Name of task Duration Predecessors

Recreation and Wellness Intranet Project 180 days April-October 2021

Project set-up

Pre-plan ideas and objectives 2 days 4/1/2021 4/2/2021

Assign Roles 1 day 4/3/2021 4/3/2021 4

Setup a work location for project 2 days 4/3/2021 4/4/2021 5

Project set-up complete 0 days 4/4/2021 4/4/2021 6

Employee Registration section

Analysis

Requirement gathering 10 days 4/5/2021 4/15/2021 7

Draft requirements doc 15 days 4/5/2021 4/20/2021 10

Review Requirements 2 days 4/19/2021 4/21/2021 11

Sign-off on Requirements 1 day 4/21/2021 4/21/2021 12

Design

High level design doc. 15 days 4/21/2021 5/6/2021 13

Design Review 20 days 5/6/2021 5/26/2021 15

Build

Component 1 (Registration rec. pr 60 days 5/27/2021 7/27/2021 16 Component 1 testing 30 days 7/28/2021 8/28/2021 18

Component 2 (Registration company programs)60 days 5/27/2021 7/27/2021 16

Component 2 testing 30 days 7/28/2021 8/28/2021 20

Component 3 (Data tracking) 30 days 5/27/2021 6/27/2021 16

Component 3 testing 20 days 6/28/2021 7/18/2021 22

Component 4 (Rewards Program) 30 days 5/27/2021 6/27/2021 16

Component 4 testing 20 days 6/28/2021 7/18/2021 24

Quality Assurance Test

Testing all programs as once 30 days 8/30/2021 9/30/2021 25

Project End

Obtain client final sign off 1 day 10/1/2021 10/1/2021 27

Provide project report 1 day 10/2/2021 10/2/2021 29

Project completed 0 days 10/2/2021 10/2/2021 30

Predecessors Notes

Throw around any ideas amongst the team

Figure out what needs to be in the program no matter what

*** Important

***Follow requirements

note any issues

***Follow requirements

note any issues

***Follow requirements

note any issues

***Follow requirements

note any issues

find any flaws before final sign off

**Important

Figure out what needs to be in the program no matter what

  • Sheet1