PROJECT SCHEDULING: IMPROVED APPROACH TO INCORPORATE UNCERTAINTY USING BAYESIAN NETWORKS
Project scheduling inevitably involves
uncertainty. The basic inputs (i.e., time,
cost, and resources for each activity) are
not deterministic and are affected by var-
ious sources of uncertainty. Moreover,
there is a causal relationship between
these uncertainty sources and project
parameters; this causality is not modeled
in current state-of-the-art project plan-
ning techniques (such as simulation tech-
niques). This paper introduces an
approach, using Bayesian network mod-
eling, that addresses both uncertainty
and causality in project scheduling.
Bayesian networks have been widely used
in a range of decision-support applica-
tions, but the application to project man-
agement is novel. The model presented
empowers the traditional critical path
method (CPM) to handle uncertainty and
also provides explanatory analysis to elic-
it, represent, and manage different
sources of uncertainty in project planning.
Keywords: project scheduling;
uncertainty; Bayesian networks;
critical path method; CPM
©2007 by the Project Management Institute
Vol. 38, No. 2, 39-49, ISSN 8756-9728/03
Introduction
Project scheduling is difficult because it inevitably involves uncertainty. Uncertainty in real-world projects arises from the following characteristics:
• Uniqueness (no similar experience) • Variability (trade-off between performance measures like time, cost, and quality) • Ambiguity (lack of clarity, lack of data, lack of structure, and bias in estimates).
Many different techniques and tools have been developed to support better project scheduling, and these tools are used seriously by a large majority of proj- ect managers (Fox & Spence, 1998; Pollack-Johnson, 1998). Yet, quantifying uncertainty is rarely prominent in these approaches.
This paper focuses especially on the problem of handling uncertainty in proj- ect scheduling. The next section elaborates on the nature of uncertainty in project scheduling and summarizes the current state of the art. The proposed approach is to adapt one of the best-used scheduling techniques, critical path method (CPM) (Kelly, 1961), and incorporate it into an explicit uncertainty model (using Bayesian networks). The paper summarizes the basic CPM methodology and nota- tion, presents a brief introduction to Bayesian networks, and describes how the CPM approach can be incorporated (using a simple illustrative example). Also dis- cussed is a mechanism to implement the model in real-world projects, and sug- gestions on how to move forward and possible future modifications are presented.
The Nature of Uncertainty in Project Scheduling
A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Third edi- tion (PMI, 2004) identifies risk management as a key area of project management:
“Project risk management includes the processes concerned with conducting risk management planning, identification, analysis, response, and monitoring and control on a project.”
Central to risk management is the issue of handling uncertainty. Ward and Chapman (2003) argued that current project risk management processes induce a restricted focus on managing project uncertainty. They believe it is because the term “risk” has become associated with “events” rather than more general sources of significant uncertainty.
VAHID KHODAKARAMI, Queen Mary University of London, United Kingdom NORMAN FENTON, Queen Mary University of London, United Kingdom MARTIN NEIL, Queen Mary University of London, United Kingdom
ABSTRACT
JU N E 2007 PR O J E C T MA N A G E M E N T JO U R N A L40
pendence of activity duration in a project network. Moreover, being event-oriented (assuming project risks as “independent events”), MCS and the tools that implement it do not identify the sources of uncertainty.
As argued by Ward and Chapman (2003), managing uncertainty in proj- ects is not just about managing per- ceived threats, opportunities, and their implication. A proper uncertainty management provides for identifying various sources of uncertainty, under- standing the origins of them, and then managing them to deal with desirable or undesirable implications.
Capturing uncertainty in proj- ects “needs to go beyond variability and available data. It needs to address ambiguity and incorporate structure and knowledge” (Chapman & Ward, 2000). In order to measure and analyze uncertainty properly, we need to model relations between trigger (source), and risk and impacts (consequences). Because projects are usually one-off experiences, their uncertainty is epistemic (i.e., related to a lack of complete knowledge) rather than aleatoric (i.e., related to randomness). The duration of a task is uncertain because there is no sim- ilar experience before, so data is incomplete and suffers from impreci- sion and inaccuracy. The estimation of this sort of uncertainty is mostly subjective and based on estimator judgment. Any estimation is condi- tionally dependent on some assump- tions and conditions—even if they are not mentioned explicitly. These assumptions and conditions are major sources of uncertainty and need to be addressed and han- dled explicitly.
