Project management report
Integrated Project Plan
Urban Bicycle GoToMarket Project - Group 5
Group Member Names:
Table of Contents
1.0 Version Control / Summary of Changes....................................................................................4
2.0 Scope Management....................................................................................................................5
2.1 Scope Statement.............................................................................................................5
2.2 Summary of WBS..........................................................................................................7
2.3 Stakeholder Register......................................................................................................9
2.4 Scope Baseline Statement............................................................................................11
3.0 Schedule & Time Management...............................................................................................12
3.1 Milestone List..............................................................................................................12 3.2 Summary of Project Schedule......................................................................................12
3.3 Schedule Baseline Statement.......................................................................................14
4.0 Communication Plan................................................................................................................15
4.1 Communication Plan....................................................................................................16
4.2 Communication Matrix................................................................................................16
5.0 Cost & Budget Management....................................................................................................18
5.1 Initial Cost Statement & Cost Estimate.......................................................................18
5.2 High Level Cost Estimates………………………..…………………………………19
5.3 Cost Baseline Statement………………………………..…………………………....20
5.4 Financial Report……………………………………………………………………...21
5.5 Contingency Reserve Policy & Request……………………………………………..22
6.0 Risk Management………………………………………………………………………...….23
6.1 Risk Management Plan………………………………………………………………23
6.2 Risk Register………....………………………………………………………………27
7.0 Quality Management ……………………………………....………………………………...28
7.1 Quality Management Plan……....……………………………………………………28
7.2 Quality Metrics………………………………………………………………..……..28
8.0 Integrated Change Control Policy & Change Request Template…………….…....………...33
8.1 Change Control Policy ………………………………………………………………33
8.2 Change Request Form ...……………………………………………………………..40
References......................................................................................................................................42
1.0 Summary of Changes
|
Version Number |
Week |
Team Leader Name |
New Sections Added |
Changes Made to Previous Sections |
|
1.0 |
1-2 |
Chen-Hsiao Shih |
Summary of WBS and Stakeholder Register issued as a separate document |
None |
|
2.0 |
3-4 |
Federico Boni |
2.0 Scope Management, 3.0 Schedule & Time Management, and 5.0 Cost & Budget Management |
None |
|
3.0 |
5-6 |
Chen-Fang Hung |
4.0 Communication Plan, Scope and Schedule Baseline Statements |
-Updated 3.2 Summary of Project Schedule -Updated Cost Estimates by cutting down the labor costs |
|
4.0 |
7-8 |
Nan Xiang |
6.0 Risk Management Plan including the Risk Register 7.0 Quality Management Plan & Statement Adding Contingency Reserve Policy & Request in 5.0 Cost & Budget Management 10.0 Integrated Change Control Process & Change Request Form
|
Updated the Project Schedule baseline and cost estimates from MS project adjustment. |
2.0 Scope Management
2.1 Scope Statement
Project Name: Urban Bicycle GoToMarket Project-Group 5
1. Project Scope
Project Objectives will be,
· The stretch goal will be to sell 200 bikes in total by December 31, 2020
· To sell 50 The Don bikes by December 31, 2020
· To reach out to 15+ more new target companies and charity organizations to implement wellness programs
· To develop 3+ more featured online workshops regarding bike product promotions
In order to accomplish these goals, our major deliverables include,
1. Project Planning
2. Target Organizations
3. Event Design and Production
4. Outreach Event Implementation
5. Customer Satisfaction Report
2. High Level Customer/ Product Requirements
Business Requirements:
· The stretch goal is to sell 200 bikes in total or sell 50 The Don by December 31, 2020
· Successfully implement outreach wellness programs to target bike-friendly business companies and community organizations
Functional Requirements:
· Reach out to large scale corporates in technology, banking, or accounting fields such as Salesforce, Hubspot, Red Hat, Inc. to seek collaborations
· Cooperate with Boston local community organizations such as the Charles River Wheelers or cycling charity organizations like the Ride to Conquer Cancer as a distributor of cycling accessories and essentials
· Design presentations and workshops featuring our bike products and cycling accessories
· Recruit speakers and certificated fitness trainers to host outreach programs and workshops
· Conduct and analyze customer satisfaction report and sales report
· Revise the content of the events with negative sales report
3. User acceptance criteria
The customer satisfaction survey (CSAT) will be designed by following the metrics of Overall Satisfaction Measure and a series of Attribute Satisfaction Measurements, and will be distributed for participants at the end of the events. Only responses of 4 (satisfied) and 5 (very satisfied) are included in the calculation as positive feedback. The calculation will be (Number of satisfied customers (4 and 5) / Number of survey responses) x 100 = % of satisfied customers.
4. Project boundaries or exclusions
The geographic target market for this project plan will be more focused on local Boston and the Northeast USA. Long-term target market plans in Australia will not be included in this document.
