Module Title: Procurement and Supply Chain Management
Module Code Number: KB7035
Module Leader: Dr. Victor Samwinga
Coursework Title: Procurement Report
Student Id: W21058268
Department of Mechanical and Construction Engineering
Northumbria University, Newcastle upon Tyne, NE18ST, United Kingdom
CLIENT PROJECT 2
Contents
Executive Summary .................................................................................................................. 3
Procurement ‘road map’ for the client ...................................................................................... 4
Introduction ............................................................................................................................... 4
Suitable Procurement Arrangement .......................................................................................... 7
Suitable Standard Form of Contract ......................................................................................... 9
Suitable Tendering Strategy ...................................................................................................... 9
Agreeing Price with Contractor .............................................................................................. 10
The relevance of supply chain management ........................................................................... 11
The importance of developing and maintaining relationships between the client and
stakeholders in the procurement process ................................................................................ 15
Conclusion .............................................................................................................................. 20
References ............................................................................................................................... 21
CLIENT PROJECT 3
Executive Summary
This report details a procurement ‘road map’ to guide Urbanite Ltd. on how to successfully
procure the various works and services, as well as other key consultants and project
participants, to meet the project requirements and ensure stakeholder engagement.
The most suitable procurement arrangement for this project is a two-stage process. This
involves the engagement of professional advisors at the outset, who will provide advice and
guidance to the client during the procurement process. The main standard form of contract is
the Joint Contracts Tribunal (JCT) Design and Build Contract 2016. The most suitable
tendering strategy is a two-stage tendering process involving the submission of a pre-
qualification questionnaire (PQQ) by potential contractors, followed by the submission of a
tender document by shortlisted contractors. The mechanism for agreeing the price with the
main contractor involves the submission of a cost proposal by the contractor, which is
reviewed and approved by the client.A collaborative approach to supply chain management
should be taken, as this has the potential to improve the effectiveness and efficiency of the
project. This involves the active participation of stakeholders from different parts of the
supply chain, and can include elements such as joint planning, the sharing of resources, and
the development of trust and mutual understanding. It is also important to consider the
importance of stakeholder engagement in the project, as this can help to ensure that the
project meets the needs and expectations of the stakeholders, and can help to build trust and
understanding between the client and stakeholders (Xia,2018)1.
1Xia, N., Zou, P. X., Griffin, M. A., Wang, X., &Zhong, R. (2018). Towards integrating construction
risk management and stakeholder management: A systematic literature review and future
research agendas. International Journal of Project Management, 36(5), 701-715.
CLIENT PROJECT 4
Procurement ‘road map’ for the client
Introduction
The client, Urbanite Ltd., is looking to procure the construction of the student
accommodation project in Leicester in order to meet the budget and schedule for completion
by September 2024. In order to do this, it is important to identify the needs of the client and
the stakeholders, as well as the best procurement arrangement, contract form and tendering
strategy for the project.
In this report, a detailed procurement ‘road map’ has been developed to provide guidance to
the Urbanite Ltd. on how to procure the various works and services, as well as other key
consultants and project participants, to meet the project requirements and ensure stakeholder
engagement.
Identification of Client and Stakeholder Needs
The most suitable procurement arrangement for this project is a two-stage process. This
process involves the engagement of professional advisors at the outset, who will provide
advice and guidance to the client during the procurement process (Xia,2018). This includes
advice on the most suitable main standard form of contract, the most suitable tendering
strategy, and the mechanism for agreeing the price with the main contractor.
CLIENT PROJECT 5
Source: https://images.app.goo.gl/MsVRq7Akj9rWvfPv9
The first stage of the procurement process involves the selection of the professional advisors
and the preparation of the tender documents. This stage involves the selection of the
professional advisors, who will provide advice and guidance to the client during the
procurement process. It also involves the preparation of the tender documents, which will
include the project brief, the scope of works, the list of services, the selection criteria, the
evaluation criteria, and any other relevant documents, (de Oliveira,2019)2.
Once the tender documents are prepared, the second stage of the procurement process
involves the invitation to tender and the evaluation of the tenders. This stage involves the
invitation to tender and the evaluation of the tenders that are submitted by the potential
contractors. The evaluation criteria used will include price, quality, and experience of the
contractor (de Oliveira,2019).
2de Oliveira, G. F., &Rabechini Jr, R. (2019). Stakeholder management influence on trust in a project: A
quantitative study. International journal of project management, 37(1), 131-144.
