Running Head: PROCUREMENT PROJECT 1
PROCUREMENT PROJECT
Student number : W20048453
Professor’s name : Dr. Victor Samwinga
Course title : Procurement and Supply Chain Management
PROCUREMENT PROJECT 2
Riverside Sunderland city Procurement manual
Executive summary
The paper focuses on providing a directive guide for the Sunderland city council in
developing sustainable housing projects for its local communities. It focuses on the techniques of
procurement which will be applicable in sourcing the needed expertise in the project. Digital
technologies are applied to ensure that all the needed services and products are made known to
the public to help interested suppliers and professionals send their proposals for placement into
the project.
Factors surrounding the use of available financial resources are discussed in the paper as
well. The project has limited finances, which are sourced from the city council as well as the
private investors involved in the project. Following the budget line and ensuring all resources are
directed towards the indented channels is made possible by outlining the prices from the
respective services and products that will be required. The procurement technique allows the city
council to meet the time deadlines which have been set. It ensures that they have adequate time
to evaluate the skill sets and compensations for the interested individuals. The properties to be
included on a standard form of contract are listed to ensure that the project managers understand
what aspects will make certain tender submissions better than others. It outlines the kind of talent
and skills that will be required from the contractors. The discussion outlines the special designs
of construction are developed in the Riverside Sunderland city.
PROCUREMENT PROJECT 3
Riverside Sunderland city Procurement manual
Contents
Introduction ................................................................................................................................5
Procurement framework ..........................................................................................................5
Organization of procurement .......................................................................................................7
Overview of the process of procurement..................................................................................7
Procurement authority .............................................................................................................9
Contract award ........................................................................................................................9
Acquisition planning and procurement strategy ......................................................................... 10
Standard form contract .......................................................................................................... 10
Sourcing.................................................................................................................................... 11
Management of submissions ..................................................................................................... 12
Tender opening committee .................................................................................................... 12
Safeguarding operations of electronic-tendering .................................................................... 12
Modification or withdrawal of submissions ........................................................................... 14
Evaluation of submissions ......................................................................................................... 14
Evaluation criteria ................................................................................................................. 14
Evaluation methodologies ..................................................................................................... 15
Financial evaluation .............................................................................................................. 16
Negotiations .......................................................................................................................... 17
Reviews by committee on contracts ....................................................................................... 18
PROCUREMENT PROJECT 4
Riverside Sunderland city Procurement manual
Contract finalization and issuance ............................................................................................. 18
Contract finalization discussion ............................................................................................. 18
Contract issuance .................................................................................................................. 19
Conclusion ................................................................................................................................ 20
Recommendations ..................................................................................................................... 21
References ................................................................................................................................ 21
Glossary .................................................................................................................................... 24
Appendix A: Procurement plan sample format .......................................................................... 25
Appendix B: Contract register sample report ............................................................................. 25
Appendix C: Evaluation of contract award sample report .......................................................... 26
Appendix D: Service Demand & Deliver………………………………………………………..25
PROCUREMENT PROJECT 5
Riverside Sunderland city Procurement manual
Introduction
Forecasting and development of specific strategies are operations that influence the future
outcomes in any community. Planning decisions that are made contribute to shaping society in
determining the kind of homes individuals will live in, the working environment that we operate
in, the placement of areas for relaxing, and the traveling roads that community members will use.
The local authorities establish local plans in pursuit of improving the livelihood of the members.
The city council of Sunderland has statutory duty to transform the city through being able to
understand how the assets of the city, such as land and property required to be protected as a way
of meeting the issues that the city is facing. It is crucial to establish an environment that supports
investments from private institutions to ensure that the determined needs in development can be
fulfilled.
Riverside Sunderland is a project that involves developing a new urban quarter by the
city council of Sunderland in collaboration with investors such as Vitality Life. The plan is to be
executed on a superb riverside site in the central part of the city. The city council hopes to build
around one thousand homes which are to be occupied by approximately two thousand and five
hundred individuals (Ahmad.et.al, 2019)The plan also involves using around one million square
feet of area to develop offices that could offer jobs for a labor force ranging between eight
thousand and ten thousand workers.