5. Project constraints
· Scope: The geographic market is more focused on Northeast USA
· Time: The sales goals should be accomplished in the end of this year
· Risk: The global pandemic might affect the customer engagement in workshops and outreach events
· Cost: The sponsor didn’t assign a specific amount of the budget. We conducted our cost estimation based on the calculation in MS Project
2.2 Summary of WBS
The summary of WBS below is retrieved from MS project
2.3 Stakeholder Register
|
Stakeholder Position/Role |
Type of Stakeholders |
Stakeholder Expectation(s) |
Stakeholder Interest |
Influence on Project Result |
Stakeholder Management Strategies |
|
Position in the organization or role in project |
Internal or External |
High level needs or expectations for the project and/or product |
High/ Med/Low |
Supporter/Opposed/ Neutral |
Strategies and tactics to maximize positive stakeholder influence and minimize or neutralize negative stakeholder influence. |
|
CEO, Gavin Brauer |
Internal |
High level expectations for the success of the project |
High |
Supporter |
-Regular updating meetings with project teams
|
|
Target companies, Such as Salesforce and Red Hat, Inc. |
External |
High level expectations for the quality of the products and bike supplies |
High |
Supporter |
-Implement the wellness programs -Provide updated presentations about the products |
|
Charity Ride Teams (The Ride to Conquer Cancer) |
External |
High level expectations for the quality of the products and bike supplies |
High |
Supporter |
-Provide updated presentations about the products -Regular meetings in order to know what kinds of supplies they need for the rides |
|
Project Manager |
Internal |
High level expectation -Completion of the project with quality and success |
High |
Supporter |
-Check the working state regularly |
|
Project Team Members |
Internal |
High level expectation of the project objective which can show the ability |
Medium |
Supporter |
-Check the working state regularly |
|
Coaches of Tiny Habits |
Internal |
Low expectation -They are doing the regular work |
Low |
Neutral |
-Check the working state twice a month with the data of challenge and feedback from them and customers |
|
Customers |
External |
High expectations for the value of the bike and high satisfaction for overall the quality of the product. |
High |
Supporter |
-Provide specific information on the bikes to the customers -Market research to determine the customer’s expectations |
|
Government |
External |
External High level expectations of the quality of the product and meet safety standards for customers. |
Low |
Neutral |
-Check regulations and specifications for product safety standards |
|
Linkedin Connections |
External |
Medium level expectations for the updates of the products |
Medium |
Neutral |
-As potential resources for outreach programs, we should do market research and implement programs or presentations of what they need -As regular clients, we should regularly update the newest information on our products |
|
Carrier Company |
External |
Low level expectation of the project and take responsibility to transport the bike |
Medium |
Neutral |
-Check the failure rate of bikes during the shipping |
|
HR Manager Comment by Chen-Hsiao Shih: We added three stakeholders based on the resources in our MS project |
Internal |
Low level expectation of the project and take the responsibility to interview the candidates of online workshop’ speaker |
Medium |
Supporter |
- Updating the state of interview with the manager frequently |
|
Speaker Comment by Chen-Hsiao Shih: We added three stakeholders based on the resources in our MS project |
External |
Medium level expectation of the project because the good result of the workshop can build the reputation of the speaker. |
Medium |
Supporter |
- Communicating with the speaker frequently and check the content of the presentation |
|
Event Planning Agency Comment by Chen-Hsiao Shih: We added three stakeholders based on the resources in our MS project |
External |
Medium level expectation of the project because the agency can earn the reputation from it. |
Medium |
Supporter |
- Communicate with the agency frequently when we work together. |
2.4 Scope Baseline Statement Comment by Chen-Fang Hung: We added the section of the scope baseline statement after setting the baseline in our MS project
This project started on April 20th, 2020 and will end on December 23rd, 2020 with a 177-day total baseline duration and $17,621.99 as the total baseline cost. This project is created to implement 15+ outreach events at bicycle-friendly coperates in technology, banking and accounting fields, local communities, and charities in major cities in Northeastern America/Canada such as Boston, New York, and Toronto. The scope of the project will be to successfully implement cycling wellness programs to promote the bikes (1~2 events per month) and to reach the sale goal of selling 50 the Don at the end of December. Our scope baseline will be adjusted in the future based on the monthly sales reports and the changes of the requirements which will be made by the sponsor. The baseline will be updated after every project review meeting with the sponsor at milestones.
3.0 Schedule & Time Management
3.1 Milestone List
The milestones of this project are listed below and also include the expected completion date of each milestone.
|
Milestone |
Name |
Date |
Description |
|
MS1 (1.3.10) |
Project Plan Completed |
8/10/2020 |
Completed the project planning phase |
|
MSda2 (1.4.1.4) |
Target Organization Terminated |
9/11/2020 |
Contracted with the ideal business companies, charities, and community organizations for collaboration |
|
MS3 (1.4.2.3) |
Event Design Concluded |
10/2/2020 |
Accomplished the event design and preparation |
|
MS4 (1.4.3.4) |
Outreach event implementation Completed |
10/28/2020 |
Completed the outreach events, including workshops, wellness programs, and charity rides |
|
MS5 (1.5.2.3) |
Customer Satisfaction Report Concluded |
11/18/2020 |
Completed the analysis of customer satisfaction survey report |
|
MS6 (1.6.4) |
Project Closed |
12/23/2021 |
Completed the Urban Bicycle GoToMarket Project |
3.2 Summary of Project Schedule
The table below is the summary of the schedule for the high-level deliverables of this project. The project started on April 20th, 2020, and is expected to be completed on December 25th, 2020. This project will take 249 days to finish (the duration of the project is 179 days).
|
Deliverable |
Duration |
Beg. Date |
End Date |
|
1.1 Staffing |
3 days |
04/20/2020 |
04/23/2020 |
|
1.2.1 Project Charter |
7.5 days |
04/23/2020 |
05/05/2020 |
|
1.2.2 Stakeholder Management Plan |
13.5 days |
05/05/2020 |
05/22/2020 |
|
1.3.1 Scope Management Planning |
12 days |
05/22/2020 |
06/09/2020 |
|
1.3.2 Schedule Management Planning |
10.5 days |
06/09/2020 |
06/24/2020 |
|
1.3.3 Cost Management Planning |
10 days |
06/16/2020 |
06/30/2020 |
|
1.3.4 Quality Management |
5 days |
06/30/2020 |
07/07/2020 |
|
1.3.5 Recourse Management |
4 days |
07/07/2020 |
07/13/2020 |
|
1.3.6 Communication Management |
2 days |
07/13/2020 |
07/15/2020 |
|
1.3.7 Risk Management |
9 days |
07/15/2020 |
07/28/2020 |
|
1.3.8 Procurement Management |
4 days |
07/28/2020 |
08/03/2020 |
|
1.3.9 Change Management |
5 days |
08/03/2020 |
08/10/2020 |
|
1.4.1 Target Organization |
29 days |
08/10/2020 |
09/18/2020 |
|
1.4.2 Event Design |
40.5 days |
08/10/2020 |
10/06/2020 |
|
1.4.3 Event Implementation |
19 days |
10/06/2020 |
11/02/2020 |
|
1.5.1 Project Performance Report |
9 days |
10/30/2020 |
11/12/2020 |
|
1.5.2 Customer Satisfaction Report |
6.5 days |
11/12/2020 |
11/20/2020 |
|
1.5.3 Project Quality |
8 days |
11/20/2020 |
12/02/2020 |
|
1.6.1 Project Closure Report |
10 days |
12/02/2020 |
12/16/2020 |
|
1.6.2 Lessons Learned |
6 days |
12/16/2020 |
12/24/2020 |
|
1.6.3 Project Sign-off |
1 days |
12/24/2020 |
12/25/2020 |
3.3 Schedule Baseline Statement
For this project, the schedule baseline is set as the start date of April 20, 2020, and the date of December 25, 2020. The project duration is 179 days. The project schedule baseline affected by project scope and anything that changed or adjusted to the project scope will impact on project schedule baseline. The project manager and project sponsors have authority to approve and evaluate any changes requests and also to re-baselines if the schedule has significantly impacted by project scope changes. The example conditions of project scope changed and delayed critical path tasks will be impacted on schedule baseline, and the project schedule baseline will only be updated based on approval given from the project manager and project sponsor.
