PROJ587 Course Project - Amazon

profileunknown_person
Program_Resource_Management_Sample1.xlsx

Instructions

INSTRUCTIONS
1. Change the starting month and drag it across the table.
2. Select the resource group.
3. Select the resource type.
4. Enter the program component name.
5. Enter the number of resources of that type and group.
NOTE: Change the drop-down menus.
Right-click worksheet name and select "Unhide."
Add or change the drop-down items.
RIght-click worksheet name and select "Hide."

Program Resource Summary

Component Name Start End Duration January February March April May June July August September October November December
Project A January August 7 17 17 17 12 17 17 12 12 0 0 0 0
Project B March September 6 0 0 19 29 16 10 8 15 14 0 0 0
Project C
0
`
Total

Resource Management

Resource Group Resource Type Component Name January February March April May June July August September October November December Start
Team Members Specialists Project A 5 5 5 5 5
Equipment Machine 1 Project A 1 1 1 1 1 1 1 1
Team Members Project Managers Project A 1 1 1 1 1 1 1 1
Team Members Technicians Project A 10 10 10 10 10 10 10 10
Team Members Technicians Project B 7 7 7 7 7 7
Team Members Specialists Project B 3 3 3 2 2
Equipment Machine 1 Project B 1 1 1 1 1
Team Members Developers Project B 18 18 5 5 5 17
Team Members Specialists Project C 5 5
Team Members Project Managers Project C 1 1 1
Technicians 10 10 10 17 17 17 17 17 7 0 0 0 0
Project Managers 1 1 1 1 1 1 1 1 1 1 1 0 0
Specialists 5 5 5 3 8 8 0 2 7 5 0 0 0
Labor 0 0 0 0 0 0 0 0 0 0 0 0 0
Developers 0 0 18 18 5 0 0 5 5 0 0 0 0
Machine 1 1 1 2 2 2 1 2 2 0 0 0 0 0
TOTAL 17 17 36 41 33 27 20 27 20 6 1 0

DropDown

Resource Group ResourceType Available Resources
Team Members Technicians 5
Equipment Project Managers 10
Material/Supplies Specialists 8
Labor 25
Developers 5
Machine 1 1