Johnston-Home Project Basement Finishing - Plans 02-05-2020

 

 

 

 

 

 

 

GENERAL REQUIREMENT

Qty

Start Date 

Finished

Apply for Building Permit 

1

02/05/2020

02/07/2020

Measure basement 

1192

02/07/2020

02/07/2020

Storage container

1

02/09/2020

02/10/2020

 

 

 

 

Total

 

 

 

 

 

 

 

Building Materials 

Qty

 

 

Drywall Sheets

40

02/12/2020

02/13/2020

2x4 boards

80

02/12/2020

02/13/2020

Drywall screws-Bucket

1

02/12/2020

02/13/2020

Plaster-Bucket

6

02/12/2020

02/13/2020

Fiber glass tape

4

02/12/2020

02/13/2020

Insallation Rolls

15

02/12/2020

02/13/2020

Total

 

 

 

 

 

 

 

FRAMING LABOR

Qty

 

 

Framing materials:

 

 

 

Rough carpentry lumber

4

02/24/2020

02/27/2020

Total

 

 

 

 

 

 

 

Steps Started to complete Drywall Basement-Priority

 

 

 

 

 

 

 

Insulation Installed 

15

02/28/2020

02/29/2020

Drywall Sheets Installed 

40

03/01/2020

03/05/2020

Taped Seam of dry wall 

 

03/06/2020

03/07/2020

Mudded Drywall

 

03/08/2020

03/09/2020

Textured Walls 

 

03/10/2020

03/11/2020

 

 

 

 

Completion of Drywalling Basement 

 

 

03/12/2020

Project Objective statement

1.0 Overview of the Project

1.1 General Project Objective Statement

The Homeowner [Teresa Johnston] is finishing Framing the Basement of the primary residence. The homeowner will be responsible for purchasing the materials, tools and equipment. Owner will also be responsible of labor and all other expenses need to for the completion of the framing of the basement.

1.2 Project Location

Basement Framing Project

555 Main Street

Newton, Utah 85445

2.0 Deliverables

2.1 Owner will supply the deliverables to any outside contractors be electricians, plumbers and Hvac installers.

2.2 Owner will provide the plans to the electrician on where to place the receptacle outlets, light fixtures and switches.

2.3 Owner will be provided where heating registers will be put installed.

2.4 The Deliverables due date will be provided for the date of execution for the electrician and hvac installers.

3.0 Milestones

3.1 Foundation work making sure waterproofing the inside of basement.

3.2 Framing-Installation of wood framing.

3.3 Mechanical-Installation of electrical, heating and plumbing.

Interior work-Finishing of installing insulation, hanging of drywall, taping, mudding, and painting.

3.4 Trim-Finish window, door and baseboard trim

4.0 Technical Requirements

4.1 Find out the Basement requirements are from the City.

4.2 Checklist for obtaining Building Permit and Permit Fees.

4.3 Plans to the contactors that are hired.

5.0 Limits and exclusions

5.1 Standards of the scope of the project so the inspector will not make any recommendations or perform any actions during the inspection.

5.2 County Inspectors will not determine the following

· Cost of materials

· The effectiveness, and efficiency of heating and its components.

· Warranty and Guarantees of the contractors.

6.0 Review

6.1 Will be done by the owner where to purchase all materials need to complete the framing of the basement.

several Deliverables, several Milestones, several Technical Requirements and any limits or exclusions you feel necessary. In addition, identify the customer reviewer.