Program Plan Elements:

No One Goes Hungry

Alan Brou

Suhui Liu

Linrui Liu

Qizhen Li

07/24/2019

Final Version

Executive Summary

This report outlines our program on the topic about a charitable activity. As graduate students, our team members are also thinking about what we can do for the society. Fortunately, one of our team members was involved in a public welfare project several years ago, which was about collecting food and daily supplies for the poor. The serious phenomenon of poor community intrigued our program management team due to our connection with the concept.

To address this issue, our team decided to develop and launch a website that is designed to make our task easier. In order to operate and promote the website to be well known in the country or even in the world, we need to do some projects include fundraising, recruitment of volunteers, community service and marketing. This report will also take into consideration all risks that we may encounter during the program. We are confident that all those risks will be hedged using appropriate strategies.

Introduction to the Program Plan

In this report, you will find our initial summary of the following using the Smartsheet Templates:

Business Case

A good business case is credible and compelling. It provides qualitative and quantitative cost-benefit analysis information.

Program Master Calendar

Easily communicate milestones and important meetings across multiple projects. With the Program Master Calendar, it is easy to keep items up to date, share the latest schedule with stakeholders

Program Management Charter

A good charter not only establishes the scope, goals, and budget of the PMO, but also stimulates discussion.

Program Governance Structure

Documenting a program’s governance structure helps stakeholders understand the program's methodologies, frameworks and context for how decisions are made.

Program Milestones

This template can be used to create a milestone chart for monitoring progress of the various projects. You include this chart as part of the program plan to highlight major events.

6. Program Change Control

Manage change requests with this change control form template. This form includes sections for documenting the reason for the change, costs and benefits, priority level, work required, approval, and implementation.

7. Program Governance Structure

Documenting a program’s governance structure helps stakeholders understand the program's methodologies, frameworks and context for how decisions are made.

Detailed Project Plan for Any One Project

We are also describing a complete Initiation phase and Project plan – including subsidiary plans for one project using the Kanabar Templates.

BUSINESS CASE (No One Goes Hungry Program)

BRIEF PROJECT BACKGROUND

People in many poor areas lack food and food, in which case many social welfare organizations need help and donations.

GENERAL AIMS

Goal - Our program is a platform for caring people in society who want to care and donate to people in poor areas.

INITIAL RISKS

High risk: Fundraising(strategic)

Medium risk:Time management(strategic and objective)

Low risks: Communication(strategic and objective), Food contamination(objective), Volunteers’ safety

Acceptable risk: Food waste

EXPECTED OUTCOMES

1. Ensure that more than 15% of poor community can eat nutritious food.

2. Increase donations by 10% in a six months period.

3.Increase people’s awareness and number of volunteers

PROGRAM BENEFITS

OPERATIONAL BENEFITS – 10% increasing donations would increase in six months.

STRATEGIC BENEFITS – promote our program’s awareness in public

COST or SIZE ESTIMATES

Three point method for all projects and non-project work.

P 4L O /6

P1 = Feasibility 750,000 + 4(1,000,000) + 1,250,000 = 1,000,000

P2 = Developing website … 15,000, 20,000 25,000

10% contingency

TIME ESTIMATES

21days+31.7days+5.2days+5.2days+5.2days+5.2days+30.8days+3days=107.2days

Samaritan Center Program-Charter and Management Plan

Prepared by: Qizhen Li

Program Name: No one goes hungry

Program Sponsor: JP Morgan

Program Manager:QIZHEN LI

Estimated start date:09/01/2019

Estimated finish date:01/20/2020

Program Scope

Program description

We expect to raise around 1 million dollars for our program that we describe as a journey to create a better community. We intend to hire staff, cook and provide food to people in the street every week.

Preliminary Understanding of Business Need

In order to realize our goal, we will need the help of sponsors and a lot of volunteers.

Benefits

This section describes the Benefits to be gained by our program.

