Introduction:
The name of our project is Pen Reader. The purpose of the project is to help all students in any country who study a language other than their native language, especially university students around the world to make their life easier. Also, one of our purpose is being one of the latest development in the technology era.
Work Breakdown Structure:
|
Project Title |
Pen Reader |
Company Name |
Inventronic |
|
Project Manager |
|
Date |
March6-2018 |
|
Expected Time |
Pessimistic Time (days) |
Most Likely Time (days) |
Optimistic Time (days) |
Predecessors |
Activity |
|
|
10 |
16 |
10 |
4 |
- |
Analysis the project idea |
A |
|
14 |
20 |
14 |
8 |
A |
Set the requirement of production plan |
B |
|
18 |
38 |
16 |
6 |
B |
Select the materials |
C |
|
20 |
20 |
20 |
20 |
B |
Order of materials |
D |
|
20 |
22 |
22 |
10 |
C,D |
Execution |
E |
|
4 |
4 |
4 |
4 |
E |
Pricing |
F |
|
15 |
32 |
14 |
2 |
F |
Marketing plan |
G |
|
8 |
14 |
8 |
2 |
F |
Distribution |
H |
|
11 |
16 |
12 |
2 |
F |
Promotion |
I |
Project-oriented Budgeting:
The project time and cost:
-time will be between 10 1o 14 months and cost will be SAR 100,000 to 120,300. The following chart presents a cost breakdown.
|
Steps |
Costs (SR) |
|
Electronic development |
|
|
-Programming |
70,000 |
|
-Safety procedures |
6000 |
|
Total electronic development: |
SR76,000 |
|
Others |
|
|
-Building the pen structure |
300 for each pen or |
|
-Computer |
4,000 |
|
-Advertisement |
40,000 |
|
Total other costs |
SR44,300 |
Our project estimated budgets is SR 120,300 by using tasks and months