IT Project Plan

profilemarkin_98
Project_1_Scheduletemplate1.xlsx

IT services for a new building

Analysis,Planning and IT services for a new building
WBS Task Duration Predecessor Resource Comment:
1.0 Building Construction Ready to Occupy Labours and material
1.1 Purchase of Computers,Laptops,cables,routers,Printers,servers,Projectors,VOIP phones,TVs 5400 min Network Administrator
1.1.1 receive of Computers,Laptops,cables,routers,Printers,servers,Projectors,VOIP phones,TVs 3780 min Network Administrator
1.1.2 store 2160 min Network Administrator
1.1.3 Install ethernet cabling projectors and all computer lab training computers 3780 min Network Administrator
1.2 Test cabling 2700 min Network Administrator
1.3 Network servers Installations 2700 min Network Administrator
1.4 New computers Installations 2700 min Network Administrator
1.5 corporate software and Testing 2700 min Network Administrator
1.6 System Network Access 1620 min Network Administrator
1.7 Wireless Systems Installation 1620 min Network Administrator
1.8 Network Printers Installation 2160 min Network Administrator
1.9 Deploy wireless Projectors 1620 min Network Administrator
1.10 Desktops access via direct cabling 1620 min Network Administrator
1.11 Mobile laptops access wirelessly 1620 min Network Administrator
1.12 Installation completed This is a milestone with zero minutes
Specialists
2.0 IT Office
2.1 4 network servers 2700 min Hardware/Network Administrator
2.2 2 laptop computers 540 min Network Administrator
2.3 2 VOIP phones 540 min Network Administrator
2.4 IT Communications Closets x min Network Administrator
2.5 1 laptop,1 VOIP phone 120 min Network Administrator
Specialty rooms 10
wireless ceiling-mounted Projector 120 min Network Administrator
desktop connected to network and Projector 120 min Network Administrator
2.12 completed 0 min This is a milestone with zero minutes
3.0 Computer Labs 2
3.1 Lab 1- 25 desktops connected Network 1.Projector 1.Printer 1.VOIP phone installation 1.desktop networked to Projector 2700 min Network Administrator
3.2 Lab 2 -25 desktops connected Network 1.Projector 1.Printer 1.VOIP phone installation 1.desktop networked to Projector 2700 min Network Administrator
3.3 Completed 5400 min etc.
3.4 Administrative Areas This is a milestone with zero minutes
4 workstations with a desktop via a network A LAN printer A VOIP phone 1440 min Network Administrator
Individual Offices
3.5 40 offices will each have • desktop computer networked via a network port • VOIP phone 4320 min Network Administrator
3.6 1st Floor Conference Room
Awireless ceiling-mounted Projector connectivity networked from the VOIP phone for laptop use VOIP phone 480 min Network Administrator
3.7 Common Areas
4 Common areas and 4 Work areas building into 4 distinct areas. Each main hallways has wireless access point installed every 50 feet one WAP must support the entire midpoint foyer VOIP phone installed in the midpoint foyer on each of the 2 floors VOIP phone installed in the middle of the hallway in each distinct unit (4 total)LAN printer networked via the VOIP phone VOIP phone 2400 min Network Administrator

Grant_Chart

Row Labels
3 days
Deploy wireless Projectors
Desktops access via direct cabling
Mobile laptops access wirelessly
System Network Access
Wireless Systems Installation
4 days
Network Printers Installation
store
5 days
corporate software and Testing
Network servers Installations
New computers Installations
Test cabling
7 days
Install ethernet cabling projectors and all computer lab training computers
receive of Computers,Laptops,cables,routers,Printers,servers,Projectors,VOIP phones,TVs
Grand Total

pertchart