Brief name

Description

Tangible or intangible?

Metrics

Expected benefit delivery date

Related program milestones and component projects

· Food sharing

· Less hungry people in the street .

intangible

Less beggar in the street ( decreased by 3%)

114 days

Serving

· Program awareness

Promote Program’s awareness

intangible

More volunteers & more donations (5-10% more)

60 days

Social Media and Marketing

H Healthier neighborhood

provide nutritious & healthier food / less risk of disease

intangible

Less people dying of food disease (3% less )

114 days

Cooking/ Healthy food menu

Program components and/or member projects

Component / Project name

Manager

Description

Primary deliverables

Estimated delivery date

Fundraising

Alan Brou

Negotiate with JP Morgan

14 days

21 days max

Hiring staff

Suhui Liu

Hire staff to help us accomplish programs

20 days

30 days

Cooking /healthy food menu

Linrui Liu

Cooking for community

4 days /w

5 days /w

Organizing and preparing ( includes testing food )

Xiansen Wu

Testing food / putting food in boxes etc..

4 days /w (2-3 hours )

5 days / w (2-3 hours)

serving

Haiqian Long

Distribute food to different locations for less favored communities

4 days /w

5 days /w

cleaning after service

Huijun Cai

Cleaning after services ( plastic boxes, recycle etc.)

4 days /w

5 days/ w

Social Media marketing

Azizah

Record our work and publish it on social media so that people can be aware of our program and activities.

1 day /w

2 days /w

Looking for volunteers (websites /school)

Dan Podeanu

Looking for people that want to occasionally participate in this program for free, and help community.

25 days

30 days

Training volunteers

Jasmine

Training students who want to participate in our activities

2 days

3 days

In Scope

This section lists the items that are to be included in this program.

Out of Scope

This section lists the items that are not to be included in this program.

Work and Program Processes

Preliminary Description of Work

This is a high level statement of the work that is required to complete this program.

Standard project management activities

This is a formal description of how changes will be submitted, evaluated, and either included or rejected in a member project. Some of the larger projects may be required to appoint a change review board.

Program steering committee

Steering committee structure and members

This section includes the steering committee members and roles as well as an outline of the meeting schedule.

Decisions

This section describes the decision making approach the committee will follow. It includes a detailed list of decision guidelines and agreed upon priorities against which decisions will be made. This section should also outline how decisions will be documented and communicated.

Reviews

Stage gate reviews: This section outlines stage gate reviews and their requirements. It should include when these reviews will be held, what will be reviewed, and the data to be reviewed prior to determining whether to move to the next stage.

Program performance reviews: This section establishes the dates for which program performance will be reviewed. These reviews concentrate on the overall performance and management of the program. This section also describes the required program performance information that must be provided in support of these reviews.

Program and component change requests: This section identifies the process the steering committee will use to manage change to the program. A process will be outlined for changing the scope of the program and initiating or terminating program components.

Risks, impacts, and dependencies

This section includes:

· Identification and ranking of program level and critical project level risks based on probability of occurrence and level of impact. Each risk will have a mitigation plan and one safe contingency plan.

· Dependencies matrix for components and other closely related activities.

· Description of impacts the program and its member projects may have on other University work and organizations.

Program and critical project risks

Risk

Risk Description

Impact (How would this risk impact schedule, budget or scope)

Likelihood of Occurrence (What is the chance or this risk situation occurring on this project: High/Medium/Low)

Mitigation and Contingency Plan (What steps would be taken to avoid the risk? What would be done if it happened?)

Owner and Trigger (Who monitors for this risk and how do we know the risk has become reality?)

Fund raising

Risk in terms of raising enough funds from sponsors. Without money we can not start the program.

This would prevent us from hiring staff, and providing food to the community.

High because Banks might not support us or agree with our budget.