The most well-established approach to handling uncertainty in these circumstances is the Bayesian approach (Efron, 2004; Goldstein, 2006). Where complex causal rela- tionships are involved, the Bayesian approach is extended by using Bayesian networks. The challenge is to incorporate the CPM approach into Bayesian networks.
In different project management processes there are different aspects of uncertainty. The focus of this paper is on uncertainty in project scheduling. The most obvious area of uncertainty here is in estimating duration for a particular activity. Difficulty in this estimation can arise from a lack of knowledge of what is involved as well as from the uncertain consequences of potential threats or opportunities. This uncertainty arises from one or more of the following: • Level of available and required
resources • Trade-off between resources and time • Possible occurrence of uncertain
events (i.e., risks) • Causal factors and interdependencies
including common casual factors that affect more than one activity (such as organizational issues)
• Lack of previous experience and use of subjective rather than objective data
• Incomplete or imprecise data or lack of data at all
• Uncertainty about the basis of subjec- tive estimation (i.e., bias in estimation).
The best-known technique to sup- port project scheduling is CPM. This technique, which is adapted by the most widely used project management software tools, is purely deterministic. It makes no attempt to handle or quan- tify uncertainty. However, a number of techniques, such as program evaluation and review technique (PERT), critical chain scheduling (CCS) and Monte Carlo simulation (MCS), do try to han- dle uncertainty, as follows: •PERT (Malcom, Roseboom, Clark, & Fazer, 1959; Miller, 1962; Moder, 1988) incorporates uncertainty in a restricted sense by using a probabil- ity distribution for each task. Instead of having a single determin- istic value, three different estimates (pessimistic, optimistic, and most likely) are approximated. Then the “critical path” and the start and fin- ish date are calculated by the use of distributions’ means and applying probability rules. Results in PERT are more realistic than CPM, but PERT does not address explicitly any of the sources of uncertainty previ- ously listed.
• Critical chain (CC) scheduling is based on Goldratt’s theory of con- straints (Goldratt, 1997). For mini- mizing the impact of Parkinson’s Law (jobs expand to fill the allocat- ed time), CC uses a 50% confidence interval for each task in project scheduling. The safety time (remain- ing 50%) associated with each task is shifted to the end of the critical chain (longest chain) to form the project buffer. Although it is claimed that the CC approach is the most important breakthrough in project management history, its oversim- plicity is a concern for many compa- nies that do not understand both the strength and weakness of CC and apply it regardless of their particular and unique circumstances (Pinto, 1999). The assumption that all task durations are overestimated by a cer- tain factor is questionable. The main issue is: How does the project man- ager determine the safety time? (Raz, Barnes, & Dvir, 2003). CC relies on a fixed, right-skewed probability for activities, which may be inappropri- ate (Herroelen & Leus, 2001), and a sound estimation of project and activity duration (and consequently the buffer size) is still essential (Trietsch, 2005).
• Monte Carlo simulation (MCS) was first proposed for project scheduling in the early 1960s (Van Slyke, 1963) and implemented in the 1980s (Fishman, 1986). In the 1990s, because of improvements in comput- er technology, MCS rapidly became the dominant technique for han- dling uncertainty in project schedul- ing (Cook, 2001). A survey by the Project Management Institute (PMI, 1999) showed that nearly 20% of project management software pack- ages support MCS. For example, PertMaster (PertMaster, 2006) accepts scheduling data from tools like MS-Project and Primavera and incorporates MCS to provide project risk analysis in time and cost. However, the Monte Carlo approach has attracted some criticism. Van Dorp and Duffey (1999) explained the weakness of Monte Carlo simula- tion in assuming statistical inde-
JU N E 2007 PR O J E C T MA N A G E M E N T JO U R N A L 41
CPM Methodology and Notation
CPM (Moder, 1988) is a deterministic technique that, by use of a network of dependencies between tasks and given deterministic values for task durations, calculates the longest path in the net- work called the “critical path.” The length of the ”critical path” is the earli- est time for project completion. The critical path can be identified by deter- mining the following parameters for each activity:
D—duration ES—earliest start time EF—earliest finish time LS—latest start time LF—latest finish time.
