Project 1
Module 2 Directing & Managing Project Work
Week 4
PROJ6003 – PROJECT EXECUTION AND CONTROL
Ibrahim Abdallah [email protected]
Learning Facilitator
Master of Global Project Management
Today’s Schedule
Module 2 – What we’ll cover
Key processes within Executing Process Group
Assessment 1 Q&A Session
Module 2
Directing & Managing Project Work
Module 3
Module 4
Where we are…
4
Module 4
• Is the process of leading and performing the work defined in the project
management plan and implementing approved changes to achieve the
project objectives.
5
Direct and Manage Project Work
• Objective: To complete the project as planned and meet the project’s
objectives
6
Direct and Manage Project Work Cont’d
Team &
Resources Risks
P e rf
o rm
a n
c e
7
Approved Changes
Corrective action Preventive action Defect repair
An intentional activity that
realigns the performance of
the project work with the
project management plan.
According to ASQ (2015),
corrective action eliminates
the cause of nonconformities
to prevent recurrence.
An intentional activity that
ensures the future performance
of the project work is aligned with
the project management plan.
Preventive action determines and
eliminates the causes of potential
non-conformities to prevent
occurrence (ASQ, 2015).
An intentional
activity to modify a
nonconforming
product or product
component
8
• It is the process of using existing knowledge and
creating new knowledge to achieve project’s objectives
and contribute to organisational learning.
9
Manage Project Knowledge
Source: PMBOK (PMI, 2017, p. 98)
• There are two types of knowledge: Explicit and Tacit, which are managed in this
process for two purposes:
• Reusing existing knowledge
• Creating new knowledge.
10
Manage Project Knowledge Cont’d
• Previously called Acquire Project Team, it is the process of
obtaining team members, facilities, equipment, materials,
supplies, and other resources necessary to complete the
project work.
11
Acquire Resources
• Factors to be considered during team/resources acquisition:
12
Acquire Resources Cont’d
Negotiation & Influence
• Effectively negotiate and influence others who are in a position to provide the required team and physical resources for the project.
Failure to acquire the necessary resources:
• May affect project schedules, budgets, customer satisfaction, quality, and risks. Insufficient capabilities decrease the likelihood of project success.
If the team resources are not available due to any constraints:
• The project manager/team may be required to assign alternative resources.
Project Team Components
13
Core team
Client team
Contract team
• Be with the project from
beginning till the end
• To be identified as early
as possible
• Participate in early
definition and planning of
the project
• Participate in the project kick-off
meeting
• Unlikely to be full-time
• To be kept informed of project status
• A result of outsourcing
processes due to
shortage of staff/skills
• Work on the project for
only short periods of
time
• Leave as soon as the
assigned tasks completed
Characteristics of Core Team
14
Shared responsibility
Task oriented Team Focus
Commitment Cohesion
Ability to use PM tools
Empowered
Diversity Self-Awareness
Structured
Ability to work within constraints
Communication
Competence
Interdependence
Recognition
• The use of virtual teams creates new possibilities when acquiring project team
members. Virtual teams can be defined as groups of people with a shared goal
who fulfil their roles with little or no time spent on face-to-face meetings.
Virtual Teams
• Can you think of any benefits of
working with virtual teams?
• And what about challenges?
Virtual Teams... Challenge or opportunity?
• Using a multi-criteria decision analysis tool, criteria are developed and used to
rate or score potential resources. The criteria are weighted according to the
relative importance for the project and values can be changed for different
types of resources.
• Some examples of selection criteria are:
17
Project Team Selection Criteria
Availability
Cost
Experience
AbilityKnowledge
Skills
Attitude
• Develop Project Team is the process of improving competencies, team member
interaction, and overall team environment to enhance project performance.
18
Develop Project Team
Source: PMBOK (PMI, 2017, p. 336)
Key benefits:
• Results in improved teamwork
• Enhanced people skills and
competencies
• Motivated employees
• Reduced attrition
• Reduces staff turnover rates
• Improved overall project
performance.