Procurement framework
The local plan developed in the city is directed towards establishing a flexible strategic
agenda that will outline the development operations. The framework will showcase the
conditions necessary for making the plan successful and assist in encouraging and supporting
PROCUREMENT PROJECT 6
Riverside Sunderland city Procurement manual
activities that are oriented toward development. The city will benefit from its capability to open a
window where businesses are promoted, and growth is encouraged. Some of these advantages
include job opportunities for the locals, offering homes that can meet the needs and expectations
of the communities within the city, and dealing with the inequalities and scarcity issues within
the surrounding. The plan will allow the local authorities to protect the natural and historic
environment assets within the city and increase the value around these assets.
Client and stakeholder needs
The main factors that have necessitated the development of this master plan are the
promotion of active citizenship and sociability among the community member, reduction of
carbon footprint, conservation of energy through having digitally enabled homes, improvement
of social infrastructure, and well as encouraging private investments. The city authorities are
only trying to integrate those aspects which they believe would make the living environment
better in the area (Ban.et.al, 2019). Realizing the goal of creating jobs among the locals is also an
important element that is fueling the strategic framework.
Client needs
The Sunderland city council seeks to ensure that the duty that the local people have
bestowed on them is carried out efficiently. They plan to drive the community to better living
standards by eliminating the problems ailing the city for so long. Their responsibility is to create
job opportunities and develop strategies to ensure that the locals can retain those jobs. The
development of environmentally friendly neighborhoods will ensure that the city can attract other
individuals seeking to live in places where people are conscious of nature. Moreover, the plan
will ensure that there is maximum use of the open spaces within the city. Using natural assets
PROCUREMENT PROJECT 7
Riverside Sunderland city Procurement manual
such as land sparingly and adequately is something that the local authorizes have been longing to
do. They want to ensure that they maximize the city communities by creating opportunities to
add to the neighborhoods.
Stakeholder needs
The private investors involved in the project are driven by their need to tap the
opportunity to share the benefits resulting from selling the houses. They also want to ensure that
they can tap future opportunities from the plan since they will be in touch with the local
authorities. The fact that the plan has very guaranteed fruitful benefits is a big driving force for
private investors. It ensures that they get to portray an image of being socially driven to meet
societal needs. The opportunity allows investors in the housing industry to make their entry into
the city and be able to ensure that the most sustainable housing options are adopted. It is an eye-
opener to them for the plans of restructuring houses within this locality. In addition, they expose
themselves to the possibility of being allowed to invest in future projects that yield more returns.
Organization of procurement
Overview of the process of procurement
Acquisition of individuals with the needed skill set to work on making the policy
framework a reality is as important as the whole process of making plans. It is crucial to entrust
the future of a city to the best-suited professionals in the housing industry. External factors such
as arrangements of funding and the city regulations in construction will be essential in selecting
the most applicable procurement technique in this scenario. One has to consider how other public
works procurement procedures have been conducted to determine how fit the selected method is.
PROCUREMENT PROJECT 8
Riverside Sunderland city Procurement manual
Source:(https://images.app.goo.gl/RMi4mdy7fdR8VVUb6)
The plan to build independent and sustainable neighborhoods will necessitate the hiring of
contractors with the capability to build therequired houses, specialists in IT to be involved in
making the homes digitally convenient, and contractors who can build the required roads within
the structured community.
The stakeholders have to ensure that they take financial budgets and time deadlines into
account when selecting the procurement method to apply. With a very short deadline and high
expectations to meet, it is crucial to use a procurement technique that will allow the client to
quickly access the needed talent. In this case, therefore, the electronic procurement technique
will be suited to professional sourcing skills which are needed in the project. The technique
ensures that only the registered users will be able to place their bids for the opportunity. It allows
PROCUREMENT PROJECT 9
Riverside Sunderland city Procurement manual
the client to have an easy time during the assessment of the applications that are set. Considering
the city council ought to ensure that all interested contractors get a chance to try and acquire the
employment position, there should be open communication to the community.
Procurement authority
The city council commissioner should delegate the procurement duties to the appropriate
officials to ensure that authorized individuals can ensure this process is completed successfully.
There should be a review committee that should govern the operations against fraudulent
activities. They ought to ensure that the activities carried out during the sourcing of services are
conducted fairly and without any malpractices. The procurement officer will ensure that
necessary procurement capacity and infrastructure are set up to allow the operations to run
smoothly. The review committee ought to be involved in scenarios where the appointed
authorities are undecided on the most suitable candidates for the position. The table shows
circumstances and accesses whether or not the committee could be required.