4.0 Communication Plan
4.1 Communication Plan
The communication approaches that we have used for operating this project include emails, virtual conference calls, and message channels. Message applications such as Whatsapp are used by the project manager to assign, track, and update the progress status of daily tasks. The messages will be sent, received, and coordinated between the project manager and the project team members. Virtual conference calls will be a more formal communication approach that is used by the project manager, the project team, the stakeholders, and even the sponsor. These meetings are hosted to let the project manager and project team demonstrate a certain status of the project to the sponsor and the stakeholders, to gather their feedback, to discuss the next step of the project. The messages in the conference calls will be sent by the project manager, coordinated between the project manager, the project team, and the stakeholders, and eventually approved by the sponsor. After the project status meetings/reviews, documented project status reports will also be created by the project manager and sent to the stakeholders and team members in order to ensure everyone could receive the information.
4.2 Communication Matrix (by Method)
|
Communication Type |
Frequency |
Goals |
Owner |
Audience |
|
By Email |
||||
|
Project Status Report |
Weekly |
-Review the status of the project, including schedule, budget, and scope -Discuss the upcoming tasks and potential risks |
Project manager |
-Stakeholders -Project team |
|
Customer Satisfaction Survey |
Once the event is over |
-Distribute the survey to all attendees to gather feedback |
Project manager |
Event attendees/customers |
|
Customer Satisfaction Report |
Once the event is over |
-Demonstrate the customers' attitudes towards the content of the events -Review and adjust the content of the events |
Project manager |
-Stakeholders -Project team |
|
By Face-to-face or Virtual Meetings |
||||
|
Kick-off Meetings |
Once |
-Introduce the project, the stakeholders, and the sponsor to the project teams -Indicate the sponsor’s the requirements and project objectives |
Stakeholders (Professors) |
-Project sponsor -Stakeholders -Project manager |
|
Project Team Meetings |
As needed |
-Review the status of the project -Distribute weekly new tasks with teams |
Project manager |
Project team |
|
Project Review |
At milestones |
-Review the accomplished deliverables -Gather feedback from the sponsor -Check in with sponsor if their requirements are achieved |
Project manager |
-Project team -Sponsor |
|
By Slack/Whatsapp Message Channel |
||||
|
Task Progress Updates |
Daily |
-Distribute tasks to team members -Share daily progress of the accomplished tasks |
Project manager |
Project team |
5.0 Cost & Budget Management Comment by Chen-Fang Hung: We adjusted and updated the newest cost estimates by cutting down the labor costs, and also revised the cost baseline statement after receiving the professor's feedback regarding our originally unaffordable costs
5.1 Project Cost Statement
The estimation method used to gather estimates for this project was bottom up and top down estimation. The initial costs for the phases was developed using the top down estimation method because it provides a high-level estimate of what it would cost to have each phase of the project completed, based on the amount of effort required and the availability of resources.
The project manager is responsible for managing and reporting on the project’s cost throughout the duration of the project. Additionally, the project manager would use Earned Value Management for monitoring and controlling the project cost. The project manager is also responsible for reporting any cost deviations to the sponsor and devising ways to get the project back on track.
Assumptions were made on how the cost should be varied among the project phases taking into consideration the amount of effort that would be required to complete the work of the different phases. For instance, the execution and monitoring & controlling phases would require the most work effort, and as a result would cost more, this assumption was made based on knowledge from previous projects.
In order to determine the cost to complete the project, costs were assigned at the work package level of the work breakdown structure; utilizing the bottom up estimating approach. By using the bottom up estimating method for the activities, the estimated cost of effort for the resources to work on the project was derived. When the estimates are made at the activity level the cost amount rolls up to the deliverables, which enables the project manager to determine the overall cost of the project deliverable.
The tables below contain a breakdown of the cost estimates for the planning and execution phases deliverables.
|
Monitoring & Controlling Phase Tasks |
Hours By Deliverables/Tasks |
Cost Estimates |
|
Control & monitor risks |
115 hrs |
$980.00 |
|
Control & monitor cost |
133 hrs |
$1,120.00 |
|
Control & monitor schedule |
130 hrs |
$1,080.00 |
|
Control & monitor quality |
140 hrs |
$1,180.00 |
|
Totals |
518 hrs |
$4,360.00 |
|
Execution Phase Deliverables |
Hours By Deliverables |
Cost Estimates |
|
Target Organizations |
345 hrs |
$1,220.00 |
|
Survey |
10 hrs |
$180.00 |
|
Event Design and Production |
202 hrs |
$3,172.00 |
|
Online workshop |
70 hrs |
$360.00 |
|
Wellness program |
120 hrs |
$2,660.00 |
|
Community Events |
102 hrs |
$520.00 |
5.2 High Level Cost Estimates
As the project proceeds and any additional costs become known, this cost estimate will be refined and communicated to all project stakeholders. Currently, the project is below the set project budget, at the amount of $8,112.00. The budget for the project is currently realistic and can be met, providing there are no changes to the project scope, schedule and cost as these can all increase the project budget. Resources for the deliverables have all been assigned and the table below depicts the costs for the high-level project deliverables.