• PMs require skills to identify, build, maintain, motivate, lead, and inspire project
teams to achieve high team performance and to meet the project’s objectives.
19
Develop Project Team Cont’d
Why develop teams?
https://www.linkedin.com/pulse/8-characteristics-high-
performing-teams-dr-tim-baker/
• One of the models used to describe team development is the Tuckman ladder or
Tuckman’s Model, which includes five stages of development that teams may go
through.
20
Team Development Model
Teams evolve overtime and
go through a series of
stages from when they are
established to when they
disband.
21
5 Dysfunctions of a Team
Jon T (2015). Patrick Lencioni – 5 Dysfunctions of a Team. [Video file]. Retrieved from: https://www.youtube.com/watch?v=inftqUOLFaM
Manage Project Team
22
Manage Project Team is the process of tracking team member performance,
providing feedback, resolving issues, and managing team changes to optimise
project performance.
Source: PMBOK (PMI, 2017, p. 345)
The key benefit of this process is that it
influences team behaviour, manages
conflict, resolves issues, and appraises
team member performance.
“Developing and
managing good
relationships – this
is what project
leadership is about”
(Anderson, 2010). “How well we manage
human interactions is the
key to the success of any
project” (Wong, 2007).
Thomas-Kilmann Conflict Styles:
Conflict Management
• Successful conflict management results in greater
productivity and positive working relationships.
Effective Decision Making
Manage Project Team – Tools & Techniques
• Is the process of obtaining seller responses, selecting a seller, and awarding a
contract.
24
Conduct Procurements
Conducting
Procurement Vendor
Solicitation
Vendor
Evaluation
Vendor
Selection
Most projects require some form of external purchasing (procurement) in order to meet
their goals. Successful sub-contracting requires knowledge of the types of contracts
available, as well as how to write them: RFI, RFQ, RFP, SOW, etc.
• How bidder proposals are evaluated.
• The buyer seeks to ensure that the
proposal selected will offer the best quality
for the services required
Source Selection Criteria
Understand the need
Costs
Technical capability
Risk
Management approach
Technical approach
Warranty
Financial capacity
Future development or interests
Business size
References
Past performance
Intellectual property rights
Procurement Types
A fixed total price of a
defined product, service,
or result to be provided.
Changes in scope may
be accommodated, but
generally with an
increase in contract price.
A hybrid type of
contractual arrangement
that contain aspects of
both cost-reimbursable
and fixed-price contracts.
May be subject to a cost
increase for the buyer.
This contract involves
payments (cost
reimbursements) to the
seller for all legitimate
actual costs incurred for
completed work, plus a
fee representing seller
profit.
• Is the process of
communicating and
working with stakeholders
to meet their
needs/expectations,
address issues as they
occur, and foster
appropriate stakeholder
engagement in project
activities throughout the
project life cycle.
27
Manage Stakeholder Engagement
28
Manage Stakeholder Engagement Cont’d
Collect feedback from Stakeholders
Cultural Awareness: Consider cultural differences & requirements
Negotiation to achieve support or agreement
Political Awareness: Understand power balance within and around project
Ground Rules: Team Charter– Set expected behaviour to manage
stakeholder engagement
Manage Stakeholder Engagement Cont’d
29
30
Interpersonal and Management Skills
Build trust
Direct healthy conflict
Active listening
Get buy in for changes
Facilitate consensus
Influence positively
Negotiate win-win approach
Modify behaviours
Assessments Overview
Assessments Timeframes
Assessment Task Overview Weight Due Date
Assessment 1 – Change Management Plan
Integrated Change Report (Individual Assessment) 40% End of Module 3
(Week 6)
Assessment 2 – Risk and Communication Management
Risk Management Report (Group Assessment) 40% First Half of Module 5
(Week 9)
Assessment 3 – Project Status Reporting
Module 4-5 Discussion Forum (Individual Assessment) 20% First Half of Module 6
(Week 11)
Total for Subject: 100%
32
You will use it for all your Assessments…
Have you had a chance to read it for a discussion?
