| WBS | Task Name | Duration | Start | Finish | Predecessors | Total project cost |
| 0 | Project A+ | | Mon 9/9/13 |
| 1 | Initiating | 10.5 days |
| 1.1 | Stakeholder identification | 1 wk |
| 1.2 | Stakeholder register completed | 0 days | | | 2 |
| 1.3 | Stakeholder management strategy completed | 0 days | | | 2 |
| 1.4 | Project charter | 1 wk | | | 2FS-50% |
| 1.5 | Project charter completed | 0 days | | | 5 |
| 1.6 | Kickoff meeting | 3 days | | | 2,6 |
| 1.7 | Kickoff meeting completed | 0 days | | | 6,7 |
| 2 | Planning | 9 days |
| 2.1 | Project schedule | 5 days | | | 5,12FS-50% |
| 2.2 | Gantt chart completed | 0 days | | | 10 |
| 2.3 | Scope statement | 8 days | | | 5 |
| 2.4 | Initial scope statement completed | 0 days | | | 12 |
| 3 | Executing | 45 days |
| 3.1 | Deliverable 1 | 3 wks | | | 12 |
| 3.2 | Deliverable 2 | 5 wks | | | 18 |
| 3.3 | Deliverable 3 | 6 wks | | | 18 |
| 3.4 | Deliverable 1 completed | 0 days | | | 15 |
| 3.5 | Deliverable 2 completed | 0 days | | | 16 |
| 3.6 | Deliverable 3 completed | 0 days | | | 17 |
| 4 | Monitoring and Controlling | 60.03 days |
| 4.1 | Actual hours tracking | 1 day | | | 2 |
| 4.2 | Project documents updates | 1 day | | | 3 |
| 4.3 | Progress report 1 | 0 days |
| 4.4 | Progress report 2 | 0 days |
| 4.5 | Team review meetings | 60.03 days | weekly |
| 4.5.1 | Team review meetings 1 | 15 mins |
| 4.5.2 | Team review meetings 2 | 15 mins |
| 4.5.3 | Team review meetings 3 | 15 mins |
| 4.5.4 | Team review meetings 4 | 15 mins |
| 4.5.5 | Team review meetings 5 | 15 mins |
| 4.5.6 | Team review meetings 6 | 15 mins |
| 4.5.7 | Team review meetings 7 | 15 mins |
| 4.5.8 | Team review meetings 8 | 15 mins |
| 4.5.9 | Team review meetings 9 | 15 mins |
| 4.5.10 | Team review meetings 10 | 15 mins |
| 4.5.11 | Team review meetings 11 | 15 mins |
| 4.5.12 | Team review meetings 12 | 15 mins |
| 4.5.13 | Team review meetings 13 | 15 mins |
| 5 | Closing | 4 days |
| 5.1 | Final project report | 4 days | | | 18,19,20 |
| 5.2 | Final project presentation | 4 days | | | 18,19,20 |
| 5.3 | Project completed | 0 days | | | 41,42 |