PROJ592
COURSE PROJECT TASKS AND DELIVERABLES
Course Project Part 5—Due Week 5 (graded, 35 points)
|
|||
|
Assignment |
Tasks |
Deliverable(s) |
Points |
|
Earned Value Analysis
|
1. Set the project status date to a date that is halfway through your project. Your project should show the tasks completed as of that date and any cost changes that have occurred. At least 10% of your task should reflect a cost overrun and 5% should come in below budget. You can choose which tasks to modify. See below:
1. Complete the Earned Value Analysis (EVA) utilizing all three methods. Go to [REPORT>Costs>Earned Value Report]. See below:
2. Save the report as a PDF |
Earned Value Report – PDF
|
15 points |
|
Project Status Communica-tion
|
Interpret the results of the EVA and write a narrative as a Project Status communication in an MS Word document. The interpretation of the following calculation is required: 1. Variance Analysis 2. Performance Index 3. Project Percentage Analysis |
Project Status with EVA interpretation (Word doc) |
20 points |