The earliest start and finish times of each activity are determined by working forward through the network and determining the earliest time at which an activity can start and finish, considering its predecessor activities. For each activity j:
ESj = Max [ESi + Di ; over predecessor activities i]
EFj = ESj+ Dj
The latest start and finish times are the latest times that an activity can start and finish without delaying the project and are found by working backward through the network. For each activity i:
LFi = Min [LFj – Dj ; over successor activities j]
LSi = LFi – Di
The activity’s “total float” (TF) (i.e., the amount that the activity’s duration can be increased without increasing the overall project comple- tion time) is the difference in the latest and earliest finish times of each activi- ty. A critical activity is one with no TF and should receive special attention (delay in a critical activity will delay the entire project). The critical path then is the path(s) through the net- work whose activities have minimal TF.
The CPM approach is very simple and provides very useful and funda- mental information about a project and its activities’ schedule. However, because of its single-point estimate assumption, it is too simplistic to be used in complex projects. The chal- lenge is to incorporate the inevitable uncertainty.
Proposed BN Solution
Bayesian Networks (BNs) are recog- nized as a mature formalism for han- dling causality and uncertainty (Heckerman, Mamdani, & Wellman, 1995). This section provides a brief overview of BNs and describes a new approach for scheduling project activi- ties in which CPM parameters (i.e., ES, EF, LS, and LF) are determined in a BN.
Bayesian Networks: An Overview Bayesian networks (also known as belief networks, causal probabilistic networks, causal nets, graphical proba- bility networks, probabilistic cause-
effect models, and probabilistic influ- ence diagrams) provide decision sup- port for a wide range of problems involving uncertainty and probabilistic reasoning. Examples of real-world applications can be found in Heckerman et al. (1995), Fenton, Krause, and Neil (2002), and Neil, Fenton, Forey, and Harris (2001). A BN is a directed graph, together with an associated set of probability tables. The graph consists of nodes and arcs. Figure 1 shows a simple BN that mod- els the cause of delay in a particular task in a project. The nodes represent uncertain variables, which may or may not be observable. Each node has a set of states (e.g. ”on time” and ”late” for ”Subcontract” node). The arcs repre- sent causal or influential relationships between variables. (e.g., “subcontract” and “staff experience” may cause a “delay in task”). There is a probability table for each node, providing the probabilities of each state of the vari- able. For variables without parents (called “prior” nodes), the table just contains the marginal probabilities (e.g., for the subcontract” node P(on- time)=0.95 and P(late)=0.05). This is also called “prior distribution” that represents the prior belief (state of knowledge) about the variable. For each variable with parents, the proba- bility table has conditional probabili- ties for each combination of the parents’ states (see, for example, the probability table for a “delay in task”
Figure 1: A Bayesian network contains nodes, arcs and probability table
JU N E 2007 PR O J E C T MA N A G E M E N T JO U R N A L42
in Figure 1). This is also called the “likelihood function” that represents the likelihood of a state of a variable given a particular state of its parent.
The main use of BNs is in situa- tions that require statistical inference. In addition to statements about the probabilities of events, users have some evidence (i.e., some variable states or events that have actually been observed), and can infer the probabili- ties of other variables, which have not as yet been observed. These observed values represent a posterior probabili- ty, and by applying Bayesean rules in each affected node, users can influence other BN nodes via propagation, mod- ifying the probability distributions. For example, the probability that the task finishes on time, with no observation, is 0.855 (see Figure 2a). However if we know that the subcontractor failed to deliver on time, this probability updates to 0.49 (see Figure 2b).
The key benefits of BNs that make them highly suitable for the project planning domain are that they: • Explicitly quantify uncertainty and model
the causal relation between variables • Enable reasoning from effect to cause as
well as from cause to effect (propaga- tion is both “forward” and “backward”)
• Make it possible to overturn previ- ous beliefs in the light of new data
• Make predictions with incomplete data • Combine subjective and objective data • Enable users to arrive at decisions
that are based on visible auditable reasoning.
BNs, as a tool for decision support, have been deployed in domains rang- ing from medicine to politics. BNs potentially address many of the “uncer- tainty” issues previously discussed. In particular, incorporating CPM-style scheduling into a BN framework makes it possible to properly handle uncer- tainty in project scheduling.
There are numerous commercial tools that enable users to build BN models and run the propagation calcu- lations. With such tools it is possible to perform fast propagation in large BNs (with hundreds of nodes). In this paper, AgenaRisk (2006) was used, since it can model continuous vari- ables (as opposed to just discrete).