Accept to delay our program if we do not find any sponsor / ask multiple sponsors to increase the probability of finding at least one sponsor (transfer method)

Alan Brou

Time management

Time to hire staff / training time may vary

This would delay the length of our program, and reduce efficiency .

Medium

Suhui Liu

Communication

Miscommunication between organism representatives and sponsors, staff/ transition between hiring - cooking - serving - cleaning.

A lack of communication would delay the accomplishment of our projects / less efficiency

Low

Prevent - more training for staff.

Linrui Liu

Food contamination

Food that we serve might get contaminated

Spread disease in the community - the total opposite of our program. This may ruin everything we worked for

Low

Prevent by testing our food before serving it to community.

Shanice Liang

Volunteers safety

Our volunteers might be serving food in dangerous neighborhoods.

If volunteers are hurt while working, our corporation’s image will be affected ,and we might lose staff.

Low

Prevent- by paying an insurance for our staff and volunteers

Blair Zheng

Food waste

Left over after serving

this would embody a less efficient cooking and service from us but this is manageable.

Acceptable

Accept it. We will just try to be more efficient in future services.

Kenneth Kai

Dependencies

The information for this section is best represented with a network diagram showing program components and milestones and their dependencies.

Component A

Component B

Milestone 1

Program level timeline

This section includes:

· Gantt chart of major project deliverables and their dependencies.

· Identification of program level and key project decision points, decision makers, and a description of the decision process to be used.

· Program level milestones and check-up points for program sponsors.

Preliminary Estimate of Program Size

This is the initial estimate that is based upon the program proposal. This estimate should be the best guess at the time of filling out the charter & may not necessarily match what is listed in the program proposal or what will eventually be listed in the project charters and plans. Detailed estimates will be coming at a later date.

Initial roles and authority

Role and Name

Authority and decisions

Approval

Program Sponsor

JP morgan

Y

Program Manager

QIZHEN Li

Y

Steering committee (see above section for full details)

Alan Brou - Fundraiser

Y

HR

Suhui Liu

Y

Operation Manager

Linrui Liu

Y

PROJECT SPONSOR: Jamie Dimon PROJECT MANAGER: QIZHEN Li

SIGNED:JD DATE: 7/25/2019

[No One Goes Hungry] Program Governance and Steering Committee

Prepared by: [Qizhen Li]

Program Name:No One Goes Hungry

Program Sponsor:JP Morgan

Program Manager:Qizhen Li

Steering committee structure and members

This section includes the steering committee members and roles as well as an outline of the meeting schedule.

Decisions

This section describes the decision making approach the committee will follow. It includes a detailed list of decision guidelines and agreed upon priorities against which decisions will be made. This section should also outline how decisions will be documented and communicated.

Reviews

Stage gate reviews: This section outlines stage gate reviews and their requirements. It should include when these reviews will be held, what will be reviewed, and the data to be reviewed prior to determining whether to move to the next stage.

Program performance reviews: This section establishes the dates for which program performance will be reviewed. These reviews concentrate on the overall performance and management of the program. This section also describes the required program performance information that must be provided in support of these reviews.

Program and component change requests: This section identifies the process the steering committee will use to manage change to the program. A process will be outlined for changing scope of the program and initiating or terminating program components.

Stakeholder Worksheet

Prepared by: [Qizhen Li] Do NOT distribute after completed

This table contains sample information to help start the process. It is not complete. Please do not limit your stakeholders to the items in this table.

Name and Role

Main Goal of Communication

Communication Preferences (how often, method, and detail)

Overrun Tolerances

Notes

Examples: project sponsor, team member, end user, support, program sponsor, project managers,

Examples: encourage collaboration | action on specific risks or issues | provide money or time or resources | prioritize project | provide public support/sponsorship | improve team morale | recognize team performance | influence attitude | manage expectations | ensure future timely responses

How often examples: daily | weekly | major milestones | exceptions only as they occur | on demand

Method examples: in person | sharepoint | email | report | informal conversations | presentations | conferences | special events | newspaper articles | newsletters | web sites | web casts | through executive sponsor only

Detail examples: all tasks and details | milestones and issues | issues only | general progress against schedule| general information about program

Describe their tolerances for a budget or schedule overrun. Which would they prefer? What are acceptable reasons for such an overrun.

