00 to 37+00
Figure 8 displays the new layout for the proposed signalized intersection at Gateway
Drive and N 4th Street. A right turn lane is constructed on N 4th Street to head east onto Gateway
Drive. Property acquisition is obtained from Fox Radiators. The current inlet is turned into a type
C R-1733 manhole. Figure 9 shows the intersection of 11th Avenue N and Gateway Drive. In the
proposed layouts for the second alternative, on the north side of Gateway Drive and the N 3rd
Street/11th Avenue N intersection, the traffic signal is removed and the north leg of N 3rd Street is
converted into a right-in-right-out street. N 4th Street is turned into a signalized intersection.
Figure 10 portrays the proposed intersection for Gateway Drive and N 3rd Street. The
raised median extends through N 3rd Street and converts the intersection into right-in-right-out
only. A right lane is implemented heading east on Gateway Drive, which turns onto N 3rd Street.
This prevents backup of the through lane and allows for a comfortable right turn. The
intersection of Gateway Drive and N 3rd Street/11th Avenue N is converted to a right-in-right-out
intersection and the raised median prevents left turns. A crosswalk is designed at the intersection
of N 4th Street and Gateway Drive to redirect crossing and allow safe travel. It also gives a
crossing route for when the pedestrian underpass is flooded. N 4th Street on the south side is
widened to create room for turn lanes. On the north side of Gateway Drive, N 4th Street has a left
turn lane and a right/thru lane. The south side of Gateway Drive and N 3rd Street is turned into a
right-in-right-out street. A right lane is added to reduce the impact of eastbound traffic on
Gateway Drive. The median extends from N 4th Street to N 2nd Street to prevent unauthorized left
turns. 11th Avenue N is closed off and turned into a hammerhead turnaround. The catch basins
shown above are readjusted to the geometry of the hammer-ended section. Property acquisition is
acquired from Fox Radiators to create room for this change. This allows for extra pickup and
drop-off space and allows for easy access out of 11th Avenue N, as well as snow removal during
the winter months.
Figure 13 Wilder Elementary Pickup and Dropoff Zone
Figure 14 Alternative 2 N 4th Street Typical Section 3+50 to 7+00
Figure 1 shows a proposed pick-up/drop-off zone along the north side of N 4th Street,
adjacent to the school. No-parking signs are added for regular school hours to prevent clogging
of the lane during school hours. This allows for extra pick-up spots for parents and buses to pick
up children on the same side of the school, which reduces the chance of accidents occurring.
4.0 Drawings and Specifications
Special Details – Standard Drawings
5.0 Construction and Traffic Control
DESCRIPTION OF WORK
Throughout the project limits, the following work shall be done as directed by the Engineer and
as per the North Dakota Standard Specifications:
• Conversion of N 3rd Street & N 4th Street from One- way to Two-way Street
• Intersection Realignment at 4th Street & Gateway Drive
• Intersection Improvement at N 3rd Street & Gateway Drive
• Installation of new Traffic Signal at N 4th Street & Gateway Drive
• Construct new Right Turn Only Lane on Gateway Drive at N 3rd Street
5.1 Construction Stages
Stage 1
Convert 11th Avenue N & Gateway Drive to Hammer Head
A. Close 11th Avenue N between N 4th Street & Gateway Drive.
B. Remove existing traffic signal at 11th Avenue N & Gateway Drive
C. Construct hammerhead at 11th Avenue N & Gateway Drive to create Dead End
Stage 2
Convert N 4th Street to Two Way Street
A. Realignment of N 4th Street & Gateway Drive Intersection
B. Use Barricades to close N 4th Street between Gateway Drive & 11th Avenue N
C. Setup Detour Route for Southbound traffic N 4th Street traffic coming from Gateway
Drive
D. Detour all traffic from N 4th Street to N 5th Street & then 11th Avenue N back onto N 4th
Street
E. See Detour Plan in Traffic Control Section
F. Construction of New Sidewalk Ramp at Intersection
G. Install new Traffic Signal
Stage 3
Pave N 4th Street Between Gateway Drive & University Avenue
A. Remove and repair he Patches
B. Extend 4th Street Closure from Gateway Street to University Avenue
C. Street Parking will be moved to Rear of Houses
D. Detour School Buses to N 5th Street to University Ave then to N 3rd Street onto 10th
Avenue N for drop off & Pickup.