The table below displays the high-level costs for the high-level deliverables in the project.
|
Project Deliverables |
Cost |
|
Project Charter |
$509.99 |
|
Stakeholder Management |
$1,200.00 |
|
Project Planning |
$4,360.00 |
|
Target Organizations |
$1,220.00 |
|
Survey |
$180.00 |
|
Event Design and Production |
$3,172.00 |
|
Online workshop |
$360.00 |
|
Wellness program |
$2,660.00 |
|
Community Events |
$520.00 |
|
Advertising |
$2,000.00 |
|
Questionnaires |
$100.00 |
|
Flyers |
$100.00 |
|
Monitoring and Control |
$4,360.00 |
|
Project Closure |
$1,360.00 |
5.3 Cost Baseline Statement
The original cost baseline for the project was set on May 2, 2020, with a current project cost of $17,621.99 . Like the schedule baseline, the cost baseline would also be affected by changes to the scope baseline. Any changes made to the cost baseline must be reviewed by the project manager and approved by the project sponsor.
The following conditions would cause changes to the cost baseline: padding costs, addition of resources to the project, scope changes, delays in the completion of critical path activities and changes to the project schedule. The cost baseline will be adjusted in situations where more resources such as team members are needed to help speed up the completion of the online workshop process. The cost baseline will not be adjusted for additional fees incurred from the vendor.
5.4 Financial Report
This report indicates all the resources that have been used in this project and the detailed information of each such as the specific used amount of each resource. All the resources including labor and non-labor resources are exactly assigned to each activity. The current cost baseline amount is $20,911.99 including the contingency reserve and this amount is calculated by the information provided above. Comment by Chen-Fang Hung: We updated the current cost baseline by including the contingency reserve
5.5 Contingency Reserve Policy & Request
Contingency
In a project management environment, uncertainties often arise. Thus, due to risks and uncertainties associated with projects, Team 5 added a reserve amount to the estimated project cost. This reserve amount, known as contingency, will be to absorb the monetary impact of the risks and to prevent cost overrun. The contingency funds are calculated on the basis from their probability of occurrence. The cost associated with these risks have been calculated based on the work to be done in order to mitigate or avoid the specific task.
After identifying these 12 risks, Team 5 will develop an alternative method for accomplishing the project goal.
There are various ways to determine the contingency reserve. Some of them include:
● Percentage of the Project’s Cost
● Expected Monetary Value
● Decision Tree Analysis
● Monte Carlo Simulation
Knowing that the project will be focused on the Expected Monetary Value method. The Expected Monetary Value is a statistical technique that is used to quantify the risks, which will help the project manager to calculate the contingency reserve. This technique is used in medium to high- cost projects where we have enough resources and cannot risk the failure of the project because the stakes are high.
Based on the previous quantitative analysis, for example risk #1 has a 55 percent probability of occurring and a cost impact of $600. The EVM for this risk event is (0.55* $600), or $330. To compensate for this risk event, the contingency reserve needs $330. By adding the EVM of each risk results in the total contingency reserve for the project. Thus adding EVM from risk 1 to 12, we may need to add a contingency reserve of $1,830 to our budget to cover all identified risks.
Funds Request
In order to implement the preventive measures, we believe that it will be beneficial for the Don project manager to submit a fund request template or form to the board. A budget review committee will be established and will meet biweekly to review requests for additional funding.
That form from the project manager should also provide a summary description of funding request with details, justification and expected accomplishments, alternative explored and partial funding effects. They might want to attach any others supporting documentations, along with cost that are reviewed weekly. The committee will review each request within the context of strategic initiatives, new regulations, emergencies, or other opportunities and determine if funds will be allocated from the contingency reserve.
Let us keep in mind that two cases can happen: denial or approval.
● If the fund request is approved that means that the sponsor approved the funding from either the contingency reserve or from management reserve
● If the request is denied, the project manager will have to accept the risk.
6.0 Risk Management
6.1 Risk Management Plan
1. Risk Identification: In order to gain a full picture of potential threats and impacts that might occur during the process of the project, we used Analogy Techniques to brainstorm and identify 12 project risks and then used Risk Breakdown Structure to organize them into categories so that we could manage these risks on a more detailed level.
Risk Breakdown Structure
|
Level 1 |
Level 2 |
Level 3 |
Risk Number |
|
External
|
Natural Cause |
Weather |
Risk 1 |
|
|
|
COVID-19 |
Risk 2 |
|
|
Human Cause |
Accident |
Risk 5 |
|
|
Environmental |
Market changes |
Risk 12 |
|
|
Technical |
Online Platform |
Risk 7 |
|
|
|
Audio Equipment |
Risk 9 |
|
Internal |
Project Management Risk |
Schedule |
Risk 3 |
|
|
|
Budget |
Risk 4 |
|
|
|
Quality |
Risk 8 |
|
|
Strategic Risk |
Advertising |
Risk 6 |
|
|
|
Customer Engagement |
Risk 10 |
|
|
|
Program Design |
Risk 11 |
2. Risk Analysis: We chose Probability and Impact Assessment to conduct the qualitative analysis (as shown in the table below) and prioritize our project risks. Furthermore, we applied the method of Expected Monetary Value to conduct the quantitative analysis (as shown in section 6.2 Risk Register) and to calculate the potential cost for the risky uncertainties.
