ProjectClosureReport.docx

Closure Report

Hardware Deployment Project for ABC Company

Closure Report

Project Manager: Krishna Marepalli

Date: January 2019

Version:

© Global Knowledge Training LLC

Version History

ID

Changes

Date Created

Author

© Global Knowledge Training LLC

Table of Contents

Project Summary 4

Project Results 5

Scope 5

Cost 5

Schedule 5

Success Criteria 6

Key Lessons Learned 7

Project Assessment 8

Project Manager Assessment 9

Team Assessment 10

Action Items / Future Projects 11

Project Acceptance 12

© Global Knowledge Training LLC

Project Summary

Project

Hardware Deployment for ABC Company

Objectives

To deploy the most current hardware system to ABC company

To ensure that there is compatibility between the current software and the newly deployed hardware.

To provide all ABC Company staffs access the newly deployed hardware system.

To improve the overall functionality and efficient program progress of ABC Company by hardware deployment.

To decommission the already existing hardware system

Project manager

Krishna Marepalli

Sponsor

ABC Company

Start date

May 2018

Planned completion date

November 2018

Actual completion date

January 2019

Project Results

Scope

Deliverable description

Were All Requirements Met?[footnoteRef:1] [1: Yes: all requirements were met; some: some of the deliverable requirements were met; no-approved: deliverable was dropped from project but change request was submitted; no-unapproved: deliverable was dropped from project but change request was not submitted]

Comments

Deploying the most current hardware to ABC Company

Ensuring compatibility between the current software and the newly deployed hardware

Yes, all the requirements were met.

Yes, all the requirements were met.

Most deliverables were provided on time.

Most of the deliverables were provided adequately.

Cost

Budget Item

Planned Cost

Actual

Cost

Variance

Comments

Salaries

$50,000

$60,000

$10,000

There was an increase in staff training costs

Other internal expenses

$10,000

$15,000

$5,000

There was an increase in other internal expenses

Consulting expenses

$5,000

$4,000

$1,000

There was a decrease in consulting costs

Capital expenditures

$15,000

$18,000

$3,000

There was an increase in capital expenditures

Schedule

Deliverable Description

Planned Completion

Actual Completion

Variance

Comments

Deploying the most current hardware to ABC Company

Ensuring compatibility between the current software and the newly deployed hardware

November 2018

November 2018

January 2019

January 2019

1 month

1 month

Adjustment in project schedule

Adjustment in project schedule

Success Criteria

Criteria

Status[footnoteRef:2] [2: Met: criteria were met; not met: criteria were not met ]

Comments

The new hardware is deployed, and all old hardware decommissioned.

All ABC staff can efficiently work and increase the productivity of the company.

The new hardware system becomes very reliable and efficient for use by the ABC Company.

The efficient flow of work is once again assured by the newly deployed hardware

Met

Met

Met

Met

Activity successful

Activity Successful

Activity Successful

Activity Successful

Key Lessons Learned

What are the most important lessons learned during this project?

There are many significant lessons that were learned when undertaking the project. Though the project schedule was not met, one important lesson learnt is the importance of sticking to the initial time schedule of the project. (Soekiman et al, 2011) examines different factors relating to labor which may affect a project schedule. Though some constraints may delay the project, it is of great essence when the schedule of the project is adhered to. The application MS Project Schedule was used for the two-thirds of the project and it helped to assess the results of delays.

There was an increase in the costs of the project. This is because there were some expenses which were not catered for during the planning process. The ABC Company did not have efficient information relating to some costs. The costs included that of training and purchase of the new hardware. Some extra funding was therefore sourced from other stakeholders so as to avoid shortages. The lesson to learn from this is that the planners of the project should try their level best to identify all possible costs. Many IT projects may be delivered on budget if all the underlying factors are considered (Bloch et al, 2012).

There were some requirements for the deliverables of the project. Though not all requirements were met, it is important to note that those requirements achieved the standards which were set. (Lock, 2017) outlines that the requirements of project deliverables are essential in project management. It is therefore important for any project planner to ensure that all the requirements for the deliverables of the project are met accordingly.

The project was very successful. The project manager was able to provide good leadership as the project was on course. The project was able to meet the original intended business benefits. The staff members cooperated well. The IT experts of the ABC Company worked hard to ensure that the project was on course. In this way the project was able to meet the customer needs. It is a significant lesson that all projects which are rolled out should try to be successful and hence meet its intended objectives. (Raymond & Bergeron, 2008) analyzes the impacts of project management system on the success of the project.

