ID Task Name Duration (in days) Start Finish Predecessors
1 Information Technology Upgrading and Expansion Plan 60 1-Aug-20 30-Sep-20
2 Identify the Scope 5 1-Aug-20 6-Aug-20
3 Analysis/Hardware Requirements 10 12-Aug-20 22-Aug-20 2
4 Design 12 29-Aug-20 10-Sep-20 8
5 Hardware Installation and Configuration 7 23-Sep-20 24-Sep-20 18
6 Scope Analysis and Requirements ration 5 25-Sep-20 30-Sep-20 29
7 Define the scope 1 3-Oct-20 4-Oct-20 36
8 Analyze the system requirements 1 4-Oct-20 5-Oct-20 37
9 Conduct Feasibility Study 1 7-Oct-20 8-Oct-20 38
10 Preliminary project plan and project proposal 1 8-Oct-20 9-Oct-20 39
11 Project plan complete 1 9-Oct-20 10-Oct-20 40
12 System Design 12 10-Oct-20 22-Oct-20 41
13 Prepare design specification document 2 26-Oct-20 28-Oct-20 42
14 Design Review 3 28-Oct-20 31-Oct-20 43
15 Revise documents 4 31-Oct-20 4-Nov-20 44
16 Set up development environment 2 6-Nov-20 8-Nov-20 45
17 Design Process complete 1 8-Nov-20 9-Nov-20 46
18 Hardware Installation and system development 7 11-Nov-20 18-Nov-20 47
19 Hardware System Procurement 1 20-Nov-20 21-Nov-20 48
20 Configure hardware system 2 21-Nov-20 23-Nov-20 49
21 Software Installation 2 25-Nov-20 27-Nov-20 50
22 Configure and Manage Operating Systems 1 27-Nov-20 28-Nov-20 51
23 Installation Completion 1 28-Nov-20 29-Nov-20 52
24 Testing 16 25-Sep-20 11-Oct-20 29
25 Develop unit test plans using product specifications 1 23-Sep-20 24-Sep-20 53
26 Develop integration test plans using product specifications 1 24-Sep-20 25-Sep-20 55
27 Hardware Testing 9 29-Sep-20 8-Oct-20 56
28 Software Testing 5 18-Oct-20 23-Oct-20 54
29 Training 53 25-Oct-20 17-Dec-20 60
30 Develop test plans 3 25-Oct-20 28-Oct-20 62
31 Develop user training materials 5 28-Oct-20 2-Nov-20 63
32 Schedule trainings 3 4-Nov-20 7-Nov-20 62
33 Hardware Testing 9 7-Nov-20 16-Nov-20 64
34 Review hardware components 1 7-Nov-20 8-Nov-20
35 Test component modules to product specifications 1 8-Nov-20 9-Nov-20 66
36 Identify anomalies to product specifications 2 11-Nov-20 13-Nov-20 67
37 Configure hardware 2 13-Nov-20 15-Nov-20 68
38 Re-test configured hardware 1 15-Nov-20 16-Nov-20 69
39 Hardware testing complete 2 18-Nov-20 20-Nov-20 70
40 Develop training specifications for end users 1 20-Nov-20 21-Nov-20 65
41 Develop training specifications for help desk support staff 1 21-Nov-20 22-Nov-20 72
42 Finalize training materials 1 22-Nov-20 23-Nov-20 73
43 Signoffs 3 25-Nov-20 28-Nov-20 74
44 Get signoffs on the plans and deliverables 3 28-Nov-20 1-Dec-20 75
45 Software Testing 5 11-Nov-20 16-Nov-20 76
46 Develop the test cases 1 18-Nov-20 19-Nov-20 77
47 Unit Testing 1 19-Nov-20 20-Nov-20 78
48 Integrating Testing 1 20-Nov-20 21-Nov-20 79
49 Functionality Testing 1 21-Nov-20 22-Nov-20 80
50 Testing Evaluation 1 22-Nov-20 23-Nov-20 81
51 Implementation 153 25-Nov-20 27-Apr-21 82
52 Implement changes suggested in system 3 25-Nov-20 28-Nov-20 83
53 Component Design implementation 3 19-Nov-20 22-Nov-20 84
54 Implementation starts 3 24-Nov-20 27-Nov-20 85
55 Assessment Evaluation 1 27-Dec-20 28-Dec-20 86
56 System evaluation 2 30-Dec-20 1-Jan-21 87
57 Prepare user manual 1 1-Jan-21 2-Jan-21 88
58 User sign-offs 2 2-Jan-21 4-Jan-21 89
59 Deployment 51 8-Nov-21 29-Dec-21 61
60 Determine final deployment strate 3 6-Jan-21 9-Jan-21
61 gyDevelop deployment methodolog 5 9-Jan-21 14-Jan-21 92
62 yDeploy software 1 16-Jan-21 17-Jan-21 93
63 Deployment complete 1 17-Jan-21 18-Jan-21 94
64 Expansion Plan Completed 1 8-Nov-20 9-Nov-20 95
Task Name Duration (in days) Start Finish
1 Information Technology Upgrading and Expansion Plan 60 1-Aug-20 30-Sep-20
6 Scope Analysis and Requirements ration 5 25-Sep-20 30-Sep-20
12 System Design 12 10-Oct-20 22-Oct-20
18 Hardware Installation and system development 7 11-Nov-20 18-Nov-20
24 Testing 16 25-Sep-20 11-Oct-20
29 Training 53 25-Oct-20 17-Dec-20
33 Hardware Testing 9 7-Nov-20 16-Nov-20
45 Software Testing 5 11-Nov-20 16-Nov-20
51 Implementation 153 25-Nov-20 27-Apr-21
59 Deployment 51 8-Nov-21 29-Dec-21
64 Expansion Plan Completed 1 8-Nov-20 9-Nov-20

Gantt Chart

Start Information Technology Upgrading and Expansion Plan Scope Analysis and Requirements ration System Design Hardware Installation and system development Testing Training Hardware Testing Software Testing Implementation Deployment Expansion Plan Completed 44044 44099 44114 44146 44099 44129 44142 44146 44160 44508 44143 Duration Information Technology Upgrading and Expansion Plan Scope Analysis and Requirements ration System Design Hardware Installation and system development Testing Training Hardware Testing Software Testing Implementation Deployment Expansion Plan Completed 60 5 12 7 16 53 9 5 153 51 1