BN for Activity Duration Figure 3 shows a prototype BN that the authors have built to model uncertain- ty sources and their affects on duration of a particular activity. The model con- tains variables that capture the uncer- tain nature of activity duration. “Initial duration estimation” is the first esti- mation of the activity’s duration; it is estimated based on historical data, previous experience, or simply expert judgment. “Resources” incorporate any affecting factor that can increase or decrease the activity duration. It is a ranked node, which for simplicity here is restricted to three levels: low, aver- age, and high. The level of resources can be inferred from so-called “indica- tor” nodes. Hence, the causal link is from the “resources” directly to observ-
able indicator values like the “cost,” the experience of available “people” and the level of available “technology.” There are many alternative indicators. An important and novel aspect of this approach is to allow the model to be adapted to use whichever indicators are available.
The power of this model is better understood by showing the results of running it under various scenarios. It is possible to enter observations any- where in the model to perform not just predictions but also many types of trade-off and explanatory analysis. So, for example, observations for the ini- tial duration estimation and resources can be entered and the model will show the distributions for duration. Figure 4 shows how the distribution of the activity duration in which the ini- tial estimation is five days changes when the level of its available resources goes from low to high. (All the subsequent figures are outputs from the AgenaRisk software.)
Another possible analysis in this model is the trade-off analysis between duration and resources when there is a time constraint for activity duration and it is interesting to know about the level of required resource. For example, consider an activity in which the initial duration is estimated as five days but must be finished in three days. Figure 5 shows the probability distribution of required resources to meet this dura- tion constraint. Note how it is skewed toward high.
Figure 2: New evidence updates the probability
JU N E 2007 PR O J E C T MA N A G E M E N T JO U R N A L 43
Figure 5: Level of required “Resources” when there is a constraint on “Duration”
Mapping CPM to BN The main components of CPM net- works are activities. Activities are linked together to represent dependencies. In order to map a CPM network to a BN, it is necessary to first map a single activity. Each of the activity parameters are represented as a variable (node) in the BN.
Figure 6 shows a schematic model of the BN fragment associated with an activity. It clearly shows the relation between the activity parameters and also the relation with predecessor and successor activities.
The next step is to define the con- necting link between dependent activi- ties. The forward pass in CPM is mapped as a link between the EF of each activity to the ES of the successor activities. The backward-pass in CPM is mapped as a link between the LS of each activity to the LF of the predeces- sor activities.
Example The following illustrates this mapping process. The example is deliberately very simple to avoid extra complexity in the BN. How the approach can be used in real-size projects is discussed later in the paper.
Consider a small project with five activities—A, B, C, D, and E. The activ- ity on arc (AOA) network of the project is shown in Figure 7.
The results of the CPM calculation are summarized in Table 1. Activities A, C, and E with TF=0 are critical and the overall project takes 20 days (i.e., earliest finish of activity E).
Figure 8 shows the full BN repre- sentation of the previous example. Each activity has five associated nodes. Forward pass calculation of CPM is done through the connection between the ES and EF. Activity A, the first activ- ity of the project, has no predecessor, so its ES is set to zero. Activity A is predecessor for activities B and C so the EF of activity A is linked to the ES of activities B and C. The EF of activity B is linked to the ES of its successor, activity D. And finally, the EF of activi- ties C and D are connected to the ES of activity E. In fact, the ES of activity E is the maximum of the EF of activities C
Figure 3: Bayesian network for activity duration
Figure 4: Probability distribution for “duration” (days) changes when the level of “resources” changes
JU N E 2007 PR O J E C T MA N A G E M E N T JO U R N A L44
one scenario is to see how changing the resource level affects the project completion time.
Figure 10 compares the distribu- tions for project completion time as the level of people’s experience changes. When people’s experience changes from low to high, the mean of finishing time changes from 22.7 days to 19.5 days and the 90% confi- dence interval changes from 26.3 days to 22.9 days.
Another useful analysis is when there is a constraint on the project completion time and we want to know how many resources are need- ed. Figure 11 illustrates this trade-off between project time and required resources. If the project needs to be completed in 18 days (instead of the baseline 20 days) then the resource required for activity A most likely must be high; if the project comple- tion is set to 22, the resource level for activity A moves significantly in the direction of low.