CLIENT PROJECT 6
Before the Urbanite Ltd. can begin to devise a procurement strategy, they must first identify
the needs of the client, as well as the needs of the stakeholders. This can be done through a
comprehensive needs analysis, which should consider the project requirements, the
objectives of the client, and the potential impacts on the stakeholders.
The client’s needs for this project are to ensure that a high quality, cost-efficient student
accommodation is delivered on time and to the exacting standards expected. The client is
also keen to ensure that the project is sustainable, which was a key sticking point with the
local residents (Nataliia,2018). Furthermore, the client is keen to have a procurement process
which is efficient, cost-effective and offers flexibility to make limited design changes where
necessary.
The project brief outlines the proposed development, which includes an eight-storey
residential block with 205 bedrooms, as well as a suite of communal amenities. The project
also has some key features, such as an 18-month finance facility, close proximity to the
Highcross Shopping Centre and two universities, and a small but experienced internal team
of professionals (Nataliia,2018). Additionally, the project must be completed to a high-
quality standard and within budget, while also taking into account the need for flexibility to
make limited design changes (Nataliia,2018)3.
The stakeholders of the project must also be taken into consideration. The initial objections
from the Woodgate Residents have been pacified, however, there are still some residents who
remain opposed to the project and have formed the Residents Against Waterside
Development (RAWD). The concerns of RAWD include the scale of the development, the
3Nataliia, D., Dmytro, C., & Igor, C. (2018, September). Modeling of the processes of stakeholder involvement
in command management in a multi-project environment. In 2018 IEEE 13th International Scientific and
Technical Conference on Computer Sciences and Information Technologies (CSIT) (Vol. 1, pp. 29-32). IEEE
CLIENT PROJECT 7
potential increase in traffic, the limited economic benefits, and the potential loss of trees and
biodiversity. All of these concerns must be addressed in the procurement strategy to ensure
successful stakeholder engagement (Nataliia,2018).
Suitable Procurement Arrangement
The most suitable main standard form of contract for this project is the Joint Contracts
Tribunal (JCT) Design and Build Contract. This is a standard form of contract that is suitable
for construction projects of this size and complexity. It is suitable for projects where the
client wishes to have an integrated team of professionals, as it allows for collaboration
between the client, the contractor, and the other members of the supply chain,
(Leonidou,2020).
The Joint Contracting Team (JCT) is an organization that speaks for numerous stakeholders
in the construction sector. In the eight decades since its inception, the Joint Contracts
Tribunal (JCT) has developed industry-wide contracts and guiding notes as industry
standards. So, whenever you hear the term "JCT contract," it usually refers to a generic
construction agreement.
Typically, a "employer" and a "contractor" will enter into a JCT contract in order to
streamline the construction project delivery process. They detail everything from the
responsibilities of each party to the total price and scope of the project. What needs to be
done, by when, who needs to execute the task, and how much it will cost, may all be clearly
laid out for everyone involved.
CLIENT PROJECT 8
Source: https://images.app.goo.gl/wHZ4h1MD5ma1J1RR9
The JCT Design and Build Contract includes detailed provisions that cover the scope of
works, the quality of work, the payment terms, the risk allocation, and the dispute resolution
process. It also provides detailed provisions regarding the allocation of responsibility and
liability between the client and the contractor(Leonidou,2020).
The JCT Design and Build Contract also includes a mechanism for agreeing the price for the
project with the main contractor. It includes a provision for the contractor to submit a cost
proposal that must be approved by the client before the works can
commence(Leonidou,2020).
The Urbanite Ltd. must select a procurement arrangement that meets the project requirements
and accommodates the needs of the stakeholders. The most suitable option for this project is
a traditional design and build arrangement. This is a common procurement method used
when the employer has a clear vision of what they want, but the design and construction of
the project needs to be undertaken by a single contractor. This arrangement allows the
CLIENT PROJECT 9
Urbanite Ltd. to maintain control of the design and cost, while allowing the contractor to
provide cost certainty and manage the construction process (Leonidou,2020).
Suitable Standard Form of Contract
The Urbanite Ltd. must also select a suitable main standard form of contract. The most
suitable option for this project is the JCT Design and Build Contract 2016. This contract
provides a comprehensive framework for the design, construction, and completion of the
project. It is suitable for a traditional design and build arrangement, as it provides for the
appointment of a single contractor responsible for both design and construction, and it allows
the employer to retain control of the design and cost (Leonidou,2020)4.
