RISKS (Blank)

Feedback for Team Deliverable 6 Submission Feedback Good work team. I think a permit failure or delay risk should be identified. A risk of imprecise measurements should be identified, too. Appliances may not fit. I found a lot of spelling errors. Overall, this is good work but may need some editing.
Project Risk Matrix
Tips for filling in the spreadsheet:
To specify multiple items in any cell (particularly for Risk Response Action(s) and Contingency Plans), after entering the first item, press Alt+Enter to start a new line within the same cell.
Only enter numerical values in the severity sections; the verbal descriptions will populate automatically depending on the numerical values.
To add a line to any section, highlight the bottom line of the section and insert a new line above it. Then copy the formulas from the severity cells and paste them in the new line.
To add an entire section (to create a new category of risks), copy an entire section and paste a new section at the bottom this document.
Severity prior to risk response Severity after risk response
Technical Threat or Opportunity? Likelihood Impact Rating Risk Response Strategy (identify an appropriate strategy - see comment)
Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept
Risk Response Action(s) (define actions to implement risk response strategy)
Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column
Likelihood Impact Rating Contingency Plans (explain what will be done if the risk actually occurs) Status Owner
T1 Non-compliance with inspection Threat 1 Low Medium 3 Moderate 2 Low Medium Avoid Choose experienced contractor who is famaliar with inspection codes Ensure plan for inspection failure is stated in contract Contractor will perform quality work that is up to code 1 Very Unlikley 1 Negligible 1 Low Discuss findings with inspector and correct in timely manner In progress Contractor
T2 Project Design Threat 2 Possible 5 Severe 2 Medium High Avoid Research and understand design options Throughly discuss and review project design with homeowner/contractor 1 Very Unlikely 2 Minor 2 Low Create new design or alter current one with the assistance of a professional designer Underway Project team, homeowner
T3 Existing plumbing, electrical, or flooring issues Threat 1 Possible 4 Severe 3 Medium High Mitigate Perform pre-inspection prior to project start Homeowner will disclose any knowledge of pre-existing damage Contractor will inform shareholders of the potential for existing damage Homewowner will set aside additioanal reserve fund to ensure project continuation 1 Unlikely 1 Negligible 1 Low Repair existing damage In progress Contractor
Severity prior to risk response Severity after risk response
Financial Threat or Opportunity? Likelihood Impact Rating Risk Response Strategy (identify an appropriate strategy - see comment)
Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept
Risk Response Action(s) (define actions to implement risk response strategy)
Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column
Likelihood Impact Rating Contingency Plans (explain what will be done if the risk actually occurs) Status Owner
F1 Going over budget Threat 3 Possible 3 Significant 3 Medium High Mitigate Ensure every stakeholder and materials/product for the project are properly budgeted. Maintain inventory supply Hold accountability meetings with project team 1 Unlikely 5 Severe 3 Medium Avoid and adjust the budget for any unnessary items or spending Notify the client of any delay to project due to budget changes In progress Budget Manager
F2 Failing to budget for full project scope Threat 1 Possible 3 Significant 2 Medium High Mitigate Include salary/wages for all stakeholders as well as required products/materials Calculate additional funding to budget for possible adjustments 1 Very Unlikley 5 Severe 3 Medium Adjust budget for unnessary items or spending Notify client of any delay to project due to budget changes In progress Budget Manager
Severity prior to risk response Severity after risk response
Operational Threat or Opportunity? Likelihood Impact Rating Risk Response Strategy (identify an appropriate strategy - see comment)
Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept
Risk Response Action(s) (define actions to implement risk response strategy)
Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column
Likelihood Impact Rating Contingency Plans (explain what will be done if the risk actually occurs) Status Owner
O1 Install exceeds timeline Threat 3 Possible 5 Severe 4 Medium High Mitigate Ensure team understands the timeline and adheres to the schedule Keep open communication with the team to be on top of any prolonged issues that would cause a change in the schedule 4 Likely 5 Significant 5 High Hold an emergeny team meeting to adjust the schedule and accommodate any changes that would delay the project's completion In Progress Project Team
O2 Delayed Delivery of Materials/Appliances Threat 4 Likely 5 Severe 5 High Mitigate Ensure team is aware of date/time of when materials will be delivered and make detailed scheduled of each material being delivered Choose in-stock items that don't require backorder 3 Possible 3 Moderate 3 Medium Contant customer service of products/material suppliers Pick-up products/materials using own transportation methods Receive updated shipment notifications from postal carrier In Progress Project Manger
O3 Demolition exceeds timeline Threat 2 Unlikely 4 Significant 3 Medium Mitigate Ensure the demolition team is aware of date/time of completion. Make sure that all team members are aware of any necessary changes that need to be implemented to meet the deadline 3 Possible 3 Moderate 3 Medium Request more dumpsters with project/buget manager's approval Contractor will provide additional laborers to speed up demolition In Progress Project Manager
Severity prior to risk response Severity after risk response
Reputational Threat or Opportunity? Likelihood Impact Rating Risk Response Strategy (identify an appropriate strategy - see comment)
Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept
Risk Response Action(s) (define actions to implement risk response strategy)
Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column

Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept

Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column
Likelihood Impact Rating Contingency Plans (explain what will be done if the risk actually occurs) Status Owner
R1 Management Team Communication Issues Threat 2 Unlikely 5 Severe 4 Medium High Mitigate Adhere to communication plan: Attend required meetings. Complete assigned correspondences. Follow up with team and stakeholders on progress. Solicit feedback from team and stakeholders on communications. 1 Very Unlikley 3 Moderate 2 Low Medium Regroup: Hold an emergency team meeting to determine the extent of miscommunication and its effect on the project completion. Adjust existing manpower to bring the outstanding deliverable into alignment. Underway- Monitor Project Manager
R2 Undocumented Project Alterations Threat 2 Unlikely 4 Significant 3 Medium Avoid Familiarize team with project scope. Perform only services as identified in scope. Advise PM of any events that may diverge from scope. Purchase only items identified in client meeting. Remove only items identified in scope. Make no alterations to the defined scope without receiving approval from PM. 1 Very Unlikley 2 Minor 1 Low Rescope: Re-draft scope to include work performed or materials used. Check with client to ensure the alteration is acceptable. Adjust budget allocations to accommodate changes. Notify team members of alterations to address any changes in timelines. Actions to be agreed Project Team
R3 Exceeding Completion Date Threat 3 Possible 5 Severe 4 Medium High Mitigate Incoporate time for testing and repair in schedule. Plan an additional 20% of time to the projected completion date to allow for scope creep and unforseen events. Maintain communication between phases and team members to account for issues in execution of labor or delays in delivery. 2 Unlikely 3 Moderate 2 Low Medium Allocate all available resources to the completion of the remaining deliverables. Consider authorization of overtime in longer workdays or work-weeks to complete the project within the defined limits. Underway- Monitor Project Manager Assistant Project Manager
Severity prior to risk response Severity after risk response
[Other] Threat or Opportunity? Likelihood Impact Rating Risk Response Strategy (identify an appropriate strategy - see comment)
Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept
Risk Response Action(s) (define actions to implement risk response strategy)
Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column

Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept

Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column
Likelihood Impact Rating Contingency Plans (explain what will be done if the risk actually occurs) Status Owner
1 Very Unlikley 1 Negligible 1 Low 1 Very Unlikley 1 Negligible 1 Low
1 Very Unlikley 1 Negligible 1 Low 1 Very Unlikley 1 Negligible 1 Low

&F Page &P

&F Page &P

&F Page &P

RISKS (Example)