Other notes (not all need to be documented, but they should be thought about): special interests, impacts on their group, higher priority initiatives, how will they measure success, what is their attitude, do they have a big influence over other stakeholders, how have they affected other projects, who do they influence and who influences them, perceived benefits if program succeeds, perceived benefits if program fail.

Campus IT Groups

To market the project within the campus hence boosting contributions to the project.

Daily through online presentations

Any amount contributed will be highly appreciated

Other students interested to join the move are welcomed with a registration fee of $10

Other folks using program resources

Supporting the project financially

On demand

Not limited to any contribution limits

Helps in achieving the project goals

Owners of any systems that interface with or can be affected by this program

Support the project in developing online links

As the come

Limited to the campus

Helps in reaching many well wishers as possible

Potential clients including current clients of other ongoing work

Providing financial support to the project

Any time when they are ready through the campus website

Not limited to the amount of contribution

Boosts the project financially.

Specific Clients

Moral support besides financially

Weekly in the project milestones

Minimum of the agreed contribution but not limited to any maximum contribution

Financially boosts the project

Specific Functional Representatives

Helps the project team in identification of shortcomings.

Weekly via presentations

All the time

Prevents downfall of the project

Specific team members

Supporting the project agendas

Daily through conferences and presentations

Limited to project supporting information

Helps in marketing the project agendas

Support team

Encourages the project besides offering financial assistance and advice

Any time via presentations

Not limited in their support

Gives morale to the project team

Vendors

Supporting the project with quality food products (Eskerod, & Jepsen, 2016).

Daily

Not limited to their support

Helps in the realization of the project goals

Students

Helps in the distribution of food staffs

Daily

Only during off studies sessions

Helps in reaching out for the hungry ones

Campus Business Managers

Supporting the group with project implementation tips

Daily

Not limited on their support

Helps in reaching out for potential sponsors of the project

Faculty

Supporting the project financially and in terms of human resource like advisors

Daily

Not limited in project support

Helps in attaining the project goals

Principal Investigators

Helps in ensuring smooth flow of activities

Daily

Not limited in their duties

Helps in project agenda implementation.

Granting agencies

Helping financially

Any time

Not limited to their assistance

Helps in finding potential sponsors

Community members

Helping in identification of poor individuals in the community

Daily

Not limited in their support

Helps in meeting the project agendas

[No One Goes Hungry] Communication Plan

Overview

This section provides a summary of the communication strategy for the overall program. It should provide an overview of how information flows between components, from components to the program level, and out to internal and external customers. If there are common approaches and goals for specific stakeholder groups, these approaches and assumptions should be detailed here.

Escalation and feedback

This section contains an outline of the escalation process for communication activities. It also documents how feedback such as email questions, service desk tickets, newspaper articles, interviews, etc.are handled.

Responsibility and authority

This section provides an outline of the type of communication activities that will occur during this process and the person who is generally responsible for those types. This section also identifies the person who generally has the authority to approve or implement the communication. In many cases the responsible person and the authorizer are the same.

Communication activities

What

Who/Target

Purpose

When/Frequency

Type/Method(s)

Program Kick-off Meeting

Project team

Planning for subsequent proceedings

Once

Meeting

Stage Gate Review

Project team

Assuring that the OMB and HHS requirements are observed (Yamaguchi et al. 2018).

Monthly

Meeting

Program Component Status Reports and Review

Project Stakeholders and project team

To inform on the project progress

Weekly

Meeting

Component Status Meetings

Project team and stakeholders

Reflection of the project’s current UI components.