E. See Detour Plan in Traffic Control Plan
Stage 4
Convert N 3rd Street to Two Way Street.
A. Realignment of N 3rd Street & Gateway Drive Intersection
B. Use Barricades to close N 3rd Street between Gateway Drive & 10th Avenue N
C. Setup Detour Route for Northbound N 3rd Street traffic going to Gateway Drive
D. Detour all traffic from N 3rd Street to 10th Ave N & then N 5th Street back onto Gateway
Drive
E. See Detour Plan in Traffic Control Section
F. Extend Closure from Gateway Drive to University Avenue
G. HMA Pavement & Concrete Patches for N 3rd Street
The plan of action regarding traffic control and how to move vehicles, and pedestrians through
the construction of the proposed layout will be implemented in 3 phases. Highlighted below, are
those 3 phases highlighted in greater detail. It is important to note that N 3rd Street, and N 4th
Street will not be open to two-way traffic until full completion of construction, as it is not
feasible, and not safe to open until construction along Gateway drive is completed.
Phase 1
The area concerning Phase 1 is the intersection of 11th Avenue N and Gateway Drive. This part
of the process will include the removal of the current traffic signals; constructing the right turn
lane going into N 3rd Street, and construction of the hammer ended intersection as well as the
storm sewer adjustment.
Figure 15 Phase 1: Traffic Control Work Zones
Shown in Figure 1 is the proposed layout of the traffic control devices utilized during the
first phase. Shown in yellow represents work areas and road closures. Channeling devices
utilized will be tubular markers for daytime and speeds not exceeding 40 miles per hour. Road
closure barricades will be type III barricades with road closure signs attached, per NDDOT
standards. N 3rd Street is converted into a temporary right-out lane to prevent any confusion for
drivers planning to turn left onto Gateway Drive. 11th Avenue N, on both sides of Gateway
Drive, is closed to allow room to remove the current traffic signals, as well as the construction of
the hammer ended turnaround and the adjustments made to the storm sewer. Gateway Drive is
reduced to the outside lane in each direction to allow for construction of the raised median.
Phase 2
Phase 2 occurs at the intersection of N 4th Street and Gateway Drive. The scope of work
nucleus in this phase includes the installation of the new traffic signal, as well as the
implementation of signal timing and crosswalk adjustment. N 4th Street is widened to allow for
the added right turn lane. The conflicting storm sewer is readjusted. Gateway Drive is reduced to
the inside lane both ways to allow for construction room. Figure 14 below shows the lane
closures and work zones to complete these actions. Figure 15 below, highlighted in purple
arrows, shows a detour route to manage the partial N 4th Street closure.
Figure 16 Phase 2: Traffic Control Work Zones
Figure 17 Phase 2: Traffic Control Detour Map
Phase 3
The last phase opens N 3rd Street and N 4th Street as new two-way pairs. This will include
repaving N 3rd Street and N 4th Street, beginning with N 4th Street. Road closure extends all the
way from 11th Avenue N to University Avenue and a detour plan enacts. It is highlighted in
purple arrows in Figure 1. 10th Avenue N remains accessible to allow for bus pick up and drop
off. Like N 4th Street, N 3rd Street closes from Gateway Drive, extending to University Avenue.
N 4th Street will open to two-way traffic and all N 3rd Street traffic is routed to N 4th Street.
Signage is removed and readjusted along the street length extending from Gateway Drive to
University Avenue, turning the intersections of N 3rd Street, N 4th Street, and University Avenue
into four-way stops. To adjust for new traffic flows, pickup and drop off zones along N 4th Street
are created along the side of the school. Pavement markings are added along the whole project
area.