Project Risk Matrix
Tips for filling in the spreadsheet:
To specify multiple items in any cell (particularly for Risk Response Action(s) and Contingency Plans), after entering the first item, press Alt+Enter to start a new line within the same cell.
Only enter numerical values in the severity sections; the verbal descriptions will populate automatically depending on the numerical values.
To add a line to any section, highlight the bottom line of the section and insert a new line above it. Then copy the formulas from the severity cells and paste them in the new line.
To add an entire section (to create a new category of risks), copy an entire section and paste a new section at the bottom this document.
Severity prior to risk response Severity after risk response
Technical Threat or Opportunity? Likelihood Impact Rating Risk Response Strategy (identify an appropriate strategy - see comment)
Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept
Risk Response Action(s) (define actions to implement risk response strategy)
Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column
Likelihood Impact Rating Contingency Plans (explain what will be done if the risk actually occurs) Status Owner
T1 Product does not pass validation testing 3 Possible 4 Significant 4 Medium High Mitigate • Build adequate time into project schedule to allow for multiple design options to go through preliminary testing • Verification testing to be completed prior to start of validation 2 Unlikely 3 Moderate 2 Low Medium • Switch to phased implementation Actions complete - monitor Project Team
T2 etc 2 Unlikely 4 Significant 3 Medium TBD • etc 3 Possible 3 Moderate 3 Medium • etc New Finance Director
Severity prior to risk response Severity after risk response
Financial Threat or Opportunity? Likelihood Impact Rating Risk Response Strategy (identify an appropriate strategy - see comment)
Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept
Risk Response Action(s) (define actions to implement risk response strategy)
Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column
Likelihood Impact Rating Contingency Plans (explain what will be done if the risk actually occurs) Status Owner
F1 Start-up costs and investments might prove too steep to endure 3 Possible 4 Significant 4 Medium High Mitigate (possibly Transfer) • Good estimation and modelling of financial flows to inform investment decision, expectations and actions • tbc Adopt an evolving model 2 Unlikely 3 Moderate 2 Low Medium • Switch to phased implementation Actions complete - monitor Project Team
F2 etc 4 Likely 4 Significant 4 Medium High TBD • etc 3 Possible 3 Moderate 3 Medium • etc New Finance Director
Severity prior to risk response Severity after risk response
Operational Threat or Opportunity? Likelihood Impact Rating Risk Response Strategy (identify an appropriate strategy - see comment)
Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept
Risk Response Action(s) (define actions to implement risk response strategy)
Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column
Likelihood Impact Rating Contingency Plans (explain what will be done if the risk actually occurs) Status Owner
O1 Some influential stakeholders might consider this is not an appropriate initiative and therefore do not adequately engage with it 4 Likely 4 Significant 4 Medium High Mitigate • PR/comms strategy • Comprehensive stakeholder management Board support • Effective communications to all stakeholders • Demonstrate the potential benefits to the stakeholders 4 Likely 3 Moderate 3 Medium • Chief Executive prepared to act 1 to 1 Actions in progress Project Team
O2 etc 5 Very Likely 4 Significant 5 High TBD • etc 4 Likely 3 Moderate 3 Medium • etc Closed Team
Severity prior to risk response Severity after risk response
Reputational Threat or Opportunity? Likelihood Impact Rating Risk Response Strategy (identify an appropriate strategy - see comment)
Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept

Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept
Risk Response Action(s) (define actions to implement risk response strategy)
Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column

Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column
Likelihood Impact Rating Contingency Plans (explain what will be done if the risk actually occurs) Status Owner
R1 A bad result might dent our reputation and/or cause contagion for other business lines 2 Unlikely 4 Significant 3 Medium Mitigate • Quality processes, standards, reviews, controls • Essential to have an experienced engagement manager • tbc - Ability to separate the brands • PR/comms contingency planning 3 Possible 4 Significant 4 Medium High • Distance new venture from the robust main business For board approval Steering Committee
R2 etc 3 Possible 3 Moderate 3 Medium TBD • etc 2 Unlikely 3 Moderate 2 Low Medium • etc Actions to be agreed Team
Severity prior to risk response Severity after risk response
[Other] Threat or Opportunity? Likelihood Impact Rating Risk Response Strategy (identify an appropriate strategy - see comment)
Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept

Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept
Risk Response Action(s) (define actions to implement risk response strategy)
Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column

Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column

Wills, Kyle: Wills, Kyle: For Threats, choose Avoid, Transfer, Mitigate, or Accept For Opportunities, choose Exploit, Share, Enhance, or Accept

Wills, Kyle: Wills, Kyle: If "Accept" is selected as the risk response strategy, enter "N/A" in this column
Likelihood Impact Rating Contingency Plans (explain what will be done if the risk actually occurs) Status Owner
2 Unlikely 4 Significant 3 Medium • Other • Other 3 Possible 4 Significant 4 Medium High • Other
3 Possible 3 Moderate 3 Medium • etc 2 Unlikely 3 Moderate 2 Low Medium • etc

&F Page &P

&F Page &P

&F Page &P

Risk Matrix

Impact
1 2 3 4 5
Probability Negligible Minor Moderate Significant Severe
5 Very Likely Low Medium Medium Medium High High High
4 Likely Low Low Medium Medium Medium High High
3 Possible Low Low Medium Medium Medium High Medium High
2 Unlikely Low Low Medium Low Medium Medium Medium High
1 Very Unlikley Low Low Low Medium Medium Medium
1 2 3 4 5
Negligible Minor Moderate Significant Severe
5 Very Likely 2 3 4 5 5
4 Likely 1 2 3 4 5
3 Possible 1 2 3 4 4
2 Unlikely 1 2 2 3 4
1 Very Unlikley 1 1 2 3 3
nb Standard UK Public Sector Risk Management matrix