WBSE EXERCISE 4
WBSE Exercise.
Students Name:
Professors Name:
Date
Problem set – 4
Project Scope Statement & Work Breakdown Structure Exercise
Instructions for both exercises are contained within the attached template. Use the template to complete the activities.
Business Case (copy and paste):
West Calgary Ring Road, in Alberta, will improve access to schools, recreation, hospitals, and workplace and help to reduce the congestion in the city. The construction of this road began in 2019, and the project is expected to complete in 2024. The project's estimated cost is $1.0B. The project is needed because, when completed, it will provide more than 101km of free-flow travel around the city. When the project will be completed, it will be 101km in length. The construction will help reduce the frequency and number of trucks using public roads to haul gravel, reducing noise and enhancing safety.
Project Scope Statement.
Scope Description:
The project scope will be to create and improve a transport system that will facilitate easy access to health facilities, schools, working paces, recreational and social amenities. The essence of this will be to eliminate congestions issues and challenges the residents face, which could otherwise waste their productive time while in transit.
Key Deliverables with acceptance criteria (product scope):
|
KEY DELIVERABLES 1. Acquiring permits permission 2. Awarding contracts to subcontractors. 3. procurement of materials 4. site visit before mobilization 5. site mobilization. 6. starting of the construction of the West Calgary Ring Road |
ACCEPTANCE CRITERIA 1.submission of applications to DOT for approval. 2. project scope and expenditure, and purchases orders sent to subcontractors for finalization and signing 3. all requirements and specification lists sent to relevant authorities. 4. setting of time and place of the owner, architect, and contractor meeting to conduct site walk or visit. 5.approval of all permits and applications and acceptance of PO 6. relevant and authorized subcontractors are provided with scheduled work. Materials are already at the construction site and ready for the project to begin. |
Title of Project: West Calgary Ring Road
1. Acquiring permits.
1.1 Report of project and land agreement.
1.2 Proposal
1.3 Confirmation notice.
2. Awarding contracts to subcontractors
2.1 Tender document.
2.2 New knowledge or experiences
2.3 Checking of tender diligence documents
3. Procurement of materials
3.1 Application documentation
3.2 Cost evaluation
3.3 Reviewing tender document.
4. Site visit before mobilization
4.1Topography proof survey.
4.2 Topographical and utility assessments
4.3 Additional ground investigation contract.
5. Site mobilization.
5.1 Licensing requirements
5.2 Road edge design.
5.3 Design requirements
6. Starting of the construction of the West Calgary Ring Road
6.2 Land agreements and accommodation works.
6.3 Claims and compensation events.