Weekly

Meeting

Sub team working meetings or discussions

Project sub-team members.

Sharing on the progress and finding solutions for the problems faced.

Weekly

Face to face meeting

Sponsor Meetings

Project design, technical and team members

Discussing the achievements, progress besides the changes that might be necessary in the initial plan.

Monthly

Meeting

Steering Committee Meetings

Project manager, stakeholders, and sponsors

Discussing the implementation of the proposed changes in the project

Monthly

Face to face Meeting

Program Review

Project team and stakeholders

Identification of the deliverables which have been produced to the present besides examining whether the project has met its objectives.

Monthly or after every project phase

Face to face meetings

Periodic Demos and Target Presentations

Audience

Presenting the project progress and the project impact to the society

Monthly

Face to face meetings

Communications to component team members

Project team

Reviewing the component status and design proceedings (Comins, Llewellyn, & Offiler, 2017).

Weekly

Email and conference call

Program level issues. risks, and escalation

Project manager and stakeholders

Discussing on the effective implementation of the ERM system in the project

Weekly

Face to face meeting

Roll-out, change and deployment announcements

Project sponsors, stakeholders and project manager

Endorsing the necessary changes to the project.

As needed

Face to face meeting

Program decisions

Project manager and project team

Deciding on the shortcomings and making the necessary decisions

Weekly

Face to face meeting

Lessons learned

Project team

Making the necessary changes from the learnt lessons

Monthly

Face to face meeting

Reviews for program performance. benefits realization, risks, change requests, and resources

Project manager and the project risk manager

Making general overview of the additional resources in the project besides ascertaining the risks associated with the project (Budde, Alkemade, & Hekkert, 2015).

As needed

Face to face meetings

Project community awareness creation

Audience and Project manager

Discussing the benefits of the project to the community

Once

Face to face meeting.

WBS Tree Diagram for the Program & Projects

PROGRAM TITLE

No One Goes Hungry

COMPANY NAME

Samaritan Center

PROGRAM MANAGER

Qizhen Li

DATE

09/01/2019

MILESTONE CHART (for all the projects and Non-project work)

MILESTONE

PROJECT MANAGER

DEADLINE Month/year

Get fundings around $900,000

Qizhen Li

10/2019

Partner with local restaurants and supermarkets

Qizhen Li

10/2019

Hire full-time employees

Qizhen Li

9/2019

Hire IT people to establish website

Qizhen Li

10/2019

Partner with schools and volunteer websites

Qizhen Li

11/2019

Training Volunteers

Qizhen Li

10/2019

Acquire place settings for program & projects operation

Qizhen Li

9/2019

Collecting from donations or purchasing equipment & tools

Qizhen Li

9/2019

Promotion in local communities

Qizhen Li

9/2019

More than 200 local poverty group join the program

Qizhen Li

11/2019

Timeline settings for operation time

Qizhen Li

10/2019

Risk Analysis and Assessment

Qizhen Li

9/2019

Complete project charter

Qizhen Li

9/2019

Food and daily goods quality and safety control

Qizhen Li

1/2020

Food and daily goods serving

Qizhen Li

1/2020

RISK ANALYSIS FOR THE PROGRAM

RISK DESCRIPTION

LIKELIHOOD

(high, medium, low)

IMPACT

(high, medium, low)

ACTION REQUIRED

OWNER

Fund raising

High

High

Mitigate : ask more sponsors than expected and pitch on benefits of program through facebook and other social media before creating our own website

Managers

Time management

Medium

Medium

Mitigate : start each project earlier than expected. Also, overestimate time for project accomplishment so that there are no bad surprises.

Managers

Communication

Low

High

Mitigate : getting sponsors and stakeholders more involved in the projects by meeting them every month or two weeks.

