Project 1
Module 1 Extra on EVA & Trend Analysis
PROJ6003 – PROJECT EXECUTION AND CONTROL
Ibrahim Abdallah [email protected]
Learning Facilitator
Master of Global Project Management
• EVA: SV (Schedule Variance) and SPI (Schedule
Performance Index=EV/PV) are used to assess the
magnitude of variation of the original schedule
baseline. Measures efficiency of the work performed
comparing the earned value to the planned value. If in
SPI, ratio is greater than 1, than the project is ahead of
schedule.
• VERY GOOD VIDEO that summarises EVA:
https://www.youtube.com/watch?v=U313VMm2r7Q
Control Schedule - Tools & Techniques
Earned Value Analysis – SV & SPI
Control Costs - Tools and Techniques
Planned value
Earned value
Actual cost
Schedule Variance =
EV-PV
Cost Variance = EV - AC
Schedule performance
index = EV/PV
Cost performance index =
EV/AC
• It is just a standard way to measure a project’s progress at any point in time
using money figure.
• Earned Value is necessary to provide a realistic estimate of performance
against a time-phased budget.
• Compares the Performance Measurement Baseline to the actual schedule and
cost performance.
• EVM integrates the scope, schedule and cost baselines to form the
Performance Measurement Baseline.
• EVM develops and monitors three key dimensions for each work package and
control account: • Earned value = budgeted cost of work performed = the % of work completed using the
original budget
• Planned value = budgeted cost of work scheduled
• Actual cost = actual cost of work performed
4
EVA explained…
1. Earned Value Management (Technique)
EVM is an objective
technique to measure the
project performance.
The underpinning notion is that
any amount of completed
project work creates value
of the project.
Using EVM, the current project
performance is measured by
comparing the EV against the
baseline or Planned Value
(PV).
Larson and Gray (2011, p. 459)
• Planned Value (PV) is the value of what should have been completed (what has
been planned).
• Earned Value (EV) is the value of what work has been completed.
• Actual Cost (AC) is the actual cost or how much we have currently spent.
• Schedule Variance (SV) is the difference between Earned Value (what has been
completed) and Planned Value (What has been planned or should have been
completed).
• The formula is SV = EV - PV and if the result is negative, then the project is behind
schedule.
• Cost Variance (CV) is the difference between Earned Value (what has been
completed) and Actual Cost (how much we have currently spent).
• The formula is CV = EV-AC and if the value is negative then we are over budget, ie we
have spent more than we should have.
6
In other words…
PMI, 2017, p. 267
Larson and Gray (2011, p. 462)
CV = EV – AC
CV = 200 – 340
CV = -140 Negative = Overbudget
SV = EV – PV
SV = 200 – 300
SV = -100 Negative = Behind Schedule
Earned Value Interpretation Practice
Larson and Gray (2011, p. 463)
EV < PV
SV = NEGATIVE
Behind schedule
EV < AC
CV = NEGATIVE
Over budget
EV > PV
SV = POSITIVE
Ahead schedule
EV > AC
CV = POSITIVE
Under budget
EV > PV
SV = POSTIVE
Ahead schedule
EV < AC
CV = NEGATIVE
Over budget
EV < PV
SV = NEGATIVE
Behind schedule
EV > AC
CV = POSITIVE
Under budget
Earned Value Example 2
Status Report
Planned values
Remember:
CV = EV – AC
SV = EV – PV
Using Indexes instead of absolute values to
determine the efficiency ratios:
Percentage Complete Index (PCIB) = EV/BAC
PCIB indicates the work accomplished in
percentage of total $ budgeted (BAC)
Cost Performance Indicator (CPI) = EV/AC
Measures cost efficiency of the work
accomplished. It is the most accepted index used.
It is very accurate, reliable and stable.
Schedule Performance Indicator (SPI) = EV/PV
Measures schedule efficiency to date.
Another Way of Monitoring Progress
Percentage Complete Index (PCIB) = EV/BAC
Graphical Interpretation of the values from the
previous example using End of Period 7.
Earned Value Practice Activity
Planned Budget:
Actual:
Planned Gantt-Chart:
AC EV PV
Solution: https://www.youtube.com/watch?v=z7b3SYQuqJM
As the project progresses, the project team may develop a forecast for the estimate
at completion (EAC) that may differ from the budget at completion (BAC) based on
the project performance.
• Forecasting involves making projections of conditions and events in the project’s
future based on current performance information and other knowledge available at
the time of the forecast.
• Forecasts, thus, are generated and updated as a result of the work performance
data (which means, you will need to perform a EVA prior to forecast the project).
• There’s a range of EAC calculations that can be used to represent
different risk scenarios…
2. Trend Analysis (Technique)
Forecasting - Estimate At Completion
1.0 EAC = AC + Bottom-up ETC
• This formula is used when original estimation is based on wrong
data/assumptions or circumstances have changed. It calculates actual costs
plus new estimate for the remaining work.
• ETC (Estimate to Complete) – expected costs to finish all the remaining work.
• Required to reestimate the remainder work from bottom up.
2. Trend Analysis (Technique) Cont’d
2.0 EAC forecast ETC work performed at the planned rate
EAC = AC + (BAC - EV)
• This method accepts the actual performance to date (favourable or not).
• The variance is caused by a one-time event and is not likely to happen again.
This formula is used if the future work (ETC) will be
accomplished at the planned rate.
• It considers that the BAC can still be used as a means to project future.
2. Trend Analysis (Technique) Cont’d
3.0 EAC forecast for ETC work performed at the present CPI
EAC = BAC / CPI
• This formula is used when original estimation is met without any deviation. It
means that your project is going well and what it has been predicted to date will
be expected in the future.
• CPI is expected to be the same for the remainder of the project.
• You are maintaining the CPI and SPI as 1 and you have to continue the project
in the same way. It is always good for a project manager if he or she is
maintaining the CPI and SPI as 1 or more than 1.
2. Trend Analysis (Technique) Cont’d
4.0 EAC forecast for ETC work considering both SPI and CPI factors
EAC = AC + [(BAC – EV) / (CPI x SPI)]
• This formula is used to calculate actual cost to date plus the remaining budget
changed based on the performance. Not everything is good, you have irregular
indexes, so you need to put into the EAC this index to see how much money
you will need to finish up the project.
• In other words, if both the CPI and SPI influence the remaining work.
2. Trend Analysis (Technique) Cont’d
3. To-Complete Performance Index (Technique)
A measure of the cost
performance that is required to
be achieved with the remaining
resources in order to meet a
specified management goal.
This ratio measures the amount
of value each remaining dollar in
the budget must earn to stay
within the budget.
TCPI = Work remaining / Funds Remaining
TCPI = (BAC-EV)/(BAC-AC)
TCPI = (EAC-EV)/(EAC-AC)
Any Questions or Concerns?
PROJ6003 – PROJECT EXECUTION AND CONTROL
Don’t forget!
I’m here to facilitate your journey, the rest is up to you!
But, when in need, don’t hesitate to contact me via the
Ask the Facilitator Forum or at [email protected].