Project E & B
Project WBS and Schedule
Project Estimating and Budgeting
ABC LIMITED AUTOMATED CEMENT MANUFUCTURING
1. Figure 1.0
PROJECT SCHEDULE FOR AN AUTOMATED CEMENT MANUFUCTURING SYSTEM
|
WEEK |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
|
STARTING |
Oct 1 |
Nov 1 |
Nov 30 |
Dec 1 |
Dec 31 |
Jan 1 |
Jan 31 |
Fed 1 |
Mar 1 |
Apr 1 |
May 1 |
Jun 1 |
Jun 15 |
Jun 31 |
Jul 1 |
Aug 1 |
Sep 1 |
Sep 8 |
Sep 20 |
Sep 28 |
|
Planning phase |
Quality assurance plan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
Project plan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
Review plan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
Analysis phase |
|
|
|
|
Requirements |
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
|
|
|
|
Capacity planning |
|
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
|
|
|
|
|
Project test plan |
|
|
|
|
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
Test plan |
|
|
|
|
|
|
|
|
|
|
|
|||
|
|
|
|
|
|
|
|
|
Requirement specification |
|
|
|
|
|
|
|
|||||
|
|
|
|
|
|
|
|
|
Phase approval |
|
|
|
|
|
|
|
|||||
|
Design phase |
|
|
|
|
|
|
|
|
Design specification |
|
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Plan configuration |
|
|
|
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
|
Design plan |
|
|
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Interface definition requirements |
|
|
|
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
|
|
|
Parts design |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
|
|
|
Integration test plan |
|
|
|
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project procedures |
|
||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Design specification |
|
|
||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Review and approval |
|
1. Figure 1.1
REFERENCES
MIL-STD-881D, Work Breakdown Structures for Defense Materiel Items,
9 April 2018.
Levy, Lacie monday.com, Your Quick Start Guide to Work Breakdown, Structure. Accessed 21.
November 2019.
Planning scheduling excellence guide. National defense industrial association, mar 2106.
Program schedule quality 101 Oct 214 retrieved 24 May 2016
CRUSHER
DRILLING
EXPLOSIVE CHARGING
SECONDARY CRUSHER
RAW MATERIAL PREPARATION
PRE-HEATING AND GRINDING
PREPARATION OF ADDITIVE
GRINDING
LIMESTONE QUERY
RAW GRINDING PROCESS
FINISH GRINDING
CRUSHING PROCESS
EXCAVATION PROCESS
PROPOTIONING PROCESS
PYRO-PROCESING
PACKAGING
MACKING AND HAULING
CLINKER
CLIINKER COOLER
SAND
CLAY
STORAGE
SHIPPING
MIXING
LEVEL 1
LEVEL 2
LEVEL 3
PROJECT
END