PROJECT PLAN
ID Task Name Duration (in days) Start Finish Predecessors
1 Information Technology Upgrading and Expansion Plan 60 Saturday, August 01, 2020 Wednesday, September 30, 2020
2 Identify the Scope 5 Saturday, August 01, 2020 Thursday, August 06, 2020
3 Analysis/Hardware Requirements 10 Wednesday, August 12, 2020 Saturday, August 22, 2020 2
4 Design 12 Saturday, August 29, 2020 Thursday, September 10, 2020 8
5 Hardware Installation and Configuration 7 Wednesday, September 16, 2020 Wednesday, September 23, 2020 18
6 Scope Analysis and Requirements ration 5 Friday, September 25, 2020 Wednesday, September 30, 2020 29
7 Define the scope 1 Saturday, October 03, 2020 Sunday, October 04, 2020 36
8 Analyze the system requirements 1 Sunday, October 04, 2020 Monday, October 05, 2020 37
9 Conduct Feasibility Study 1 Wednesday, October 07, 2020 Thursday, October 08, 2020 38
10 Preliminary project plan and project proposal 1 Thursday, October 08, 2020 Friday, October 09, 2020 39
11 Project plan complete 1 Friday, October 09, 2020 Saturday, October 10, 2020 40
12 System Design 12 Saturday, October 10, 2020 Thursday, October 22, 2020 41
13 Prepare design specification document 2 Monday, October 26, 2020 Wednesday, October 28, 2020 42
14 Design Review 3 Wednesday, October 28, 2020 Saturday, October 31, 2020 43
15 Revise documents 4 Saturday, October 31, 2020 Wednesday, November 04, 2020 44
16 Set up development environment 2 Friday, November 06, 2020 Sunday, November 08, 2020 45
17 Design Process complete 1 Sunday, November 08, 2020 Monday, November 09, 2020 46
18 Hardware Installation and system development 7 Wednesday, November 11, 2020 Wednesday, November 18, 2020 47
19 Hardware System Procurement 1 Friday, November 20, 2020 Saturday, November 21, 2020 48
20 Configure hardware system 2 Saturday, November 21, 2020 Monday, November 23, 2020 49
21 Software Installation 2 Wednesday, November 25, 2020 Friday, November 27, 2020 50
22 Configure and Manage Operating Systems 1 Friday, November 27, 2020 Saturday, November 28, 2020 51
23 Installation Completion 1 Saturday, November 28, 2020 Sunday, November 29, 2020 52
24 Testing 16 Friday, September 25, 2020 Sunday, October 11, 2020 29
25 Develop unit test plans using product specifications 1 Wednesday, September 23, 2020 Thursday, September 24, 2020 53
26 Develop integration test plans using product specifications 1 Thursday, September 24, 2020 Friday, September 25, 2020 55
27 Hardware Testing 9 Tuesday, September 29, 2020 Thursday, October 08, 2020 56
28 Software Testing 5 Sunday, October 18, 2020 Friday, October 23, 2020 54
29 Training 53 Sunday, October 25, 2020 Thursday, December 17, 2020 60
30 Develop test plans 3 Sunday, October 25, 2020 Wednesday, October 28, 2020 62
31 Develop user training materials 5 Wednesday, October 28, 2020 Monday, November 02, 2020 63
32 Schedule trainings 3 Wednesday, November 04, 2020 Saturday, November 07, 2020 62
33 Hardware Testing 9 Saturday, November 07, 2020 Monday, November 16, 2020 64
34 Review hardware components 1 Saturday, November 07, 2020 Sunday, November 08, 2020
35 Test component modules to product specifications 1 Sunday, November 08, 2020 Monday, November 09, 2020 66
36 Identify anomalies to product specifications 2 Wednesday, November 11, 2020 Friday, November 13, 2020 67
37 Configure hardware 2 Friday, November 13, 2020 Sunday, November 15, 2020 68
38 Re-test configured hardware 1 Sunday, November 15, 2020 Monday, November 16, 2020 69
39 Hardware testing complete 2 Wednesday, November 18, 2020 Friday, November 20, 2020 70
40 Develop training specifications for end users 1 Friday, November 20, 2020 Saturday, November 21, 2020 65
41 Develop training specifications for help desk support staff 1 Saturday, November 21, 2020 Sunday, November 22, 2020 72
42 Finalize training materials 1 Sunday, November 22, 2020 Monday, November 23, 2020 73
43 Signoffs 3 Wednesday, November 25, 2020 Saturday, November 28, 2020 74
44 Get signoffs on the plans and deliverables 3 Saturday, November 28, 2020 Tuesday, December 01, 2020 75
45 Software Testing 5 Wednesday, November 11, 2020 Monday, November 16, 2020 76
46 Develop the test cases 1 Wednesday, November 18, 2020 Thursday, November 19, 2020 77
47 Unit Testing 1 Thursday, November 19, 2020 Friday, November 20, 2020 78
48 Integrating Testing 1 Friday, November 20, 2020 Saturday, November 21, 2020 79
49 Functionality Testing 1 Saturday, November 21, 2020 Sunday, November 22, 2020 80
50 Testing Evaluation 1 Sunday, November 22, 2020 Monday, November 23, 2020 81
51 Implementation 153 Wednesday, November 25, 2020 Tuesday, April 27, 2021 82
52 Implement changes suggested in system 3 Wednesday, November 25, 2020 Saturday, November 28, 2020 83
53 Component Design implementation 3 Thursday, November 19, 2020 Sunday, November 22, 2020 84
54 Implementation starts 3 Tuesday, November 24, 2020 Friday, November 27, 2020 85
55 Assessment Evaluation 1 Sunday, December 27, 2020 Monday, December 28, 2020 86
56 System evaluation 2 Wednesday, December 30, 2020 Friday, January 01, 2021 87
57 Prepare user manual 1 Friday, January 01, 2021 Saturday, January 02, 2021 88
58 User sign-offs 2 Saturday, January 02, 2021 Monday, January 04, 2021 89
59 Deployment 51 Monday, November 08, 2021 Wednesday, December 29, 2021 61
60 Determine final deployment strate 3 Wednesday, January 06, 2021 Saturday, January 09, 2021
61 gyDevelop deployment methodolog 5 Saturday, January 09, 2021 Thursday, January 14, 2021 92
62 yDeploy software 1 Saturday, January 16, 2021 Sunday, January 17, 2021 93
63 Deployment complete 1 Sunday, January 17, 2021 Monday, January 18, 2021 94
64 Expansion Plan Completed 1 Sunday, November 08, 2020 Monday, November 09, 2020 95