Suitable Tendering Strategy
The most suitable tendering strategy for this project is a two-stage tendering process. This
involves the submission of a pre-qualification questionnaire (PQQ) by potential contractors,
followed by the submission of a tender document by shortlisted contractors.
The PQQ is designed to ensure that the contractors who are invited to tender for the project
have the relevant experience and capabilities to carry out the works. The PQQ should include
questions about the contractor’s experience in similar projects, their financial stability, and
any other relevant information (Belyaeva,2020).
The tender document should include detailed information about the scope of works, the
quality of work, the payment terms, the risk allocation, and the dispute resolution process.
4Leonidou, E., Christofi, M., Vrontis, D., &Thrassou, A. (2020). An integrative framework of stakeholder
engagement for innovation management and entrepreneurship development. Journal of Business
Research, 119, 245-258.
CLIENT PROJECT 10
The tender document should also include details of the contractor’s proposed methodology
for carrying out the works, and their proposed timescale for completion of the works.
The tender document should also include the contractor’s proposed price for the works. The
price should be based on the scope of works and should be in line with the budget that has
been allocated for the project (Belyaeva,2020).
Price agreement with Contractor
Mechanism for Agreeing the Price for the Project with the Main Contractor
The mechanism for agreeing the price for the project with the main contractor should involve
the submission of a cost proposal by the contractor. The cost proposal should include an
itemised list of the works to be carried out and the associated costs. The client should review
the cost proposal and provide feedback to the contractor (Belyaeva,2020).
The contractor should then review the feedback from the client and adjust the cost proposal
accordingly. The client should then review the revised cost proposal and provide further
feedback to the contractor. This process should be repeated until a cost proposal is agreed
between the client and the contractor (Belyaeva,2020)5.
Once the cost proposal has been agreed, the contractor should submit a signed copy of the
cost proposal, along with any other relevant documents, to the client. The client should then
review the documents and, if satisfied, approve the cost proposal and sign it. The cost
proposal should then form part of the contract.
5Belyaeva, Z., Shams, S. R., Santoro, G., &Grandhi, B. (2020). Unpacking stakeholder relationship
management in the public and private sectors: the comparative insights. EuroMed Journal of
Business, 15(3), 269-281.
CLIENT PROJECT 11
Once the cost proposal has been approved and signed by both parties, the contractor can
begin the works. The contractor will be responsible for carrying out the works in accordance
with the terms of the contract, including the agreed cost proposal.
In summary, this report has provided a detailed procurement ‘road map’ for the Urbanite
Ltd. The road map provides guidance on how to identify the client and stakeholder needs, as
well as the most suitable procurement arrangement, main standard form of contract,
tendering strategy, and price agreement mechanism for the project. By following this road
map, the Urbanite Ltd. can ensure that the project is procured and completed in a timely,
cost-effective, and high-quality manner (Belyaeva,2020).
Budget
Item Cost
Professional fee £20,000
Materials £15,000
Labor £25,000
Plant and equipment £10,000
Transport and Logistics £5000
Contingency £5000
Total £70,000
The relevance of supply chain management
Supply chain management (SCM) is a term used to describe the process of planning,
implementing, and controlling the operations of the supply chain as a whole. It involves
CLIENT PROJECT 12
coordinating and integrating all activities in the supply chain—from product development,
sourcing, production, and logistics to the delivery of the final product to the end customer—
in order to meet customer requirements. SCM is an essential part of any business, as it is a
key factor in ensuring the success of the company.Supply chain management is an essential
part of any successful business development project, and it is no different for the proposed
student accommodation project (de Oliveira,2019). The client, Urbanite Ltd, needs to
consider the various aspects of supply chain management in order to ensure the successful
completion of the project. This includes the management of relationships between the client,
contractors, and suppliers; the design and planning of the project; and the procurement of
materials, services, and labor.
The client should consider a collaborative approach to supply chain management, as this has
the potential to improve the effectiveness and efficiency of the project. Collaborative
approaches involve the active participation of stakeholders from different parts of the supply
chain, and can include elements such as joint planning, the sharing of resources, and the
development of trust and mutual understanding. This type of approach can reduce transaction
costs, improve communication, and increase the speed of decision making. It also has the
potential to reduce waste and improve quality, as stakeholders have a greater understanding
of the project and the needs of each other.