Qualitative Analysis: Probability X Impact Matrix
Impact
|
|
Low |
Medium |
High |
|
Low |
Risk 9 |
Risk 7 Risk 11 Risk 12 |
Risk 5 Risk 6
|
|
Medium |
|
|
Risk 3 Risk 4 Risk 8 Risk 10 |
|
High |
|
|
Risk 1 Risk 2 |
Probability
3. Controlling and Monitoring Phase and Risk Response:
Having project status reports checked weekly is the process for controlling and monitoring the project risks; besides, conducting customer satisfaction survey reports to receive feedback from customers and assessing work performance data once every event is over are how we control and prevent risks happening during the events. We also implemented detailed risk responses for our primary risks and secondary risks in our Risk Register. The contingency reserve and the Change Control Board will also be assigned as risk response planning. The following are the guidelines of our risk response strategies.
|
Negative risk response |
General definitions |
Positive risk response |
|
Avoid |
Eliminate uncertainty |
Exploit |
|
Transfer |
Allocate ownership |
Share |
|
Mitigate |
Modify exposure |
Enhance |
|
Accept |
Include in baseline |
Include |
|
Escalate |
Manage at program, portfolio, or organization level |
Escalate |
4. Roles and Responsibility
|
Level 1 |
Level 2 |
Level 3 |
Risk Number |
Risk Owner |
|
External
|
Natural Cause |
Weather |
Risk 1 |
Project Team |
|
|
|
COVID-19 |
Risk 2 |
PM |
|
|
Human Cause |
Accident |
Risk 5 |
Staff |
|
|
Environmental |
Market changes |
Risk 12 |
PM |
|
|
Technical |
Online Platform |
Risk 7 |
Project Team |
|
|
|
Audio Equipment |
Risk 9 |
Staff |
|
Internal |
Project Management Risk |
Schedule |
Risk 3 |
Project Team |
|
|
|
Budget |
Risk 4 |
Project Team |
|
|
|
Quality |
Risk 8 |
HR |
|
|
Strategic Risk |
Advertising |
Risk 6 |
Project Team |
|
|
|
Customer Engagement |
Risk 10 |
Project Team |
|
|
|
Program Design |
Risk 11 |
Project Team |
5. Budgeting and Timing
Budgeting:
· Allowing about a contingency reserve of $1,830 to cover the project in most circumstances.
Timing:
· Having regular updating meetings with the project team every week to report the progress of the project status and address potential risks to the project manager.
· Involving key stakeholders and sponsors in project steering board, so that they can oversee and monitor the project
Running Head: GROUP FIVE - INTEGRATED PROJECT PLAN
2
GROUP FIVE - INTEGRATED PROJECT PLAN
6.2 Risk Register
7.0 Quality Management
7.1 Quality Management Plan and Statement
The quality management plan for this “Urban Bicycle GoToMarket Project” will institute the proper processes and procedures to ensure effectiveness and provide marketing promotion to meet quality standards. The main purpose of this quality management plan is to set the quality standards for what is defined as acceptable. Also, this plan helps project manager and project team to quality assurance and control quality and in addition to establish the responsible roles to ensure that quality management is properly managed throughout the project lifecycle.
The quality management plan is to ensure the quality of this project meets all quality standards including all key deliverables throughout the project. The project sponsors, company boards and key stakeholders will define the success criteria for quality management and also the project team and project manager will review quality standards from Urban Bicycle. All these standards will be used with key processes and procedures and communicated to all stakeholders. All quality standards need to be properly documented by the Project Manager and communicated for reference purposes.
7.2 Quality Metrics
|
Project Deliverable |
Quality Standard |
Quality Control Activity |
Frequency Interval |
Responsible |
|
Project Documents |
Project Charter, Project Management Plan, Stakeholder Management plan and scope, schedule and cost management plan, etc. need to be 100% completed. |
Review by project team, project sponsor and key stakeholders.
|
All project documents must review and check once a month. |
Project Sponsor Project Manager |
|
Target Organization |
Contracted with the ideal business companies, charities, and community organizations for collaboration with 90% rate. |
Cost benefit analysis
|
Once completed define the target organization, keep checking once week. |
Project Manager |
|
Event Design |
Meets all needs and requirement from project sponsors with 100% rate |
Review rule and requirements for designing |
Once week during design phase |
Project Manager Project Sponsor |
|
Event Implementation |
Completed the outreach events, including workshops, wellness programs, and charity rides to meet project scope, cost and schedule requirements. |
Review Project Management Plan. Project requirements.
Conduct meetings with project sponsors and key stakeholders.
|
Weekly |
Project Manager
|
|
Project Performance Report |
Completed project performance report and ready to document lesson learned for this project. |
Project team should document the performance report and project manager evaluate the performance of key deliverables |
Monthly |
Project Manager Project Team |
|
Customer Satisfaction Report |
Completed the analysis of customer satisfaction survey report with 95% rate of satisfaction. |
Commuted with customers frequently understands their needs and requirements. |
Monthly |
Project Manager |
Policies and procedures:
The quality standards are defined by the project manager, project team, project sponsors and key stakeholders of this project. To ensure that all quality standards are being met, responsible parties will review appropriate material and document any issues and recommendations for approval. The fishbone diagrams, flowcharts, check sheets, benchmarking, brainstorming, and the meeting will be used to define the quality standards, evaluate quality, and continuously improve quality. Metrics are set up and used to evaluate the quality of deliverables and processes during the project lifecycle. The project manager has authority to lead and complete the inspections for each key deliverable of this project by using the quality stands that were established by project team and project sponsors. also the project manager will be able to review and assess whether the quality standards are being met.
The project manager and project team will update the project documents through the project and document and record any quality improvements. The project manager, project team, and key stakeholders will establish quality improvements if needed. The project manager will update all documents to record the quality improvements.
Furthermore, all improvements and recommendations should be reviewed and assessed against key aspects of the project to determine whether it is beneficial to the project. The Project Manager must update all documentation if any changes occur.
• Project deliverables must achieving 100% success rate
• Project deliverables should be within project budget and time
• All quality requirements and needs must meet with the sponsor, customers and key stakeholders.
• Successfully implement outreach wellness programs to target companies and organizations
Quality Assurance
Project managers and project teams should conduct regular quality audits to help determine that the activities and products in the project meet quality standards. For the quality assurance of the project management process, the following processes must also be audited bi-weekly until completion:
● Development of Project management documents
● Terminating of target organization
● Implemented and completed the outreach event
● Assessment of customer satisfaction
● Assessment of project performance evaluations
8.0 Integrated Change Control Policy and Change Control Template
8.1 Change Control Policy
Purpose
The purpose of this document is to provide the project manager, sponsor, project team members, and all other stakeholders with the standard process for managing changes on the “Urban Bicycle GoToMarket” project.
