qz
QUESTION 1
1. Who are usually the parties to a construction contract?
|
|
A. |
engineer and owner |
|
|
B. |
engineer, contractor and owner |
|
|
C. |
owner and contractor |
|
|
D. |
none of the above |
10 points
QUESTION 2
1. Who does the engineer or architect usually have a contract with:
|
|
A. |
contractor |
|
|
B. |
owner |
|
|
C. |
owner's representative |
|
|
D. |
none of the above |
10 points
QUESTION 3
1. Does the engineer usually have authority to change the project?
|
|
A. |
Yes |
|
|
B. |
No |
10 points
QUESTION 4
1. Can the engineer recommend changes to the Owner?
|
|
A. |
Yes |
|
|
B. |
No |
10 points
QUESTION 5
1. Does the soil information available in a soils report always become part of the contract to allow it to be relied on by the contractor?
|
|
A. |
Yes |
|
|
B. |
No |
10 points
QUESTION 6
1. If soil quantities are not known when a contract is formed, how is this often handled to make things fair for the contractor?
|
|
A. |
lump sum bid |
|
|
B. |
unit price bid or lump sum plus unit prices |
|
|
C. |
bid bond coverage |
|
|
D. |
none of the above |
10 points
QUESTION 7
1. Specifications usually include:
|
|
A. |
drawings |
|
|
B. |
specific details on work requirements such as compaction levels |
|
|
C. |
directions to the site |
|
|
D. |
none of the above |
10 points
QUESTION 8
1. Disputes not settled by negotiation and a change order can be resolved through:
|
|
A. |
arbitration |
|
|
B. |
court |
|
|
C. |
mediation |
|
|
D. |
none of the above |
|
|
E. |
any of the above |
10 points
QUESTION 9
1. Are Bid Documents required to include a Soils Report?
|
|
A. |
Yes |
|
|
B. |
No |
10 points
QUESTION 10
1. Changed conditions clauses are usually included in earthwork contracts to:
|
|
A. |
allow cancellation of the contract |
|
|
B. |
lower bid prices by shifting risk of changed conditions to the Owner |
|
|
C. |
to force the contractor to pay for changes |
|
|
D. |
none of the above |
QUESTION 1
1.
Who are usually the parties to a construction contract?
A.
engineer and owner
B.
engineer, contractor and owner
C.
owner and contractor
D.
none of the above
10 points
QUESTION 2
1.
Who does the engineer or architect usually have a contract with:
A.
contractor
B.
owner
C.
owner's representative
D.
none of the above
10 points
QUESTION 3
1.
Does the engineer usually have authority to change the project?
A.
Yes
B.
No
10 points
QUESTION 4
1.
Can the engineer recommend changes to the Owner?
A.
Yes
QUESTION 1
1. Who are usually the parties to a construction contract?
A. engineer and owner
B. engineer, contractor and owner
C. owner and contractor
D. none of the above
10 points
QUESTION 2
1. Who does the engineer or architect usually have a contract with:
A. contractor
B. owner
C. owner's representative
D. none of the above
10 points
QUESTION 3
1. Does the engineer usually have authority to change the project?
A. Yes
B. No
10 points
QUESTION 4
1. Can the engineer recommend changes to the Owner?
A. Yes