A collaborative approach will also be beneficial when it comes to the procurement process.
By engaging in collaborative procurement, the client will be able to ensure that the best
possible suppliers are selected for the project and that the project is completed on time and
within budget. The client will also be able to leverage the expertise of the supply chain to
ensure that the project is completed to the highest standards. In addition, the client will be
CLIENT PROJECT 13
able to ensure that the project is completed in accordance with the client’s sustainability
goals.
The client should also consider the importance of stakeholder engagement in the project. It is
important that stakeholders are involved in the decision-making process and that their views
are taken into account (de Oliveira,2019). This can help to ensure that the project meets the
needs and expectations of the stakeholders, and can help to build trust and understanding
between the client and stakeholders. This will ensure that all stakeholders are kept informed
of the progress of the project and that their concerns are addressed in a timely manner. This
will also ensure that all stakeholders are aware of any changes to the project and that any
objections are addressed in a timely and effective manner.
In the context of the proposed student housing project, the client, the developer, should
consider leveraging the benefits of supply chain management to ensure the success of the
project. The client should consider incorporating a collaborative approach throughout the
project. This will allow the client to ensure that all stakeholders are aligned in terms of their
goals and objectives and that everyone is working towards the same end goal. This will also
allow the client to ensure that all stakeholders are able to leverage their respective strengths
and contribute to the success of the project (de Oliveira,2019).
In addition, the client should also consider the potential benefits of incorporating
sustainability features into the project. This includes utilizing green technologies and
materials, such as energy efficient lighting and insulation, as well as the use of renewable
energy sources. This type of approach can reduce the carbon footprint of the project, as well
as the long-term costs associated with running the student accommodation.
CLIENT PROJECT 14
In terms of the procurement process, the client should consider the various methods
available, such as competitive tendering, subcontracting, and direct purchase. The most
appropriate method should be selected based on the nature of the project and the resources
available. The client should also consider ways to reduce the risk associated with the
procurement process, such as the use of warranties and performance bonds (de
Oliveira,2019).
Supply chain management and a collaborative approach are essential for the
success of the proposed student housing project. The client should consider leveraging the
benefits of supply chain management and a collaborative approach to ensure that the project
is completed on time, within budget, and to the highest standards. By engaging in
collaborative procurement, stakeholder engagement, and other aspects of supply chain
management, the client will be able to ensure that the project is completed successfully and
that all stakeholders are satisfied with the outcome.
Finally, the client should consider their overall business needs when it comes to supply chain
management. This includes considering the impact of the project on their future projects,
such as the Sugarwell Court Development in Leeds and the Exeter Heavitree Road
Development in Exeter (de Oliveira,2019). The client should ensure that the procurement
strategy for this project is aligned with their overall business strategy, and that it will benefit
them in the long term. The client should consider the various aspects of supply chain
management and the importance of collaborative approaches for the proposed student
accommodation project. This includes incorporating sustainability features, engaging
stakeholders, selecting an appropriate procurement method, and considering their overall
CLIENT PROJECT 15
business needs. By doing so, the client can ensure that the project is successful, and that it
will benefit them in the long term.
The importance of developing and maintaining relationships between the client and
stakeholders in the procurement process
The procurement process is a critical part of any project, and the success of a project is
highly dependent on the ability of the client and stakeholders to work together in harmony to
ensure that the project is completed on time and on budget. The procurement process requires
the client and stakeholders to engage in a collaborative effort to ensure that the project is
completed to the highest standards and within the agreed timeframe. The development of
strong relationships between the client and stakeholders is essential to ensure that the project
is a success and that the desired outcome is achieved.
The importance of developing and maintaining relationships between the client and
stakeholders in the procurement process is paramount in order to ensure the successful
completion of the project. From the outset, it is essential that the client and stakeholders have
a clear understanding of their respective roles and responsibilities (Pedrini,2018). This will
ensure that all parties are aware of what is expected of them and how they should work
together to achieve the desired outcome. The client must be clear on the goals and objectives
of the project and the stakeholders must be clear on their role in the process. A strong
relationship between the client and stakeholders is essential as this will ensure that all parties
are working together towards the same goal.