Note: In the following document, there will be references to “Project Manager” and “Project Team Members”. Since we have decided to switch Project Manager every two weeks, the responsibility he holds will switch accordingly every two weeks as well. For example, at the time this document is being drafted (week 7-8), the Project Manager is Nan Xiang, while with “Project Team Members” we are referring. The team roles rotation schedule can be found in the Team Charter.
Related Documents
The scope of the Urban Bicycle GoToMarket Project has been defined in the approved Project Charter dated April 19, 2020. The work breakdown of the project and the timeline are detailed in the approved project plan dated May 3, 2020.
Purpose and Objectives
The purpose of this change management procedure is to manage change requests so that approved changes will be controlled, ensuring the project remains on schedule, within budget and provides the agreed deliverables. The primary objectives of change management are to:
· Manage each change request from initiation through to closure;
· Process change requests based upon direction from the appropriate authority;
· Communicate the impact of changes to appropriate personnel; and
· Allow small changes to be managed with a minimum of overhead.
Scope
The Change Management Process is the mechanism used to initiate, record, assess, approve and resolve project changes. Project changes are needed when it is deemed necessary to change the scope, time or cost of one or more previously approved project deliverables. Most changes will affect the budget and/or schedule of the project.
Policy
The use of the formal change management procedure will be required when any changes are discovered or requested which impact previously reviewed, approved and published project deliverables. The documentation and tracking of all change requests will be managed using the defined procedure and facilitated by the use of the change management log. A multi-tiered approach will be used to approve change requests:
· The Project Manager will make decisions to analyze and decisions to proceed with changes if the changes do not impact scope, budget or schedule or result in an increase in risk for the project.
· Changes which do impact scope, budget or schedule will also be forwarded to the Project Team Members for review. Then, they will decide together with the Project Manager and will advise the Project Sponsor.
· Where the KindHuman Bicycles has the resources to absorb the impact of the change, the Project Sponsor will make the final decision, based upon the information provided by the Project Manager and the input of the Project Team Members. The Project Sponsor and the Project Manager will discuss requests that may result in a significant change in scope, schedule, and budget, i.e. the impact of the change cannot be covered by KindHuman Bicycles resources.
· The Project Sponsor will make the final decision based upon the information provided.
Decision Matrix
|
|
|
Scope Change |
Increase Budget |
Not Increase Budget |
Increase Risk |
Not Increase Risk |
Increase Schedule |
Not Increase Schedule |
|
The impact of the change may be absorbed by KindHuman Bicycles |
Decision by Project Manager |
NO |
NO |
YES |
NO |
YES |
NO |
YES |
|
|
Vet with Project Team Members |
YES |
YES |
NO |
YES |
NO |
YES |
NO |
|
|
Decision by Project Sponsor |
YES |
YES |
YES |
YES |
YES |
YES |
YES |
|
The impact of the change cannot be absorbed by KindHuman Bicycles |
Vet with Project Manager |
YES |
YES |
N/A |
YES |
N/A |
YES |
N/A |
|
|
Decision by Project Sponsor |
YES |
YES |
YES |
YES |
YES |
YES |
YES |
The following is a general guideline for the change management process. Most changes will require a subset of the steps listed.
Procedures
Each request will be tracked from the time of presentation through:
1. Identify (identify and document the required change)
2. Validate (verify the change is valid and requires management)
3. Analyze (analyze and record schedule, cost and effort impact of change)
4. Control (decide whether to execute the change)
5. Action (execute decision, including revision to project plans if necessary)
6. Close (verify that action is complete and close change request)
Identify Change Request
|
Action |
Responsibility |
|
1. Identify and record the issue |
Project Manager |
Validate Change Request
|
Action |
Responsibility |
|
2. Identify members of the management team as the issue owner 3. Validate change request with project team members as appropriate 4. Assess and evaluate change for necessity to project 5. Update change request with target date for completion of analysis |
Project Manager |
Analyze Impact
|
Action |
Responsibility |
|
6. Triage with consultation of the Project Sponsor 7. Meet contract requirements for responding to Change Requests. 8. Assign resources to review the impact of the change request. 9. Direct activity to assess the scope, cost and schedule impact of the change. 10. Update change request with impact analysis and estimates in terms of scope, cost, schedule and effort impacts. 11. Update change request with target date for decision. |
Project Manager |
Control Change Request
|
Action |
Responsibility |
|
12. Meet Sigma contract requirements for responding to Change Requests. 13. Determine required approvals and assign priority to the change request. 14. If changes impact scope, budget or schedule, place the request on the agenda for the next Project Team meeting. 15. If changes do not impact scope, budget or schedule, decide whether to proceed with the change. |
Project Manager |
|
16. Review and discuss analysis of change request 17. Develop recommendation for the Project Sponsor |
Project Team Members |
|
18. Decide whether to proceed with the change 19. If the impact of change cannot be absorbed by KindHuman Bicycles, schedule a discussion with the CEO. |
Project Sponsor |
|
20. Review and discuss analysis of change request. 21. If change request should be escalated to the Steering Committee, place the request on the agenda for the next meeting (or email if the request is urgent). 22. Develop recommendation for the Steering Committee. |
Project Sponsor |
|
23. Review and discuss analysis of change request. 24. Decide whether to proceed with the change. |
Steering Committee |
|
25. General approval signature sheets for each outstanding change request. 26. Update status of change request with control decision. |
Project Sponsor |
Action Change Request
|
Action |
Responsibility |
|
27. Negotiate contract changes. 28. Execute contract changes. |
Project Manager, Project Sponsor, Technology Acquisition Manager |
|
29. Incorporate change request into appropriate plans and work plan. 30. Update work plan baseline for agreed changes. |
