Running Case Brainstorming and Schedule Development

profilektzjoey24d
responsibility-assignment-matrix.docx

RESPONSIBILITY ASSIGNMENT MATRIX

Project Title:

Date Prepared:

Person 1

Person 2

Person 3

Person 4

Etc.

Work package 1

R

C

A

Work package 2

A

I

R

Work package 3

R

R

A

Work package 4

A

R

I

C

Work package 5

C

R

R

A

Work package 6

R

A

I

Etc.

C

A

R

R

R = Responsible: The person performing the work.

A = Accountable: The person who is answerable to the project manager that the work is done on time, meets requirements, and is acceptable.

C = Consult: The person who has information necessary to complete the work.

I = Inform: This person should be notified when the work is complete.

Page 1 of 1