Reporting Performance

profilejugxyaev
ReportingPerf.docx

14–1 Do cost overruns just happen, or are they caused?

14–2 What impact would there be on BCWS, BCWP, ACWP, and cost and schedule variances as a result of the:

1. Early start of an activity on a PERT chart?

2. Late start of an activity on a PERT chart?

14–3 Alpha Company has implemented a plan whereby functional managers will be held totally responsible for all cost overruns against their (the functional managers’) original estimates. Furthermore, all cost overruns must come out of the functional managers’ budgets, whether they be overhead or otherwise, not the project budget. What are the advantages and disadvantages of this approach?

14–4 What would be the result if all project managers decided to withhold a management reserve? What criteria should be used for determining when a management reserve is necessary?

14–5 Consider a situation in which several tasks may be for one to two years rather than the 200 hours normally used in the work-package level of the WBS.

1. How will this affect cost control?

2. Can we still use the 50-50 rule?

3. How frequently should costs be updated?

14–6 Complete the table below and plot the EAC as a function of time. What are your conclusions?

Cumulative Cost, in Thousands

Variance $

Week

BCWS

BCWP

ACWP

Schedule

Cost

EAC

1

50

50

25

2

70

60

40

3

90

80

67

4

120

105

90

5

130

120

115

6

140

135

130

7

165

150

155

8

200

175

190

9

250

220

230

10

270

260

270

11

300

295

305

12

350

340

340

13

380

360

370

14

420

395

400

15

460

460

450

14–7 Calculate the total price variance for direct labor and the labor rate cost variance from the following data:

Direct Material

Direct Labor

Planned price/unit

$ 10.00

$ 22.00

Actual units

9,300

12,000

Actual price/unit

$ 9.25

$ 22.50

Actual cost

$86,025,00

$270,000

14–8 Companies usually estimate work based upon man-months. If the work must be estimated in man-weeks, the man-month is then converted to man-weeks. The problem is in the determination of how many man-hours per month are actually available for actual direct labor work.

Your company has received a request for proposal (RFP) from one of your customers and management has decided to submit a bid. Only one department in your company will be required to perform the work and the department manager estimates that 3,000 hours of direct labor will be required.

Your first step is to calculate the number of hours available in a typical man-month. The Human Resources Department provides you with the following yearly history for the average employee in the company:

· Vacation (3 weeks)

· Sick days (4 days)

· Paid holidays (10 days)

· Jury duty (1 day)

1. How many direct labor hours are available per month per person?

2. If only one employee can be assigned to the project, what will be the duration of the effort, in months?

3. If the customer wants the job completed within one year, how many employees should be assigned?