Project Manager |
Close Change Request
|
Action |
Responsibility |
|
31. Close change request. 32. Communicate work plan change to project team. 33. Monitor and report progress against the project plan. 34. Confirm all updates have been recorded and file all Change Request Documents. |
Project Manager |
8.2 Change Request Form
|
|
||||||
|
DESCRIPTION OF REQUESTED CHANGE(S) AND REASONS FOR CHANGE |
A) PROPOSED CHANGE 1. Reason for change 2. Reason for change
B) PROPOSED CHANGE Reason for change
|
|||||
|
AREAS OF IMPACT OF PROPOSED CHANGE |
Scope _____ Cost _____ Other _____ Schedule _____ Risk _____ |
|||||
|
DISPOSITION |
Approve _____ Disapprove _____ Approve as amended _____ Deferred _____ |
|||||
|
PRIORITY |
Emergency _____ Urgent _____ Medium _____ Low _____ |
|||||
|
FUNDING SOURCE |
Management reserve _____ Customer _____ Contingency reserve _____ Other _____ |
|||||
|
SIGN-OFF APPROVALS |
Project Manager __ __ Date __May 31, 2020__ Project Team Member __ __ Date __May 31, 2020__ Project Team Member __ __ Date __May 31, 2020__ Project Team Member __ __ Date __May 31, 2020__ Project Team Member __ __ Date __May 31, 2020__
|
References
Berkeley (n.d.). Change Control Process. Retrieved from https://vcaf.berkeley.edu/sites/default/files/change_control_process_aa.pdf
Birkett, A. (n.d.). What is Customer Satisfaction Score (CSAT)? Retrieved from
https://blog.hubspot.com/service/customer-satisfaction-score
Haney, L. (2018). The 25 Best Companies for Cyclists. Retrieved from
https://www.bicycling.com/culture/g20967875/the-top-25-best-companies-for-cyclists/
How to Measure Customer Satisfaction: 4 Key Metrics. (n.d.). Retrieved from
https://www.qualtrics.com/experience-management/customer/measure-customer-satisfact
Risk Identification Risk Analysis Risk Response Plan Risk Monitoring and Controlling Risk Number Risk Statement Risk Owner Trigger Qualitatitive Analysis Quantitative Analysis Risk Action Risk Response Detail of Response Integration with Project Plan Cost of Response Reassessment of Risk Contingency Plan Secondary Risk Secondary Risk Analysis Secondary Risk Response Risk Status
Cause Condition Consequence Category Probability Reasoning Impact Explanation EMV-Cost EMV-Duration Probability Impact Risk introduced based on Risk Response
1
Negative weather conditions or sudden weather changes on the event dates
It may affect participation in the events, especially for outdoor ones like charity/community rides
It'll limit the number of attendees who has willing to come to the events Natural cause Project team
The unpredictable weather changes in Boston High
Rapid weather changes are normal and happen a lot in Boston High
Sudden rain and breezy wind might injure participants in the outdoor rides
Probability = 55% Impact = $600 EMV = $330 n/a
Respond Required Mitigate
Provide rainproof cycling accessories to reduce the impact
Add extra resources (rainproof equipment) to the document $150.00 Medium Medium
Postpone the outdoor events
Participants get injured because of negative weather conditions
Probability- Medium Impact- Medium
Avoid-Cancel or postpone the outdoor events which are completely affected by severe weather conditions Open
2 Due to the huge impact of COVID-19
People are still concered about any large social gathering events
which will limit the number of participants in any in-person events including wellness programs Natural cause
Project manager Global pandemic High
The virus spreads easily and sustainably between people High
It might cause people who are infected are severely ill
Probability = 55% Impact = $600 EMV = $330 n/a
Respond Required Avoid
Put more focus on the online workshops, move in-person wellness programs to online
Make a specific plan of virtual workshops as alternatives for in- person events $0.00 Medium Medium
Postpone the in- person events to the time of fully re-open
A lack of customer/attendee engagement because of physical distance
Probability- Medium Impact- Medium
Exploit-Hold a raffle during the online workshops as a reward to increase engagement Open
3 Schedule delay
The activities are delay and prolong the whole schedule of the project
Fail the time expectation of the stakeholder Schedule Project team
The unexpected efficiency of team member Medium
The schedule will be controlled carefully by the project manager. Besides, this project primary relates with the internal resources so the schedule will be easier to control. High
If the risk becomes an issue in this project, it will fail the expectation of stakeholder. The goal of this project is to sell 50 bikes before the end of this year which means the time limit of this project is necessary.
Probability = 35% Impact = $600 EMV = $210
Probability = 40% Impact = 90days EMV = 36days
Respond Required Avoid
Manage the schedule carefully and report the finished work everyday to control and monitor. Add lead or lag time in schedule $0.00 Medium Medium
Create a daily check list for the team and everyone reports the work state.
Low efficiency cause the schedule still delay
Probability- Medium Impact- Medium
Avoid - The manager check the work state frequently and observe the working condition. Giving advice when necessary. Open
4 Budget overrun
The cost is more than estimated budget of the project
The project may be ended due to the unexpected expenditure Budget Project team
The unexpected cost of the project Medium
All the resources are listed in the ms project with consideration, and the cost is calculated and estimated with the resources list. Therefore, the budget should be correct. High
The impact of budget overrun will lead to the end of the project because a project can't run without fund.
Probability = 35% Impact = $600 EMV = $210
Probability = 40% Impact = 90days EMV = 36days
Respond Required Avoid
Control the cost from every sides carefully such as labor and equipment
Developing a procurement plan and list all the required equipment. $0.00 Medium Medium
Prepare a contingency in budget
The contingency still overrun
Probability- Low Impact- High
Avoid - When the unexpected cost shows up, evaluating if the cost is necessary. If it is, tring to find the cheaper alternative option. Open
5
The participants harmed during the event
The participants may harmed when they join the community ride
Lose the reputation of the organization Accident
The staff in the event Accident Low
The community ride is an event for fun which is not a competition. The participants will enjoy the ride with attention. High
The impact of this risk depends on the situation of the participant injury. If the participant gets minor injuries, the impact is low. On another hand, when the participant get serious injuries, the impact is high.
