This is an example of Gantt chart showing the progress I intend to make on my project over the next few months. On the x-axis is each objective that is mentioned above. Along the y-axis are the dates I intend to start and finish each section.
Page 1 of 1 14/05/2019
Obj 1Obj 2Obj 3Obj 4Obj 5Obj 6StartComplete
Chart1
| Obj 1 | Obj 1 | Obj 1 |
| Obj 2 | Obj 2 | Obj 2 |
| Obj 3 | Obj 3 | Obj 3 |
| Obj 4 | Obj 4 | Obj 4 |
| Obj 5 | Obj 5 | Obj 5 |
| Obj 6 | Obj 6 | Obj 6 |
Start
Complete
Remaining
39811
0
14
39818
0
14
39832
0
14
39839
0
14
39853
0
7
39860
0
21
Sheet1
| | Start | Complete | Remaining |
| Obj 1 | 12/29/08 | 0 | 14 |
| Obj 2 | 1/5/09 | 0 | 14 |
| Obj 3 | 1/19/09 | 0 | 14 |
| Obj 4 | 1/26/09 | 0 | 14 |
| Obj 5 | 2/9/09 | 0 | 7 |
| Obj 6 | 2/16/09 | 0 | 21 |
Sheet1
Start
Complete
Remaining