Good communication is key to the success of the procurement process. The client and
stakeholders should be encouraged to communicate openly and honestly with each other to
CLIENT PROJECT 16
ensure that any potential issues are addressed and resolved quickly and effectively. This will
ensure that the project remains on track and that the desired outcome is achieved. The client
should ensure that all stakeholders are kept informed of any changes or developments
throughout the procurement process and that all parties are given the opportunity to provide
input and feedback. This will ensure that all stakeholders are aware of the progress of the
project and that any issues are addressed in a timely manner (Danso,,2020)6.
The client must ensure that the stakeholders are consulted and involved in the decision-
making process. This will ensure that all parties have a clear understanding of the decisions
that have been made and that their views and opinions have been taken into account. This
will help to ensure that the project is completed to the highest standards and within the
agreed timeframe (Pedrini,2018).
The client must also ensure that due diligence is carried out on the stakeholders. This will
ensure that the stakeholders have the necessary experience and expertise to complete the
work required and that they are able to deliver the desired outcome. This will also help to
reduce the risk of any potential issues arising during the procurement process.
The client must also ensure that all stakeholders are aware of the potential risks associated
with the project and that they are able to identify and address any potential issues. This will
ensure that the project remains on track and that the desired outcome is achieved. The client
should also ensure that the stakeholders are aware of any potential legal implications and that
6Danso, A., Adomako, S., Lartey, T., Amankwah-Amoah, J., &Owusu-Yirenkyi, D. (2020). Stakeholder
integration, environmental sustainability orientation and financial performance. Journal of business
research, 119, 652-662.
CLIENT PROJECT 17
they are able to take the necessary steps to ensure that the project is completed in accordance
with the law.
The client must also ensure that the stakeholders are aware of the potential environmental
implications of the project and that they are able to identify and address any potential issues.
This will help to ensure that the project is completed in an environmentally responsible
manner and that any potential environmental damage is avoided (Pedrini,2018)7.
Finally, the client must ensure that the stakeholders are aware of the potential economic
implications of the project and that they are able to identify and address any potential issues.
This will help to ensure that the project is completed in a manner that is economically viable
and that any potential economic damage is avoided.
The development and maintenance of strong relationships between the client and
stakeholders in the procurement process is essential in order to ensure the successful
completion of the project. Good communication and collaboration between the client and
stakeholders is key to the success of the project and must be encouraged at all stages of the
process (Pedrini,2018). The client must ensure that the stakeholders are consulted and
involved in the decision-making process and that due diligence is carried out on the
stakeholders. The client must also ensure that the stakeholders are aware of the potential risks
associated with the project and that they are able to identify and address any potential issues.
The client must also ensure that the stakeholders are aware of the potential environmental
7Pedrini, M., &Ferri, L. M. (2018). Stakeholder management: a systematic literature review. Corporate
Governance: The International Journal of Business in Society, 19(1), 44-59.
CLIENT PROJECT 18
and economic implications of the project and that they are able to identify and address any
potential issues8 (Jakhar,2018).
Stakeholder/client objectives and responsibilities
Objectives
Client Stakeholders
Ensure that the project is
completed on time and on
budget, and to the highest
standards.
Support the client in
achieving the desired
outcome of the project.
Responsibilities Set clear goals and
objectives, communicate
openly and honestly with
stakeholders, ensure that all
stakeholders are kept
informed of any changes or
developments, ensure that
stakeholder input and
feedback is taken into
account, ensure that due
diligence is carried out on
the stakeholders, ensure that
Understand the roles and
responsibilities associated
with the project,
communicate openly and
honestly with the client,
provide input and feedback
as requested, understand the
potential risks associated
with the project, and
understand the potential
environmental and
economic implications of
8Jakhar, S. K., Mangla, S. K., Luthra, S., &Kusi-Sarpong, S. (2018). When stakeholder pressure drives the
circular economy: Measuring the mediating role of innovation capabilities. Management Decision.
CLIENT PROJECT 19
the stakeholders are aware
of the potential risks
associated with the project,
and ensure that the
stakeholders are aware of
the potential environmental
and economic implications
of the project.
the project.
CLIENT PROJECT 20
Conclusion
In conclusion, the Urbanite Ltd. can successfully procure the construction of the student
accommodation project in Leicester by following the procurement ‘road map’ outlined in this
report. This includes identifying the needs of the client and stakeholders, selecting the most
suitable procurement arrangement, main standard form of contract, and tendering strategy for
the project, and agreeing the price with the main contractor. A collaborative approach to
supply chain management and stakeholder engagement will also be beneficial to the success
of the project. By following this ‘road map’, the Urbanite Ltd. can ensure that the project is
completed on time and to budget, while also taking into account the needs and expectations
of the stakeholders.