Probability = 15% Imapct = $600 EMV = $90
Probability = 15% Impact = 7days EMV = 1days
Respond Required Mitigate
Set an emergency station to provide medical support
Add activity to WBS and related resource in document $200 Low Medium
The member in the event sent the injured participants to hospital.
The emergency station doesn't provide enough medical staff.
Probability- Low Impact- High
Mitigate - Ask for the expert judgement to know how to prepare the emergency station Open
6
The advertising effect fail to reach the expectation
Low participation rate of workshop
Not enough people know about the product Marketing Project team Weak marketing Low
The current customer will attend the workshop at least. High
It will become a factor to affect the project success
Probability = 15% Imapct = $600 EMV = $90
Probability = 15% Impact = 90days EMV = 13.5days
Respond Required Avoid
Connect with the current customer tight and open the online workshop link for the customer to share
Communicate with the stakeholder (current customer) frequently - List the indiviual stakeholder in the communication plan $0.00 Low Medium
Encourage employees to post the event information and invite their friends and family to join the workshop.
The communication skill of the team member doesn't work well so that the customer decreases the interest to join the event.
Probability- Low Impact- High
Mitigate - The member who is in charge of communicating with stakeholders must have good communication skills. The manager should assign people with consideration. Open
7 The functional issue of the online platform
Unsolved and uncontrollable issue occur during the online workshop
The online workshop will be stopped or canceled
Third party platform Project team Functional risk Low
The function of online platform can be tested in advance. Medium
It will affect the quality of workshop.
Probability = 15% Impact = $300 EMV = $45
Probability = 15% Impact = 30days EMV = 4.5days
Respond Required Mitigate
Select a second online platform to be the back up. When an unsolveable issue occur, we can use the other platform.
Add activities in WBS to select the platform $120.00 Low Low
Record the presentation in advance
The second-choice online platform still has functional issue.
Probability- Low Impact- High
Mitigate - Testing the function of the platform in advance and knowing what kind of functional issue has happened before. Open
8 No qualified candidates of speakers
The quality of the online workshop will not achieve the expected impact
The potential customers may drop the interest in product Quality HR manager
The requirements of speaker are not specific enough Medium
The speaker has to get the professional knowledge about the bike structure and industry and this is not a weird known field so the candidates who match all the requirements are not easy to find. High
The quality of the speaker will influence the whole workshop and determine the interest of the participants.
Probability = 35% Impact = $600 EMV = $210
Probability = 40% Impact = 30days EMV = 12days
Respond Required Mitigate
Prolong the schedule of interviewing the candidates and post the job require on the website earlier.
Adjust the schedule about speaker searching in schedule management $50.00 Medium Medium
One of the team members who is familiar with the bike industry prepare the content to support the speaker.
The sponsor still dissatisfied with the candidates of speaker
Probability- Medium Impact- Medium
Avoid - Asking for the draft of the presentation to ensure the quality of the content reach the expectation. Open
9
Malfunctioning technical equipment, such as microphones, speakers, or professional audio gears
It will require staff to repair the machines
It will pause the event. It will lower the quality of the event because of no audio
Technical Cause Staff
Technical problem Low
The equipment should be required to do the soundcheck and audio test every time before the event starts Low
The wellness programs will be hard to continue because of no audio outputs
Probability = 15% Impact = $100 EMV = $15 n/a
Response Required Avoid
Alternative supplier/back-up technical equipment is prepared
Add extra resources to the document $50.00 Low Low
Use one of the staff's mobile phone as equipment
Overrun the budget because of the cost of back-up equipment and repair service fee
Probability - Low Impact - Low
Enhance-Use the contingency serve to cover this cost Open
10
Participants are willing to attend the events but have no interests in purchasing bikes
The revenue of the project will not be able to cover the expenses of the project
We will not make as much profit as we expected Strategic risk Project team
A lack of customer engagement in purchasing Medium
People might find workshops are useful but not won't spend $2,000 on bikes High
The expenses might higher than the revenue. We won't be able to accomplish the sales goal
Probability = 35% Impact = $600 EMV = $210 n/a
Response Required Mitigate
Focus on the companies that have higher purchasing rates or higher scores in customer satisfaction survey
Conduct research of customer satisfaction to find out the most engaged target organizations with higher sales $0 Low Low
Cut down the costs of some events or the number of the events
Decrease the exposure toward some potential buyers who are not related to any LinkedIn connections
Probability - Low Impact - Low
Transfer-Transfer the outputs of branding exposure to social media platforms Open
11
Target customers lack interests in the content of the programs
Customers will not attend the wellness events
It will decrease our opportunity to promote the products and build brand awareness Strategic risk Project team
Poor program design Low
As a one of the wellness trainer, our sponsor already has a clear understanding of what kinds of wellness programs work better Medium
It will low the participant rate and decrease the exposure
Probability = 15% Impact = $300 EMV = $45 n/a
Response Required Mitigate
Conduct pre- and post- event survey to find out the participants' expectations and reflections of each event
Conduct marketing research and pre- and post- event survey $0 Low Low
Implement the content of previous wellness programs
Still might have some participants dislike the content of the workout programs
Probability - Low Impact - Low
Accept-Implement the content of previous wellness programs Open
12
Due to a lack of interests in collaboration
We couldn't find as many cycling organizations or business companies that we could collaborate with
It will decrease our opportunity to promote the products and build brand awareness Business risk
Project manager
A lack of business interests Low
The awareness of employee wellness program is rising in many corporates Medium
It will decrease our opportunity to promote the products and build brand awareness
Probability = 15% Impact = $300 EMV = $45 n/a
Response Required Transfer
Hire event planning agency to help us to find target organizations Add extra costs to the document $200 Medium Low
Focus on the companies that already have collaborated with us before
Increase the budget because of the cost of event planner hiring
Probability - Medium Impact - Low
Enhance-Use the contingency serve to cover this cost Open