Scenarios Requires review committee
More than one submission is approved Yes
Only one tender submission is approved No
Claims of irregularities arise Yes
The contract notice fails to be displayed to the
public
Yes
The selected candidate has higher prices than
the budgeted ones
Yes
Contract award
Only the tender submissions that meet the necessary criteria of the project should be
awarded the opportunity to work with this city. Using digital means in procuring experts to fill
the positions set in the project will ensure the local authorities follow the outlined employment
PROCUREMENT PROJECT 10
Riverside Sunderland city Procurement manual
rules and avoid discrimination against certain groups of people. The city council will be able to
attract a large pool of professionals who are in need of a job. As a result, they will have a larger
group of highly skilled people, and thus they will be in a position to select contractors who are
most suited for the job (Dada.et.al, 2017). The technique will ensure that the skills of the
interested party are put to the test and determined to be fitting perfectly in this arena. Therefore,
the client will be in a position to source the expertise who can realize all the goals and objectives
set aside in the project.
Acquisition planning and procurement strategy
Standard form contract
Designing and outlining the standard contract form is useful in ensuring that the most
suited contractors can be identified at ease since their ideas will line up with the expectations that
a project has. In this case, a standard form of contract will ensure that the local authorities can
determine the role and responsibilities the contracting parties will have in relation to the
practiced construction work. They will point out those parties that have shown promising relation
to achieving what is expected in the development of Riverside Sunderland neighborhoods. The
standard form of contract should include the roles that a contractor will be playing in the project,
the tools they will use in achieving the perfect project which is envisioned, and the time duration
they could possibly take to complete the tasks.
The standard form of contract that will be utilized in this project is the Joint contract
tribunal since it will ensure the project managers can outline all processes within the project with
their respective prices. The contract will include prescriptions and guidance on the processes
concerning the administration of the contract. It will help ensure that the contracting parties
PROCUREMENT PROJECT 11
Riverside Sunderland city Procurement manual
include all their capabilities in efficiently meeting the project's requirements. The local
authorities will be able to outline all the important aspects that any contract given should have. In
doing these, they will be in a position where they can select the outstanding contract and ensure
that they can follow all the necessary requirements. The most suitable standard form of contract
will showcase all the procedures involving building all the one thousand smart homes. It should
outline the necessary financial budget that is set as well as point towards the fulfillment of the
time deadline. It is critical in development over the most likely scenario of ensuring that the
master plan becomes a reality. The JCT contract will allow the local authority to utilize the
Riverside Sunderland city master plan to ensure that all designs and construction operations are
majorly controlled by the city council.
Sourcing
The client should ensure that the contractors source the construction materials locally in
the effort of reducing costs which could be attributed to getting materials from companies that
are far away. It would guarantee that the shipment and delivery costs are eliminated, and
therefore the overall prices of the goods would be lower. Moreover, using a specific supplier to
provide the materials would ensure that they offer reasonable prices to the city council and also
have felt entitled to deliver the best quality items (Rane.et.al, 2019). In doing this, the costs that
are incurred due to the purchase of faulty products which are of poor quality would be reduced.
Utilization of the expert opinions would allow the stakeholders to avoid incidents where they are
overcharged in purchasing the products leaving the tasks of purchasing materials to given experts
would allow consistency and lower the chances of having inconsistencies within the construction
PROCUREMENT PROJECT 12
Riverside Sunderland city Procurement manual
process (Delmonico.et.al, 2018). It would be essential to source small sizes of construction
materials and make other orders of purchases as soon as need be to allow the accounting of all
items and avoid misplacement of materials, which could negatively influence cost reduction
efforts.
Management of submissions
Tender opening committee
The authorized personnel should ensure that the people involved in the projects are given
the independence to analyze the tender submissions sent through the electronic-tendering
opportunities. At last, two city council members should be included in the committee to ensure
that the procurement process can be trusted. The committee is expected to keep the information
confidential to safeguard the integrity of the process.
Safeguarding operations of electronic-tendering
It is essential to ensure that the uploaded tenders are scanned for viruses before being
downloaded and utilized in procurement. The city council will be required to check on various
aspects of the contracts submitted in assessing and awarding the most deserving contractors the
tender of carrying our construction of the designed beautiful neighborhoods. Even though the
local authorities have to consider the indicated cost that different contractors have listed to be
given as compensation for their good work in the project,they will have to look at the quality of
services, the capability of aspiring contractors to meet the environmental needs, the innovative
aspect of the parties as well as the accessibility of those talents. The tender submissions will have
listed out all the characteristics that make given contracting parties efficient in handling the said
project. Thus it will be easier to list out those aspects that make them economically advantageous
PROCUREMENT PROJECT 13
Riverside Sunderland city Procurement manual
to the project. The checklist below can be used for purposes of references when assessing the
submissions.
