Wk 5 - Project Management Plan

profileQiana.Reynolds
ProjectActivitiesandSequences.edited.final.docx

Running Head: PROJECT ACTIVITIES AND SEQUENCES

Project Activities and Sequences Scenario Paper

Qiana Reynolds

University of Phoenix

Project Management/CPMGT-301

December 7, 2020

Instructor: Gary Denney

Project Activities and Sequencing Scenario

Work Breakdown Structure and a project schedule are crucial to have a successful outcome for the Acme Shipping and Warehouse company. The Work Breakdown Structure is fundamental because it breaks each task and milestone into more refined, and gives a project manager knowledge to continue the project. Acme Shipping and Warehouse is a company that has outdated software that needs to be updated. This includes the software within the tracking, shipping, and receiving database. Within this paper, we will identify the project's scope, define the needs of the stakeholder, create the Work Breakdown Structure schedule, and list the tools and milestones necessary to complete the project.

Project Scope

Within the operation area, Acme Shipping and Warehouse's focus is to install the new software updates for the company called Roadrunner software. This software ensures tracking, receiving, shipping, and even inventory is being tracked correctly. The computers will be down, and there will be five employees who will be trained in updating the software on the computers. In this case, only the trained employees will have the chance to undertake the Roadrunner software and administer the updates company-wide.

Project Stakeholders

The first stakeholder is Acme Shipping and Warehouse company Operations Managers, who are directly affected by the project's success or failure. Next are the customers who acquire products and services, which will cause computer downtime. As presented by SEBoK authors, there is a need from the stakeholders for requirements that will be represented in terms of the individual's view within the business enterprises level of operations (SEBoK authors.2015). The last stakeholder is the project team, who will directly collect the data, oversee the project's execution, and opinions from all involved in its comprehensive software update.

Work Breakdown Structure

Work Breakdown Structure

Setup

Prep

Install

Test

Train employees

Confirm computers

Allow time for delays.

Greater efficiency?

working condition

Extend store hours

Software updates

Confirm contract with

All components in

on hand

Roadrunner Software

Working order?

Schedule employees

Make working space

Install software

Meets project goals?

Find funding for Sunday pay.

Specify operating

Meets stakeholders

requirements

Expectations?

Necessary Tools

According to Levin, PMP, PgMP, and Wyzalek, PfMP (2015), launching the strategic plan involves using the organization's many departments and resources in the form of projects" (Chapter 3). First, the project team needs to contact the vendors who supplies the Roadrunner software. Then approval from the department manager of the trainers to release them from their regular duties and spend additional hours administering the updates.

The techniques involved in the issue of the aspects affected are inclusive of the methodology associated with the development of a work breakdown structure. There are two simple stages within the phase to make for the elements of the following topics.

The tools that are available include the example of the instrument which are used for the actualization of the needed process, in this case, include the likes of

1. WBS template

2. Tree diagrams

3. Table

4. Microsoft project

Project Milestones

The milestones of a project are like significant trail markers you insert in your project schedule. In this project, there are five milestones. "Each of those five deliverables—initiation, planning, execution, control, and closeout—branch of the main deliverable" ("The Ultimate Guide To... Work Breakdown Structure", 2020). The project initiation, which included the project charter created and developed. During this milestone, the project goals and initial plan are brought together. Planning of the project, for example, the software purchase. This milestone is also created and developed within the platform of operation. Under this segment is needed to develop a training schedule to charter for the affected issues, which is the software update.

Project launch of the computer software is next. The computers are set-up for installation of the new software. Lastly is the project closeout, which involves testing all computers to make sure it's working correctly.

Project Tasks/Subtask Diagram

Programs

Roadrunner software update

01-00-00

Projects 1

Software

01-01-00

Task

Purchase

01-01-01

Task

Software update evaluation

01-01-02

Project 2

Training

01-02-00

Task

Training timetable

01-02-01

Task

Training documentation

01-02-02

Projects 3

Communication

01-03-00

Task

Communication plan

01-03-01

Task

Communication templates

01-03-02

Project 4

Computer software update

01-04-00

Task

Backup critical files

01-04-01

Task

Update computer software

01-04-02

Task

Verify software update

01-04-03

Task

Remedies and solutions

01-04-03

References

The Ultimate Guide to... Work Breakdown Structure (2020). https://www.projectmanager.com/work-breakdown-structure

Levin, PMP, PgMP, Dr. G., & Wyzalek, PfMP, J. (2015). Portfolio Management, a Strategic Approach. https://portal.phoenix.edu/library.html.

SEBoK authors. (2015). Stakeholder Needs and Requirements. Retrieved from http://sebokwiki.org/w/index.php?title=Stakeholder_Needs_and_Requirements&oldid=51430