PROJ6003_Assessment Case Study_The Case of IV Pumps in a Health Care Centre
Case Study
33
Assessment 2 – Group Formation
To complete this assessment task, you must:
Form groups of three (3) people.
Groups will be formed by students themselves or assigned by the Learning Facilitator in
consultation with the students, if required.
Only in exceptional situation a different group size may be approved by the Learning
Facilitator.
The deadline for team formation is 11:59pm AEST/AEDT Friday end of Module 2 (Week
4) to be advised to the Learning Facilitator in class or via email.
34
Assessment 1
35
Assessment 1 – Task Summary
In this assessment, you are required to write an individual report of 2000 words
(excluding tables, figures, and graphs) proposing a change to be implemented in the
case study, provided by the Learning Facilitator, addressing:
• Change impact analysis,
• Tools & techniques to manage the change,
• Integrated change control process to submit the change,
• Options to implement the change along with its associated risks.
A change request form must also be submitted attached to the report demonstrating
how the change would be requested for the given project.
The intention of this assessment is that you take a practical approach by considering
this change to be submitted to key stakeholders of given case study.
Please refer to the Task Instructions for details on how to complete this task.
36
Assessment 1 – Key Requirements
The report should encompass a practical approach in addressing the following requirements:
a) Identify and propose one (1) change you believe is required for the case study and
justify it by applying tools & techniques from quality management in identifying root-
cause for the issues found in the case study.
b) Critically analyse the impacts of your change proposal on scope, time, cost, quality of
the project.
c) Propose and justify tools & techniques used to manage the change.
d) Explain what processes are involved in submitting your change request given the
scale of your change proposal and address responsibilities considering the stakeholders from
your case study.
e) Identify and discuss options (at least 2) to satisfy the proposed change and any risks
associated with each of these options.
f) Complete the Change Request Form (CRF) provided or one that is used from a workplace.
37
▪ You are not supposed to
investigate the issues, but
rather propose 1 change!
▪ From this change, follow a
change management process
that makes sense to your
change proposal.
▪ Be specific!
Propose options to implement the change
What are the available options to actually implement the change?
What are the risks associated with each option?
Consider your change proposition Discuss the scale of the change proposed before determining the best process to conduct
that specific change.
“All models are wrong… some are useful” George Box
Analyse the change & its impact on the project
What is the impact of the change in scope, time, cost and quality?
What tools & techniques can help manage the change?
Identify & Propose one change
Propose and explain the change (1 Change)
A few tips..
Change Request Form Template
Do not fill out this part.
1. Cover Page:
• Student Name, Student ID, Lecturer, Date, Assessment
2. Executive Summary
3. Table of Contents
4. Introduction (Overview/Purpose)
5. Body of the Report (Headings)
• Follow overall paper themes/topics
6. Conclusion
7. References
8. Appendix (Change Request template here)
Assessment 1 Basic Structure
REPORT FORMAT!
HINT!
▪ Make it dynamic!
Use diagrams, tables,
illustrations..
Please refer to the Task Instructions for details on how to complete this task.
Submission Instructions
Submit Assessment 1 via the Assessment link in the main navigation menu in PROJ6003 –
Project Execution and Control.
The Learning Facilitator will provide feedback via the Grade Centre in the LMS portal.
Feedback can be viewed in My Grades.
If submitting more than one document:
Please note during the submission process: If you would like to include appendix items in your
submission, once your first item has been uploaded, click ‘Browse Your Computer’ to attach
your extra documents as an appendix. Then click Final Submit button.
41
Any Questions or Concerns?
PROJ6003 – PROJECT EXECUTION AND CONTROL
Don’t forget!
I’m here to facilitate your journey, the rest is up to you!
But, when in need, don’t hesitate to contact me via the
Ask the Facilitator Forum or at [email protected].