PROCUREMENT PROJECT 14
Riverside Sunderland city Procurement manual
Sample Tender Checklist
Source :(https://images.app.goo.gl/tSTmfMyetbk4aA3V8)
Modification or withdrawal of submissions
The tenders which will be received after the deadline of application has ended should not
be considered. The procurement committee should ensure that these tenders are withdrawn from
the list of probable tenders that will be assessed. It should be noted that the submissions which
are modified in any manner by the applicants after submission will not be used. The city council
ought to implement the assessment technique which focuses on settling with the most
economically advantageous tender. The strategy will ensure the contracting party focuses not
only on the price to be incurred after hiring the given individuals but also on the overall aspects
revolving aroundthe whole construction process (Fahimnia.et.al, 2019). For instance, considering
that the project is geared towards lowering carbon footprint, the local authorities can better
identify with contractors whose methods of construction are environmentally friendly. Moreover,
they should check for the submissions that have the most reasonable and realizable goals in
connection with the outcomes of the project.They should print out a contract notice that
elaborates the most economically advantageous tender to hint at the principles required in
making their submissions and making it clear on the factors that will determine how suitable a
tenderer is in meeting the essential plans within the project.
Evaluation of submissions
Evaluation criteria
There are two steps that should be conducted in the evaluation of the submission and
determine their suitability to the contract. The local authorities of Sunderland city should conduct
PROCUREMENT PROJECT 15
Riverside Sunderland city Procurement manual
an evaluation of the technical capability of the interested party by using the individual weighted
method to evaluate the technical advantage that the individuals have over other parties. Their
past jobs can be used as a reference to determining how capable they can be of handling this
huge contract. It is also crucial to determine the pricing strategy which is listed out.
Evaluation methodologies
The selected evaluation committee should check on the pricing of the tenderers to
compare those that have the lowest and most reasonable prices. The tenders are to be positions
based on the overall score in order to select the one with the highest score. The tender that
appears to have high scores in maintaining relatively low cost and high-efficiency skills will
have the capability to reach the outcomes the council wants and has developed. Proposals with
low prices and sufficient technical skills required in the project should be considered fit (Ghosh,
2019). Also, the committee of evaluation of the tenders should look for the submissions that
include the best combination scores in regard to skills and alignment with the objectives of the
project. The table below is a sample of reports of evaluation of contract award.
PROCUREMENT PROJECT 16
Riverside Sunderland city Procurement manual
Financial evaluation
In the construction industry, pricing refers to the action of settling at a certain amount to
represent the compensation needed for specific given services. Realizing a project as big as the
Riverside Sunderland masterplan, making cost considerations is essential in avoiding delays
during construction or having money-related issues which could hinder the realization of the
goals. A reasonable and achievable pricing mechanism has to be utilized to ensure that financial
resources are allocated in all the operations that need funding. The first step would be to come up
with a conclusive report of all the available financial resources which are to be directed into the
project. The stakeholders should now make necessary decisions in regard to the amount of
money to be spent in each house and the payment the contractor should receive within the
created time frame.
PROCUREMENT PROJECT 17
Riverside Sunderland city Procurement manual
Source:( https://images.app.goo.gl/KZUBioQcmmXBVnFL7)
Negotiations
Necessary negotiations with the hired contractors are to be made to ensure that the city
council comes to an agreement on the amount of money the skills and expertise they bring to the
table are worth. All the operations within the project should be carried out within the £ 160
million budget. It, therefore, implies that all the financial operations have to be conducted with
precisions and accounted for throughout the project to help maximize their utilization (Yang &
Yu, 2019). The local authorities should ensure that they create a plan for affordable prices.
PROCUREMENT PROJECT 18
Riverside Sunderland city Procurement manual
Reviews by committee on contracts
In the construction contracts, such as in this project, the price that the suppliers who want
to be involved will offer is the tender, while the prices that are agreed upon are the contract
sums. In most cases, the prices in such projects will have room for negotiat ion and adjustments.