Managers

Food contamination

Low

High

Prevent : Test the food before serving it to people

Scientists

Volunteers safety

Low

High

Transfer: by purchasing insurance for employees

Insurance

Food waste

Low

Low

Accept

NA

PROJECT DEFINITION FORM FOR ANY ONE PROJECT

PROJECT TITLE

Food & daily goods project

PROJECT SPONSOR

JP morgan Chase

PROJECT BACKGROUND

In order for this project to make a good first impression and also get stakeholders and sponsors more involved, we need good organization. In fact, we consider working with a lot of volunteers, but we need to hire and train cooks and get staff more involved in our vision. This project involves training staff to cook, serve and organized the distribution of healthy nutrients to community.

PROJECT BENEFITS

Less hungry people in the street- Food sharing - Healthier food in poor community - less diseases caused by the consumption of unhealthy food- Less death by hunger.

PROJECT OBJECTIVES

Distribute food to poor community 5 times a week. ( Cook, place food in boxes, go to poor neighborhood, share, clean )

PROJECT DELIVERABLES

114 DAYS

MEASURABLE CRITERIA FOR SUCCESS

Less sick people in poor community (3%).

CONSTRAINTS

Not too much diversity in foods we will provide / distribution of foods will be limited to 1-2 times a day.

KEY ASSUMPTIONS

More poor people will eat healthier, and avoid certain diseases.

PROJECT MANAGER

Linrui Liu / ROLE RESPONSIBILITIES : Reach out sponsors for

PROJECT SPONSOR

JP MORGAN CHASE / ROLE RESPONSIBILITIES: Provide us funds to pay for food, cooks , people who will test the food etc.

OPTIONAL

Change Control Form Template

PROJECT TITLE

PROJECT SPONSOR

CHANGE REQUEST

ORIGINATOR NAME

DATE OF REQUEST

ORIGINATOR CONTACT INFO

CHANGE

ID NO.

ITEMS TO BE CHANGED

ARGUMENT REFERENCE(S)

CHANGE DESCRIPTION

ESTIMATED FINANCIAL IMPACT

ESTIMATED TIMELINE IMPACT

PRIORITY / CONSTRAINTS

CHANGE EVALUATION

ASPECTS AFFECTED

WORK REQUIRED

RELATED REQUESTS

DATE EVALUATED

EVALUATOR NAME

EVALUATOR SIGNATURE

CHANGE APPROVAL

ACCEPTED - REJECTED - HOLD

DATE APPROVED

APPROVED BY

SIGNATURE

COMMENTS

CHANGE IMPLEMENTATION

ASSET

IMPLEMENTER

DATE EXECUTED

SIGNATURE

CHANGE

ID NO.

AUTHORIZER

CHANGE DESCRIPTION

DATE EVALUATED

DATE EVALUATED

DATE APPROVED

DATE EXECUTED

Conclusion and Findings:

In this paper, we decided to evaluate the implementation of a program called "No One Goes Hungry " designed to manage the problem that poor community lacks of food and daily goods. In order to set up this program, we focused on some important program management tools and area that helped us to achieve the final goal of our program. It includes the program management charter, program governance and steering committee, WBS trees, program communication, key risks and milestone assumptions. Our team made a lot of efforts and commitment to set up a website and make it functional to satisfy our stakeholders expectations.

In order to prove our program is efficient, the measurement might be the key factor. First, we five program managers have learned many lessons from the program. In the process of completing this program, we learned how to use Wechat app and google drive to communicate our creative ideas and some formal documents. All the knowledge we have learned here in this program will be useful for other programs in the future as well. In other words, the accumulated experience increased the probability of success of other programs. Although there will be some differences between programs and specific problems need to be analyzed, some parts of teamwork are almost the same. Therefore, lessons learned from this program can serve as recommendations for other programs.

For the project itself, by building a website, Raising donations and food can help people in many deprived communities to Increase health in more deprived community. We increase people's awareness and number of volunteers in our program. This kind of donation and helping activity can guide more people into the area of donation. The issue of poor community will come back on the stage.