The results of the project were impressing. All the stakeholders who were engaged in the project were very happy about the project’s results. The members of staff were now able to use the new hardware. IT tests were conducted, and it was found that the new hardware was fully compatible with the software in place. (Mir & Pinnington, 2014) tries to link the performance of the project management and the results of the project. The stakeholders included the project planners, sponsors, management and the teams. This is a good lesson to learn in that each project which is started should always produce the desired results.

Project Assessment

Areas to Improve

Comments

Business case development

Alternatives to the project

Customer needs

Other alternatives to the project were not carefully researched on.

The project could not meet some of the customer needs.

Initiation

Project assumptions

Project constraints

Some of the project assumptions were never identified.

There were some project constraints which could not be identified yet it had impacts on the project.

Requirements definition

Project requirements

Technical documents

Some of the project requirements were not defined clearly.

Some technical documents of the project were not completed.

Planning

Work breakdown structure

Project resources

The breakdown structure of work was not adequate and efficient.

Some of the resources which were required could not be acquired.

Controlling

Control process

Status reports

Some of the change control processes which were used to manage the scope of the project did not follow the required guidelines.

The status reports were not being distributed on a required regular basis.

Executing

Training materials

Test cases

Some of the training materials were not developed.

Some of the test cases were not executed.

Closing

Knowledge

Not all knowledge was transferred from the vendors to workers.

Other

Workers’ turnover

Some of the workers who were employed to execute the project quit on the way citing some reasons.

Project Manager Assessment

Areas to Improve

Comments

Integration management

Project methodology

Management of the project

The methodology of the project should be adhered to. In some instances, the methodology of the project was not followed.

The project should be well managed so as to accomplish its objectives.

Scope management

Management of changes to project scope

Estimation of the changes in project scope

The changes in scope of the project were not efficiently managed.

The changes in the project scope were not effectively estimated.

Cost management

Budget

Estimation of changes in the costs of the project

The budget of the project was inadequate.

The changes in the costs of the project were not accurately estimated.

Time management

Change control process

Management of changes to schedule of the project

No formal change control process was used to ensure control in the initial schedule of the project.

The changes to schedule of the project was not managed properly

Quality management

Management plan

Deliverables

The project did not follow the laid down management plan.

Some of the deliverables did not meet the quality standards which were set for the project.

Risk management

Risk monitoring

The risks were not well monitored during the course of the project.

Communication management

Communicating issues

In some instances, the issues pertaining to the project could not be communicated well.

Procurement management

Time of providing the deliverables

In some scenarios the vendor delayed in providing deliverables of the project.

Human resources management

Organizational structure

The organizational structure was not effective since there was duplication of roles and responsibilities.

Other

Project piloting

Pilot tests may be carried before the roll out of the project in order to clearly understand the expectations of the project.

Team Assessment

Areas to Improve

Comments

Professionalism

Expectations of the team

Duties and responsibilities

The expectations of the team should be well defined before the start of the project.

Members of the team should be made aware of their specific duties and responsibilities

Collaboration

Assistance to each other

Willingness to work well with each other

The members of the team should be willing to help each other when undertaking various tasks of the project.

Team members should be willing to work well with each other.

Teamwork

Team unity

Communication within the team

Team members should work as a one united unit.

There should be an effective communication among the team members

Conflict management

Resolving issues

Unacceptable behavior

Issues which may arise among the team members should be resolved as early as possible and in the right manner

The members of the team should always conduct themselves well and avoid engaging in unacceptable acts

Responsiveness

Responding to requests from other team members

The members of the team should be in a position to respond to issues from other members without any delay

Other

Recreational facilities for team members

In future, there should be recreational facilities and services for various project teams

Action Items/Future Projects

What remains to be done on this project or as a result of this project?

The future projects may include:

Updating the current software of the ABC Company

Checking the system regularly in order to ascertain that the software and hardware systems are compatible

Providing regular trainings to members of staff until they are fully conversant with the new hardware system

Project Acceptance

Signature of sponsor

Printed name of sponsor

Date

Signature of project manager

Printed name of project manager

Date

Works Cited

Bloch, M., Blumberg, S., & Laartz, J. (2012). Delivering large-scale IT projects on time, on budget, and on value. Harvard Business Review.

Lock, D. (2017). The essentials of project management. Routledge.

Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management32(2), 202-217.

Raymond, L., & Bergeron, F. (2008). Project management information systems: An empirical study of their impact on project managers and project success. International Journal of Project Management26(2), 213-220.

Soekiman, A., Pribadi, K. S., Soemardi, B. W., & Wirahadikusumah, R. D. (2011). Factors relating to labor productivity affecting the project schedule performance in Indonesia. Procedia engineering14, 865-873.