Therefore, the city council has to set up a certain price range which will be used to come up with
the most favorable prices. The prices would be expected to vary when the selected architect may
necessitate the established designs, quantities of materials, their respective quality, or the
necessary working condition to be changed in any given manner. Moreover, the project pricing
mechanisms should include the uncertainty of natural occurrences or other events such as the
failure of the supplier to deliver the needed items. Events leading to loss of materials will add
more incurred costs to the project, and thus they should be accounted for when developing a
pricing strategy. There is a need to ensure that some sum of money is included as an allowance
for price changes or inflation that might occur in the future during the progress of the project.
Costs resulting from statutory fees ought to be included to ensure that they can be allocated a
given sum to avoid interference with the payments to other stakeholders in the project.
Contract finalization and issuance
Contract finalization discussion
The city council has made a good decision of pairing with partners who have greater
experience in the housing market, and thus, the stakeholders can be used in making designs of
the houses and, as a result, lower the cost. Sourcing professional skills in making design models
could be an expensive experience. However, allowing the stakeholders and the client to be
directly involved in the development of houses that have certain designs could be useful in
PROCUREMENT PROJECT 19
Riverside Sunderland city Procurement manual
lowering the costs. The Sunderland city council can ensure that the models with the same
number of rooms follow one given design, and those that are anticipated to be mansionettes have
another design. In this case, therefore, only a limited number of designs would be needed, which
would be assimilated into the other homes (de Sousa Jabbour.et.al, 2017). This would encourage
uniformity in the neighborhood and also encourage better use of the natural and environmental
assets.
Contract issuance
After the committee finalizes the contract has made all the necessary discussions, it will
be an opportunity to decide the fit procedures of issuing the contract. All the working terms
should be listed out, and the arrangement for reaching out to the suppliers who have won the bid
should be on the way. The submissions with the most appropriate and well-aligned goals will be
analyzed, and the fitting contractor will be allowed to work with the city council.
PROCUREMENT PROJECT 20
Riverside Sunderland city Procurement manual
Conclusion
The master plan that the city council of Sunderland has created is useful in offering
sustainable housing options to its locals. It will allow the city to utilize its natural and land assets
to allow more growth within the community. Partnering with private investors will help the city
council source financial assistance while allowing those involved to get returns from their
investments. The project will allow the local community to reduce their carbon footprint and be
conscious of the environmental consequences of human activities. It is a brilliant idea of the local
authorities to create job opportunities for its local members who will help immensely in being
productive to societal development while being able to gain finances from these actions. The
success of a procurement process depends on the effectiveness of the committee members and
the stakeholders involved in the acquisition of the needed talents. It is crucial to ensure that the
process is reviewed and that any errors are corrected before the finalization of the discussions.
The local authorities will be able to benefit from the outlined procurement methods as well as the
devised mechanisms for pricing.
PROCUREMENT PROJECT 21
Riverside Sunderland city Procurement manual
Recommendations
It is always useful to select the tender submissions whose goals can be related to the
financial resources and the needed kind of expertise. The selection of efficient suppliers in
providing necessary materials always helps speed up the operations of the project.It is always
essential in any project to ensure that the entrusted contractors share the client's goals. Finding a
contractor who will not only have the needed skill sets but also require low compensation will
ensure that the client is able to save financial resources, which can be directed in the project to
make an outstanding difference in speeding up the operations (Villena, 2019). The project's
success will allow the future authorities to have even bigger goals that could potentially see the
whole city embrace cohesion and growth in its economy.
All the procurement procedures should be followed to the letter if the stakeholders wish
to have better chances of acquiring the talents and services they are in need of. Public projects
must follow the necessary procurement processes to prevent irregularities such as discrimination
and corruption. In doing so, the public members can have equal chances of acquiring the desired
positions within their skill set. It is the duty of the evaluation committee to help the city council
to choose the best contractors who will help ensure the operations of the projects are reached.
Financial resources should be evaluated to determine the extent to which the services which are
to be sourced should be priced.
PROCUREMENT PROJECT 22
Riverside Sunderland city Procurement manual
References
Ahmad, T., Aljafari, R., & Venkatesh, V. (2019). The government of Jamaica’s electronic
procurement system: experiences and lessons learned. Internet Research.
Ban, G. Y., Gallien, J., & Mersereau, A. J. (2019). Dynamic procurement of new products with
covariate information: The residual tree method. Manufacturing & Service Operations
Management, 21(4), 798-815.