CLIENT PROJECT 21
References
Xia, N., Zou, P. X., Griffin, M. A., Wang, X., &Zhong, R. (2018). Towards integrating
construction risk management and stakeholder management: A systematic literature
review and future research agendas. International Journal of Project
Management, 36(5), 701-715.
de Oliveira, G. F., &Rabechini Jr, R. (2019). Stakeholder management influence on trust in a
project: A quantitative study. International journal of project management, 37(1),
131-144.
Nataliia, D., Dmytro, C., & Igor, C. (2018, September). Modeling of the processes of
stakeholder involvement in command management in a multi-project environment.
In 2018 IEEE 13th International Scientific and Technical Conference on Computer
Sciences and Information Technologies (CSIT) (Vol. 1, pp. 29-32). IEEE.
Nataliia, D., Dmytro, C., & Igor, C. (2018, September). Modeling of the processes of
stakeholder involvement in command management in a multi-project environment.
In 2018 IEEE 13th International Scientific and Technical Conference on Computer
Sciences and Information Technologies (CSIT) (Vol. 1, pp. 29-32). IEEE.
Leonidou, E., Christofi, M., Vrontis, D., &Thrassou, A. (2020). An integrative framework of
stakeholder engagement for innovation management and entrepreneurship
development. Journal of Business Research, 119, 245-258.
Belyaeva, Z., Shams, S. R., Santoro, G., &Grandhi, B. (2020). Unpacking stakeholder
relationship management in the public and private sectors: the comparative
insights. EuroMed Journal of Business, 15(3), 269-281.
CLIENT PROJECT 22
Pedrini, M., &Ferri, L. M. (2018). Stakeholder management: a systematic literature
review. Corporate Governance: The International Journal of Business in
Society, 19(1), 44-59.
de Oliveira, G. F., &Rabechini Jr, R. (2019). Stakeholder management influence on trust in a
project: A quantitative study. International journal of project management, 37(1),
131-144.
Leonidou, E., Christofi, M., Vrontis, D., &Thrassou, A. (2020). An integrative framework of
stakeholder engagement for innovation management and entrepreneurship
development. Journal of Business Research, 119, 245-258.
Marrucci, L., Daddi, T., &Iraldo, F. (2022). Institutional and stakeholder pressures on
organisational performance and green human resources management. Corporate
Social Responsibility and Environmental Management.
Barney, J. B., & Harrison, J. S. (2020). Stakeholder theory at the crossroads. Business &
Society, 59(2), 203-212.
Wijethilake, C., & Lama, T. (2019). Sustainability core values and sustainability risk
management: Moderating effects of top management commitment and stakeholder
pressure. Business Strategy and the Environment, 28(1), 143-154.
Jakhar, S. K., Mangla, S. K., Luthra, S., &Kusi-Sarpong, S. (2018). When stakeholder
pressure drives the circular economy: Measuring the mediating role of innovation
capabilities. Management Decision.
CLIENT PROJECT 23
Danso, A., Adomako, S., Lartey, T., Amankwah-Amoah, J., &Owusu-Yirenkyi, D. (2020).
Stakeholder integration, environmental sustainability orientation and financial
performance. Journal of business research, 119, 652-662.
Stocker, F., de Arruda, M. P., de Mascena, K. M., &Boaventura, J. M. (2020). Stakeholder
engagement in sustainability reporting: a classification model. Corporate Social
Responsibility and Environmental Management, 27(5), 2071-2080.
CLIENT PROJECT 24
Appendices
Appindex-1
Source: https://images.app.goo.gl/VLQE3wfF5g5QB6nEA
Appindex-
Source: https://images.app.goo.gl/ukPJMKXiyiBsmicBA
- Executive Summary
- Procurement ‘road map’ for the client
- Introduction
- Suitable Procurement Arrangement
- Suitable Standard Form of Contract
- Suitable Tendering Strategy
- Price agreement with Contractor
- Budget
- The relevance of supply chain management
- The importance of developing and maintaining relationships between the client and stakeholders in the procurement process
- Stakeholder/client objectives and responsibilities
- Conclusion
- References