Hi Lava,
I'm a bit confused, because you re-did the first week's paper correctly, and parts of it were applicable to this paper (five contract types in the FAR). Please see the rubric and let me know if you have questions, thanks.
Critical Elements Proficient Needs Improvement Not Evident Criterion Score
Overview: Purpose
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 2/12
10 / 10
Overview: Basic Components
10 points
Comprehensively discusses the purpose of a procurement management plan
7.5 points
Discusses the purpose of a procurement management plan, but with gaps in detail
0 points
Does not discuss the purpose of a procurement management plan
Criterion Feedback
Nice, comprehensive discussion of why the procurement management plan is so important to project success.
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 3/12
15 points
Comprehensively defines the basic components of a procurement management plan
11.25 points
Defines basic components of a procurement management plan, but with gaps in detail
0 points
Does not define basic components of a procurement management plan
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 4/12
15 / 15
Overview: Satisfaction of Project Requirements
Criterion Feedback
Good overview of the basic components of the procurement management plan.
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 5/12
11.25 / 15
Contract Types: Definition
15 points
Comprehensively explains how each major component of the procurement management plan satisfies the project or organizational requirements in the case study
11.25 points
Explains how components of the procurement management plan satisfy the project or organizational requirements in the case study, but with gaps in detail
0 points
Does not explain how each major component of a procurement management plan satisfies the project or organizational requirements in the case study
Criterion Feedback
I'd like more specific detail here on how the components apply to the case study; for example how does Harley Davidson use the SOW, schedule, risk plan, communications plan, etc. to satisfy the company's project requirements.
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 6/12
0 / 10
Contract Types: Suitability
10 points
Accurately defines each type of contract
7.5 points
Defines each type of contract, but with gaps in accuracy
0 points
Does not define each type of contract
Criterion Feedback
I'm looking for the information you had here in the first paper: the five contract types defined by the FAR (fixed price, cost type, incentive, indefinite delivery, and time and materials).
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 7/12
10 points
Accurately assesses contract types for their suitability for different types of projects
7.5 points
Assesses contract types for their suitability for different types of projects, but with gaps in accuracy
0 points
Does not assess contract types for their suitability for different types of projects
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 8/12
0 / 10
Contract Types: Value and Risk
Criterion Feedback
See comments above.
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 9/12
0 / 15
Contract Types: Selection
15 points
Comprehensively assesses contract types for their ability to maximize value and minimize risk for the buyer
11.25 points
Assesses contract types, but with gaps in detail
0 points
Does not assess contract types for their ability to maximize value and minimize risk for the buyer
Criterion Feedback
See comments above.
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 10/12
11.25 / 15
Articulation of Response
15 points
Selects the most appropriate contract type(s) for procurement plan in case study, and justifies rationale with research
11.25 points
Selects contract type(s) for procurement plan in case study, but contract type(s) are not appropriate, or does not justify rationale with research
0 points
Does not select contract type(s) for procurement plan in case study
Criterion Feedback
So I think you mean fixed price here, but I'm not sure, and I'd like more input on how that specifically relates to the Harley Davidson case study.
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 11/12
Total 57.5 / 100
Overall Score
10 / 10
10 points
Submission has no major errors related to citations, grammar, spelling, syntax, or organization
7.5 points
Submission has major errors related to citations, grammar, spelling, syntax, or organization that negatively impact readability and articulation of main ideas
0 points
Submission has critical errors related to citations, grammar, spelling, syntax, or organization that prevent understanding of ideas
1/24/2021 Feedback for 2-2 Final Project Milestone One: Analysis Overview and Contract Selection - QSO-349-J3611 Proj Contracting/Procurement 21EW3 - So…
https://learn.snhu.edu/d2l/lms/dropbox/user/folder_user_view_feedback.d2l?db=1126120&grpid=0&isprv=0&bp=0&ou=638690 12/12
Score
57.5 / 100 - F
Feedback Date
Jan 23, 2021 9:52 PM
Assignment
2-2 Final Project Milestone One: Analysis Overview and Contract Selection
Proficient 76 points minimum
Instructors should not modify this row (it will automate from the scores above). This score represents the average evaluation across all rubric criteria.
Needs Improvement 1 point minimum
Instructors should not modify this row (it will automate from the scores above). This score represents the average evaluation across all rubric criteria.
Not Evident 0 points minimum
Instructors should not modify this row (it will automate from the scores above). This score represents the average evaluation across all rubric criteria.
Submission ID Submission(s) Turnitin® Similarity Date Submitted 15747197 PROJECT
17 % Jan 18, 2021 9:49 AM