Figure 18 Phase 3: N 4th Street Detour Map
6.0 Cost Estimates
Table 2 shows the cost estimate. The estimate includes paving the entirety of N 3rd St and
N 4th St with asphalt and milling between 00+50 and 11+50 on N 3rd St. Asphalt is also used to
construct the hammerhead on 11th Avenue N. The most expensive bid items are the Gateway
Drive and N 4th Street traffic signal system, the curb, gutter, and median concrete, and the
asphalt paving. Traffic control signs are estimated using “Traffic Control Requirements for
NDDOT Operations on Highways and Streets” for lane closures on a multi-lane road with
reduced speed. The standard drawing for the traffic control is shown in Figure 17. Table 3 shows
the number of traffic control signs needed for each phase. Table 4 shows the 2023 NDDOT
specifications for temporary traffic control. The specifications are listed in appendix A.
Table 2 Cost Estimation
Description $/unit Quantity Unit Total
Removal of Trees $ 1,500.00 8 EA $ 12,000.00
Removal of Concrete Sidewalk $ 36.00 140 SY $ 5,040.00
Removal of Curb and Gutter $ 11.00 675 LF $ 7,425.00
Removal of Concrete Pavement $ 36.00 1000 SY $ 36,000.00
Removal of Asphalt $ 17.00 70 SY $ 1,190.00
Removal of Signs $ 10.00 65 EA $ 650.00
Common Excavation $ 8.00 2200 SY $ 17,600.00
Obliteration of Pavement Markings $ 2.00 500 SF $ 1,000.00
Inlet Protection $ 150.00 11 EA $ 1,650.00
Geosynthetic Material Type G $ 2.00 2200 SY $ 4,400.00
Adjust Manhole $ 2,000.00 1 EA $ 2,000.00
Adjust Storm Inlet $ 1,400.00 2 EA $ 2,800.00
Detectable Warning Panel $ 52.00 8 EA $ 416.00
Epoxy PVMT MK Line $ 2.00 2500 SF $ 5,000.00
Epoxy PVMT MK Message $ 16.00 250 SF $ 4,000.00
Revise Signal System $ 50,000.00 1 EA $ 50,000.00
Remove Traffic Signal System $ 30,000.00 1 EA $ 30,000.00
Tubular Markers $ 6.00 90 EA $ 540.00
Delineator Drums $ 22.00 90 EA $ 1,980.00
Type III Barricade $ 90.00 32 EA $ 2,880.00
Sequencing Arrow Panel-Type B $ 70.00 2 EA $ 140.00
Traffic Control Signs $ 3.00 110 UNIT $ 330.00
Traffic Signs $ 30.00 24 EA $ 720.00
Superpave FAA 43 $ 70.00 1275 TON $ 89,250.00
Concrete Pavement $ 270.00 1300 SY $ 351,000.00
Sidewalk Concrete $ 120.00 125 SY $ 15,000.00
Curb & Gutter- Type 1 $ 50.00 1800 LF $ 90,000.00
Milling Pavement Surface-2 INCH $ 6.50 3400 SY $ 22,100.00
Mobilization at 10% $ 75,184.60
Contract Bond at 1% $ 7,518.46
Total $ 838,173.21
Figure 19 Gateway Drive Traffic Control Diagram
Table 3 Traffic Control Signs by Phase
Sign
Phase
Total 1 2 3
End Road Work 2 2 2 6
Speed Limit Enforced- Minimum Fee $80 when
workers present 3 3 2 8
End Detour 1 1 2 4
Detour Arrow 3 3 6 12
Road Work Ahead 3 2 4 9
Lane Ends 3 3 0 6
25 MPH Speed Limit 3 3 4 10
Speed Reduction Ahead 2 2 0 4
Road Closed Ahead 4 1 18 23
Detour Ahead 1 1 6 8
Road Closed (mounted on Barricade) 2 2 16 20
Total 110
Table 4 NDDOT 2023 Traffic Control Specifications
Spec & Code
Description UNIT Phase
1 2 3
704-1018 Lane Closure EACH 3 3 0
704-1052 Type III Barricades EACH 6 4 32
704-1060 Delineator Drums EACH 40 50 0
704-1067 Tubular Markers EACH 50 90 0
704-1086 Sequencing Arrow Panel-Type B EACH 2 2 0
704-1500 Obliteration of PVMT MK SF 800 100 0
7.0 Conclusion and Recommendations
7.1 Conclusion
The transformation of N 3rd Street and N 4th Street from one-way to two-way roads in
Terrific Forks, North Dakota, presents a huge metropolitan arranging drive pointed toward
improving security, effectiveness, and maintainability inside the task region. The existing traffic
signals and their proximity to the proposed changes are analyzed to ensure that the signal design
aligns with the city’s traffic control standards and guidelines. Through an exhaustive examination