The next scenario investigates the impact of risk in activity A on the project completion time as it is shown in Figure 12. When there is a risk in activity A, the mean of distri- bution for the project completion time changes from 19.9 days to 22.6 days and the 90% confidence interval changes from 22.5 days to 25.3 days.
One important advantage of BNs is their potential for parameter learning, which is shown in the next scenario. Imagine activity A actually finishes in seven days, even though it was originally esti- mated as five days. Because activity A has taken more time than was expected, the level of resources has probably not been sufficient.
By entering this observation the model gives the resource probability for activity A as illustrated in Figure 13. This can update the analyst’s belief about the actual level of avail- able resources.
Assuming both activities A and E use the same resources (e.g., people), the updated knowledge about the level of available resources from activity A (which is finished) can be entered as evidence in the resources
and D. The EF of activity E is the earli- est time for project completion time.
The same approach is used for backward CPM calculations connecting the LF and LS. Activity E is the last activ- ity of the project and has no successor, so its LF is set to EF. Activity E is succes- sor of activities C and D so the LS of activity E is linked to the LF of activities C and D. The LS of activity D is linked to the LF of its predecessor activity B. And finally, the LS of activities B and C are linked to the LF of activity A. The LF of activity A is the minimum of the LS of activities B and C.
For simplicity in this example, it is assumed that activities A and E are more risky and need more detailed analysis. For all other activities the uncertainty about duration is expressed simply by a normal distribution.
Results This section explores different scenar- ios of the BN model in Figure 8. The main objective is to predict the proj-
ect completion time (i.e., the earliest finish of E) in such a way that it fully characterizes uncertainty.
Suppose the initial estimation of activities’ duration is the same as in Table 1. Suppose the resource level for activities A and E is medi- um. If the earliest start of activity A is set to zero, the distribution for project completion is shown in Figure 9a. The distribution’s mean is 20 days as was expected from the CPM analysis. However, unlike CPM, the prediction is not a single point and its variance is 4. Figure 9b illustrates the cumulative distribu- tion of finishing time, which shows the probability of completing the project before a given time. For example, with a probability of 90% the project will finish in 22 days.
In addition to this baseline sce- nario, by entering various evidence (observations) to the model, it is pos- sible to analyze the project schedule from different aspects. For example,
Figure 6: Schematic of BN for an activity
Figure 7: CPM network
JU N E 2007 PR O J E C T MA N A G E M E N T JO U R N A L 45
for activity E (which is not started yet) and consequently updates the project completion time. Figure 14 shows the distributions of comple- tion time when the level of available resource of activity E is learned from the actual duration of activity A.
Another application of parameter learning in these models is the ability to incorporate and learn about bias in estimation. So, if there are several observations in which actual task completion times are underestimated, the model learns that this may be due
to bias rather than unforeseen risks, and this information will inform sub- sequent predictions. Work on this type of application (called dynamic learn- ing), is still in progress and can be a possible way of extending the BN ver- sion of CPM.
Figure 8: Overview of BN for example (1)
JU N E 2007 PR O J E C T MA N A G E M E N T JO U R N A L46
Object-Oriented Bayesian
Network (OOBN)
It is clear from Figure 8 that even simple CPM networks lead to fairly large BNs. In real-sized projects with several activi- ties, constructing the network needs a huge effort, which is not effective espe-
cially for users without much experience in BNs. However, this complexity can be handled using the so-called object-ori- ented Bayesian network (OOBN) approach (Koller & Pfeffer, 1997). This approach, analogous to the object-ori- ented programming languages, supports
a natural framework for abstraction and refinement, which allows complex domains to be described in terms of interrelated objects.
The basic element in OOBN is an object; an entity with an identity, state, and behavior. An object has a set of attributes each of which is an object. Each object is assigned to a class. Classes provide the ability to describe a general, reusable network that can be used in different instances. A class in OOBN is a BN fragment.
The proposed model has a highly repetitive structure and fits the object- oriented framework perfectly. The internal parts of the activity subnet (see Figure 6) are encapsulated within the activity class as shown in Figure 15.
