Signature Assignment: Choosing a Methodology
Name of task Duration Predecessors
Recreation and Wellness Intranet Project 180 days April-October 2021
Project set-up
Pre-plan ideas and objectives 2 days 4/1/2021 4/2/2021
Assign Roles 1 day 4/3/2021 4/3/2021 4
Setup a work location for project 2 days 4/3/2021 4/4/2021 5
Project set-up complete 0 days 4/4/2021 4/4/2021 6
Employee Registration section
Analysis
Requirement gathering 10 days 4/5/2021 4/15/2021 7
Draft requirements doc 15 days 4/5/2021 4/20/2021 10
Review Requirements 2 days 4/19/2021 4/21/2021 11
Sign-off on Requirements 1 day 4/21/2021 4/21/2021 12
Design
High level design doc. 15 days 4/21/2021 5/6/2021 13
Design Review 20 days 5/6/2021 5/26/2021 15
Build
Component 1 (Registration rec. pr 60 days 5/27/2021 7/27/2021 16 Component 1 testing 30 days 7/28/2021 8/28/2021 18
Component 2 (Registration company programs)60 days 5/27/2021 7/27/2021 16
Component 2 testing 30 days 7/28/2021 8/28/2021 20
Component 3 (Data tracking) 30 days 5/27/2021 6/27/2021 16
Component 3 testing 20 days 6/28/2021 7/18/2021 22
Component 4 (Rewards Program) 30 days 5/27/2021 6/27/2021 16
Component 4 testing 20 days 6/28/2021 7/18/2021 24
Quality Assurance Test
Testing all programs as once 30 days 8/30/2021 9/30/2021 25
Project End
Obtain client final sign off 1 day 10/1/2021 10/1/2021 27
Provide project report 1 day 10/2/2021 10/2/2021 29
Project completed 0 days 10/2/2021 10/2/2021 30
Predecessors Notes
Throw around any ideas amongst the team
Figure out what needs to be in the program no matter what
*** Important
***Follow requirements
note any issues
***Follow requirements
note any issues
***Follow requirements
note any issues
***Follow requirements
note any issues
find any flaws before final sign off
**Important
Figure out what needs to be in the program no matter what