Dada, M., Petruzzi, N. C., & Schwarz, L. B. (2017). A newsvendor’s procurement problem when
suppliers are unreliable. Manufacturing & Service Operations Management, 9(1), 9-32.
Delmonico, D., Jabbour, C. J. C., Pereira, S. C. F., de Sousa Jabbour, A. B. L., Renwick, D. W.
S., & Thomé, A. M. T. (2018). Unveiling barriers to sustainable public procurement in
emerging economies: Evidence from a leading sustainable supply chain initiative in Latin
America. Resources, Conservation and Recycling, 134, 70-79.
de Sousa Jabbour, A. B. L., Luiz, J. V. R., Luiz, O. R., Jabbour, C. J. C., Ndubisi, N. O., de
Oliveira, J. H. C., & Junior, F. H. (2017). Circular economy business models and
operations management. Journal of cleaner production, 235, 1525-1539.
Fahimnia, B., Pournader, M., Siemsen, E., Bendoly, E., & Wang, C. (2019). Behavioral
operations and supply chain management–a review and literature mapping. Decision
Sciences, 50(6), 1127-1183.
Ghosh, M. (2019). Determinants of green procurement implementation and its impact on firm
performance. Journal of Manufacturing Technology Management.
PROCUREMENT PROJECT 23
Riverside Sunderland city Procurement manual
Rane, S. B., Narvel, Y. A. M., & Bhandarkar, B. M. (2019). Developing strategies to improve
agility in the project procurement management (PPM) process: Perspective of business
intelligence (BI). Business Process Management Journal.
Villena, V. H. (2019). The missing link? The strategic role of procurement in building
sustainable supply networks. Production and Operations Management, 28(5), 1149-1172.
Yang, J., & Yu, K. (2019). The role of an integrated logistics and procurement service offered by
a 3PL firm in the supply chain. Journal of Management Analytics, 6(1), 49-66.
PROCUREMENT PROJECT 24
Riverside Sunderland city Procurement manual
Glossary
The section includes summary of the relevant terms which are applied in this procurement
manual.
Award It is the authorization that one gets after the
review committee recommends it.
Bid A response to a solicitation from a supplier
Contract An agreement which is sealed legally between
a supplier and an organization establishing the
terms and conditions of employment.
Contractor Any party to a procurement contract with a
firm
E-tendering Electronic procurement which occurs once the
activities of acquiring a procurement are done
using digital technologies.
Procurement The acquisition by lease or purchase of items,
property, services or works
Proposal An offer in response to a request for proposal
Review committee City council staff members who are required
to regulate the operations of procurement
acquisition.
Sourcing Identification process involving acquiring
suitable suppliers
PROCUREMENT PROJECT 25
Riverside Sunderland city Procurement manual
Appendix A: Procurement plan sample format
Source:( https://images.app.goo.gl/WK94aSA61rPyoQ6R9)
Appendix B: Contract register sample report
Source: (https://images.app.goo.gl/9XeroiYBcaG5hzXn6)
PROCUREMENT PROJECT 26
Riverside Sunderland city Procurement manual
Appendix C: Evaluation of contract award sample report
Source:( https://images.app.goo.gl/KZUBioQcmmXBVnFL7)
PROCUREMENT PROJECT 27
Riverside Sunderland city Procurement manual
Appendix D: Service Demand & Delivery
Source; (https://images.app.goo.gl/1MJS6yL8XeQNshDCA)
- Appendix D: Service Demand & Deliver………………………………………………………..25
- Introduction
- Procurement framework
- Organization of procurement
- Overview of the process of procurement
- Procurement authority
- Contract award
- Acquisition planning and procurement strategy
- Standard form contract
- Sourcing
- Management of submissions
- Tender opening committee
- Safeguarding operations of electronic-tendering
- Modification or withdrawal of submissions
- Evaluation of submissions
- Evaluation criteria
- Evaluation methodologies
- Financial evaluation
- Negotiations
- Reviews by committee on contracts
- Contract finalization and issuance
- Contract finalization discussion
- Contract issuance
- Conclusion
- Recommendations
- References
- Glossary
- Appendix A: Procurement plan sample format
- Appendix B: Contract register sample report
- Appendix C: Evaluation of contract award sample report
- Appendix D: Service Demand & Delivery