Quiz 2
1 Activities which can take place at the same time are termed
|
|
|
Parallel activity. |
|
|
|
Merge activity. |
|
|
|
Burst activity. |
|
|
|
Critical path. |
|
|
|
Independent activity. |
2 An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a
|
|
|
Random chance. |
|
|
|
Bad luck. |
|
|
|
Risk. |
|
|
|
Hazard. |
|
|
|
Disaster. |
3 Based on the following, which event should you be most concerned about?
|
Risk Event |
Likelihood |
Impact |
|
Bad weather |
2 |
3 |
|
Design flaw |
3 |
5 |
|
Accident |
1 |
5 |
|
Shipment delay |
2 |
2 |
|
Power outage |
1 |
5 |
|
|
||
|
|
|
Accident |
|
|
|
Shipment delay |
|
|
|
Bad weather |
|
|
|
Power outage |
|
|
|
Design flaw |
4 If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
|
|
|
Check to see which activities are on the critical path. |
|
|
|
Check to see which activities cost the least. |
|
|
|
Check to see which activities have the most slack. |
|
|
|
Check to see which activities have the highest risk. |
|
|
|
Check to see which activities have the longest duration. |
5 Information to develop a project network is collected from the
|
|
|
Budget. |
|
|
|
Organization breakdown structure. |
|
|
|
Responsibility matrix. |
|
|
|
Project proposal. |
|
|
|
Work breakdown structure. |
6 One common mistake made early in the risk identification process is to
|
|
|
Not consider all possibilities. |
|
|
|
Encourage participants be over optimistic. |
|
|
|
Give too much attention to past events. |
|
|
|
Support participants being over pessimistic. |
|
|
|
Focus on consequences and not on the events that could produce consequences. |
7 Risks are evaluated in terms of
|
|
|
Impact and cost. |
|
|
|
Likelihood and cost. |
|
|
|
Time and impact. |
|
|
|
Cost and schedule. |
|
|
|
Likelihood and impact. |
8 The amount of time an activity can be delayed and yet not delay the project is termed
|
|
|
Total slack. |
|
|
|
Free slack. |
|
|
|
Critical float. |
|
|
|
Slip pad. |
|
|
|
Float pad. |
9 The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as
|
|
|
Risk management. |
|
|
|
Contingency planning. |
|
|
|
Risk forecasting. |
|
|
|
Scenario analysis. |
|
|
|
Disaster protection. |
10 The backward pass in project network calculations determines all of the following EXCEPT
|
|
|
Earliest time an activity can finish. |
|
|
|
How long an activity can be delayed. |
|
|
|
Latest time an activity can begin. |
|
|
|
The critical path. |
|
|
|
Latest time an activity can finish. |
11 The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
|
|
|
Remain about the same. |
|
|
|
Drop sharply and then level out. |
|
|
|
Rise sharply and then level out. |
|
|
|
Slowly rise. |
|
|
|
Slowly drop. |
12 The critical path in a project network is the
|
|
|
Longest path through the network. |
|
|
|
Shortest path through the network. |
|
|
|
Network path with the most difficult activities. |
|
|
|
Network path with the most merge activities. |
|
|
|
Network path using the most resources. |
13 The forward pass in project network calculations determines all of the following EXCEPT
|
|
|
Duration of the project. |
|
|
|
Earliest time an activity can finish. |
|
|
|
How soon the project can finish. |
|
|
|
The critical path. |
|
|
|
Earliest time an activity can begin. |
14 The initial step in the risk management process is to
|
|
|
Set aside budget funds for managing the risks. |
|
|
|
Assess the risk potential. |
|
|
|
Appoint a risk manager. |
|
|
|
Identify the risks. |
|
|
|
Determine the level of acceptable risk. |
15 The likelihood the original critical path(s) will change once the project is initiated is referred to as
|
|
|
Rigidity. |
|
|
|
Concurrent engineering. |
|
|
|
Sensitivity. |
|
|
|
Flexibility. |
|
|
|
Resilience. |
16 When translated into a project network, a work package will become
|
|
|
An arrow. |
|
|
|
A milestone. |
|
|
|
One or more activities. |
|
|
|
A single activity. |
|
|
|
A critical path. |
17 Which of the following correctly calculates the early finish for an activity?
|
|
|
LF + SL |
|
|
|
LF + DUR |
|
|
|
ES + SL |
|
|
|
LS + DUR |
|
|
|
ES + DUR |
18 Which of the following correctly calculates the late start for an activity?
|
|
|
EF - DUR |
|
|
|
LF - DUR |
|
|
|
ES - DUR |
|
|
|
LF - SL |
|
|
|
ES - SL |
19 Which of the following will correctly calculate the total slack in an activity?
|
|
|
LS - ES |
|
|
|
LF - ES |
|
|
|
LF - EF |
|
|
|
LS - LF |
|
|
|
Either LS - ES or LF - EF |
________ activities must be completed immediately before a particular activity.
|
|
|
Merge |
|
|
|
Burst |
|
|
|
Successor |
|
|
|
Predecessor |
|
|
|
Parallel |