Table 1: Activities’ time (days) and summary of CPM calculations
Figure 9: Distribution of project completion (days) for main scenario in example (1)
Figure 10: Change in project time distribution (days) when level of people's experience changes
JU N E 2007 PR O J E C T MA N A G E M E N T JO U R N A L 47
Classes can be used as libraries and combined into a model as needed. By connecting interrelated objects, complex networks with several dozen nodes can be constructed easily. Figure 16 shows the OOBN model for the example previously presented.
The OOBN approach can also sig- nificantly improve the performance of inference in the model. Although a full discussion of the OOBN approach to this particular problem is beyond the scope of this paper, the key point to note is that there is an existing mecha- nism (and implementation of it) that enables the proposed solution to be genuinely “scaled-up” to real-world projects. Moreover, research is emerg-
ing to develop the new generation of BNs tools and algorithms that support OOBN concept both in constructing large-scale models and also in propa- gation aspects.
Conclusions and How to Move Forward
Handling risk and uncertainty is increasingly seen as a crucial compo- nent of project management and plan- ning. One classic problem is how to incorporate uncertainty in project scheduling. Despite the availability of different approaches and tools, the dilemma is still challenging. Most cur- rent techniques for handling risk and uncertainty in project scheduling (sim- ulation-based techniques) are often
Figure 11: Probability of required resource changes when the time constraint changes
Figure 13: Learnt probability distribution “resource” when the actual duration is seven days
Figure 12: The impact of occurring risk in activity A on the project completion time
JU N E 2007 PR O J E C T MA N A G E M E N T JO U R N A L48
event-oriented and try to model the impact of possible “threats” on project performance. They ignore the source of uncertainty and the causal relations between project parameters. More advanced techniques are required to capture different aspects of uncertainty in projects.
This paper has proposed a new approach that makes it possible to
incorporate risk, uncertainty, and causality in project scheduling. Specifically, the authors have shown how a Bayesian network model can be generated from a project’s CPM network. Part of this process is auto- matic and part involves identifying specific risks (which may be common to many activities) and resource indi- cators. The approach brings the full
weight and power of BN analysis to bear on the problem of project sched- uling. This makes it possible to: • Capture different sources of uncer-
tainty and use them to inform proj- ect scheduling
• Express uncertainty about comple- tion time for each activity and the whole project with full probability distributions
• Model the trade-off between time and resources in project activities
• Use ”what-if?” analysis • Learn from data so that predictions
become more relevant and accurate.
The application of the approach was explained by use of a simple example. In order to upscale this to real projects with many activities the approach must be extended to use the so-called object-oriented BNs. There is ongoing work to accommo- date such object-oriented modeling so that building a BN version of a CPM is just as simple as building a basic CPM model.
Other extensions to the work described here include: • Incorporating additional uncertainty
sources in the duration network • Handling dynamic parameter learn-
ing as more information becomes available when the project progresses
• Handling common causal risks that affect more than one activity
• Handling management action when the project is behind its plan.
Figure 14: completion time (days) based on learned parameters compare with baseline scenario
Figure 15: OO model for the presented example
Figure 15: Activity class encapsulates internal parts of network
JU N E 2007 PR O J E C T MA N A G E M E N T JO U R N A L 49
References
AgenaRisk. (2006). Available at www.agenarisk.com
Chapman, C., & Ward, S. (2000). Estimation and evaluation of uncer- tainty: A minimalist first pass approach. International Journal of Project Management, 18, 369–383.
Cook, M. S. (2001). Real-world Monte Carlo analysis. Proceeding of PMI Annual Seminars and Symposium, Nashville, TN.
Efron, B. (2004). Bayesians, fre- quentists, and scientists. Journal of the American Statistical Association, 100(469), 1–5.
Fenton, N. E., Krause, P., & Neil, M. (2002). Software measurement: Uncertainty and causal modeling. IEEE Software 10(4), 116–122.
Fishman, G. S. (1986). A Monte Carlo sampling plan for estimating network reliability. Operations Research, 34(4), 581–594.
Fox, T. L., & Spence, J. W. (1998). Tools of the trade: A survey of project management tools. Project Management Journal, 29, 20–28.
Goldstein, M. (2006). Subjective Bayesian analysis: Principle and prac- tice2. Bayesian Analysis, 1(3), 403–420.
Goldratt, E. M. (1997). Critical chain. Great Barrington: The North River Press Publishing Corporation.
Heckerman, D., Mamdani, A., & Wellman, M. (1995). Real-world appli-
cations of Bayesian networks. Comm ACM, 38(3), 25–26.