of the current circumstances, including land use, street setups, option to proceed, utilities, and
traffic designs, as well as thought of different plan choices, the venture group has recognized key
difficulties and potential open doors for development. Elective One spotlights insignificant
changes to the current format, principally changing over N 3rd Street and N 4th Street into two-
way roads while consolidating raised medians and assigned go paths to advance traffic stream
and improve security. Elective Two, then again, proposes major overhauls and crossing point
realignments to address traffic concerns more thoroughly, including the establishment of new
traffic lights and the production of turn paths and pickup/drop-off zones close to More stunning
Primary School. The impact on the existing businesses and other surrounding existing structures
are considered in preserving the right-of-way and possible implications for pedestrians and
school access. All through the plan cycle, a few difficulties were distinguished and tended to,
including obliging existing foundation, guaranteeing person on foot security, limiting
interruptions to organizations and inhabitants, and complying to traffic light principles and rules.
Nitty gritty development plans and traffic signal measures have been illustrated to work with the
smooth execution of the proposed changes while alleviating possible interruptions to traffic and
encompassing exercises.
7.2 Recommendation
Considering the exhaustive examination and assessment of the other options, as well as
considering the project’s goals and the recognized difficulties, the proposal is to continue with
Elective Two for the change of N third Road and N fourth Road into two-way streets.
Elective Two offers a more comprehensive way to deal with tending to somewhere safe
and secure, proficiency, and supportability worries inside the task region. By executing major
overhauls and crossing point realignments, including the establishment of new traffic lights and
the making of assigned turn paths and get/drop-off zones, Elective Two gives a stronger answer
for improve traffic stream and upgrade security for all road users, especially around wilder
Elementary School.
Besides, Elective Two shows a more noteworthy potential for long haul benefits,
including further developed versatility, diminished clog, and upgraded metropolitan experience
for inhabitants and guests. While Elective One offers a more direct methodology with
insignificant changes, it may not completely address the complex traffic elements and wellbeing
worries inside the undertaking region.
Hence, it is recommended to continue with Elective Two, likely to additional partner
meeting, nitty gritty designing examination, and administrative endorsements, to guarantee
fruitful execution and expand the venture's positive effect on the local area. Moreover,
progressing observing and assessment ought to be directed to evaluate the adequacy of the
proposed changes and address any arising issues or concerns promptly. Other factors considered
in the process of designing alternatives for the idea of transforming N 3rd Street and N 4th Street’s
one-ways are the optimization of traffic signals, working within traffics codes, cost, and possible
limitations and constraints.
8.0 References
https://www.dot.nd.gov/divisions/programming/docs/trafficops.pdf
https://www.gfgis.com/Html5Viewer/index.html?viewer=PublicViewer
https://www.dot.nd.gov/divisions/programming/docs/trafficops.pdf
- CE 483 Transpo Midterm 2-29-24.pdf
- N 3rd St 1
- Sheets and Views
- N 3rd St 1
- N 3rd St 2
- Sheets and Views
- N 3rd St 2
- N 4th St
- Sheets and Views
- N 4th St