Herroelen, W., & Leus, R. (2001). On the merits and pitfalls of critical chain scheduling. Journal of Operations Management, 19, 559–577.
Kelly, J. E. (1961). Critical path planning and scheduling mathematical bases. Operations Research, 9, 246–320.
Koller, D., & Pfeffer, A. (1997). Object-oriented Bayesian networks. In D. Geiger & P. Shenoy, (Eds.), Proceedings of the Thirteenth annual Conference on Uncertainty in Artificial Intelligence (UAI-97) (pp. 302–313), San Francisco, CA.
Malcolm, D. G., Roseboom, J. H., Clark, C. E., & Fazer, W. (1959). Application of a technique for research and development program evaluation. Operations Research, 7(5), 646–669.
Miller R. W. (1962). How to plan and control with PERT. Harvard Business Review, 93–104.
Moder, J. (1988). Network tech- niques in project management. Project Management Handbook, 2nd edition (pp. 324–373). New York: Van Nostrand Reinhold.
Neil, M., Fenton, N., Forey, S. & Harris, R. (2001). Using Bayesian belief networks to predict the reliability of military vehicles. IEE Computing and Control Engineering Journal 12(1), 11–20.
Pinto, J. K. (1999). Some con- straints on the theory of constraints:
Taking a critical look at the critical chain. PM Network, 13(8), 49–51.
Pertmaster. (2006). Project risk soft- ware. Available at www.pertmaster.com
PMI. (1999). Project management software survey, Newtown Square, PA: Project Management Institute.
PMI. (2004). A guide to the project management body of knowledge (PMBOK® guide – 3rd edition). Newtown Square, PA: Project Management Institute.
Pollack-Johnson, B. (1998). Project management software usage patterns and suggested research direc- tions for future development. Project Management Journal, 29, 19–29.
Raz, T., Barnes, R., & Dvir, D. (2003). A critical look at critical chain project management. Project Management Journal, 34, 24–32.
Trietsch, D. (2005). Why critical path by any other name would smell less sweet? Project Management Journal, 36, 27–36.
Van Dorp, J. R., & Duffey, M. R. (1999). Modelling statistical depend- ence in risk analysis for project net- works. International Journal of Production Economics, 58, 17–29.
Van Slyke, R. M. (1963). Monte Carlo methods and the PERT problem. Operations Research, 11(5), 839–860.
Ward, S., & Chapman, C. (2003). Transforming project risk management into project uncertainty management. International Journal of Project Management, 21, 97–105.
MARTIN NEIL is a reader in “systems risk” at the Department of Computer
Science, Queen Mary, University of London, where he teaches decision and
risk analysis and software engineering. He is also a joint founder and chief
technology officer of Agena Ltd., which developed and distributes AgenaRisk,
a software product for modeling risk and uncertainty. His interests cover
Bayesian modeling and/or riskquantification in diverse areas: operational risk
in finance, systems and design reliability, project risk, decision support,
simulation, artificial intelligence and personalization, and statistical learning.
He earned a BSc in mathematics, a PhD in statistics and software metrics and
is a chartered engineer.
VAHID KHODAKARAMI is a PhD student at RADAR
group at Queen Mary University of London. He
earned a BSc in industrial engineering from
Tehran Polytechnic and an MSc in industrial
engineering from Sharif University of Technology
in Iran. He has more than 10 years experience in
both academia and industry. He has also
consulted for several companies in project
management and system design. He earned his
second MSc in information technology from
Queen Mary. His research interests include project
management, project risk management, decision-
making and Bayesian networks.
NORMAN FENTON is a professor of computing at
Queen Mary (London University) and is also chief
executive officer of Agena, a company that
specializes in riskmanagement for critical systems.
At Queen Mary he is the computer science
department director of research and he is the head
of the Risk Assessment and Decision Analysis
Research Group (RADAR). His books and
publications on software metrics, formal methods,
and riskanalysis are widely known in the software
engineering community. His recent work has
focused on causal models (Bayesian nets) for risk
assessment in a wide range of application
domains such as vehicle reliability, embedded
software, transport systems, TV personalization
and financial services. He is a chartered engineer
and chartered mathematician and is a fellow of the
British Computer Society. He is a member of the
editorial board of the Software Quality Journal.