Problem set in Planning the project

profileSow
Problemset2.docx

Problem set Week 6:

1. In addition to cost, what factors should be considered in selecting a building contractor? What can go wrong if the lowest bid is selected and nothing else is considered? (Answer in your own words, maximum 70 words.)

2. What is the difference between an RFP and an RFQ? Give two specific examples where an RFQ could be used and two specific examples where it is more likely that the organization will go with an RFP. (Use examples NOT from your textbook.)

3. Prepare a Pareto chart of the possible causes for a student to fail a final examination in a university course.

Problem set Week 7:

1. Describe the general processes that should be followed in managing risks throughout a project. Be sure to include the general sequence in which these processes are carried out.

2. Prepare a sample risk register for a project to put humans on Mars (four or five risks).

3. What is the difference between qualitative and quantitative risk analysis? Which one is always done? Why is the other one not always done for every project?

Problem set Week 8:

Question 1

Your team has been asked to test and document enhancements to a web application that allows buyers to purchase custom-printed canvas shoes. The tasks and dependencies are as follows:

· Create a testing plan

Once the testing plan is ready, your team can:

· Test the user interfaces

· Test the database

· Test the network

· Write the documentation first draft

When the user interface tests are complete, you can:

· Perform user testing—enlist some users to test the user interface

When the database and network testing are complete, you can:

· Perform integration testing—network with the database

When the user testing of the user interface and the database testing are complete, you can:

· Perform integration testing—database, network, and user interface

When all integration testing and user testing are complete, you can:

· Perform system testing

Then you can:

· Review and revise documentation

After all other tasks are complete, you can:

· Obtain management approval

Duration estimates for the tasks:

 a.

 3 days

 b.

 10 days

 c.

 6 days

 d.

 7 days

 e.

 20 days

 f.

 5 days

 g.

 3 days

 h.

 2 days

 i.

 8 days

 j.

 4 days

k.

 5 days

1. Create a network diagram and a Gantt chart for the project tasks. Ask your instructor if you are permitted to use software such as Microsoft Project to help you prepare your diagrams.

1. What is the planned duration for the testing project?

2. What is the critical path for the testing project?

3. For each task NOT on the critical path, calculate the amount of slack available.

4. If the user testing of the user interface takes 15 days, what will the impact be on the project duration?

Question 2

Wedding cost estimation: Given the following information, calculate the estimated costs for a wedding with 250 guests and a bridal party of six, using the methods indicated. Show your work. Note that members of the bridal party are already counted as guests, you don’t need to add them twice.

1. Parametric estimate

2. Bottom-up estimate

3. Analogous cost estimate

4. You will probably notice some differences in the estimated values. Are these differences significant? What might cause the differences? If you were estimating a significant project in the future, which method(s) would you use and why?

Wedding Cost Estimates

Item

Dollars

Groom’s brother’s wedding, last year, 175 guests, similar venue and style

$20,300

Catering

$65 per person

Photographer

$1,500

Rental of hall

$500

Clothing, bride

$2,000

Clothing, groom

$750

Flowers

$800

Other décor items

$500

Cake

$500

Gifts for bridal party

$80 each

Wedding planner

$2,000

Wedding planner’s estimate of typical cost for this kind of wedding

$10,000 plus $75 per guest

Question 3

Cost reimbursable contract calculation.

1. A contract calls for a total payment of $800,000 with a guarantee. Essentially the contractor is guaranteed to make at least $200,000 above his costs. If the contractor can demonstrate his costs exceed $600,000, the project will pay the difference, with a $50,000 ceiling on the overage. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?

2. Another option for the same contract has the contractor guaranteed to be paid his costs plus 20%, for costs that exceed $600,000. With the same initial assumption—guarantee of $800,000 gross payment (no requirement to itemize costs), but if the contractor can show that costs exceed $600,000, the project will pay $800,000 plus the costs that exceed $600,000, plus 20% of those excess costs, with a ceiling of $900,000 gross. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?

3. Under option 3.2, at what dollar amount of total costs would the contractor be assuming all of the excess costs beyond that point?

4. In which option did the project assume more of the risk of a cost overrun? Explain.

Problem set Week

6

:

1.

In

addition

to

cost,

what

factors

should

be

considered

in

selecting

a

building

contractor?

What

can

go

wrong

if

the

lowest

bid

is

selected

and

nothing

else

is

considered?

(Answer

in

your

own

words,

maximum

70

words.)

2.

What

is

the

difference

between

an

RFP

and

an

RFQ?

Give

two

specific

examples

where

an

RFQ

could

be

used

a

nd

two

specific

examples

where

it

is

more

likely

that

the

organization

will

go

with

an

RFP.

(Use

examples

NOT

from

your

textbook.)

3.

Prepare

a

Pareto

chart

of

the

possible

causes

for

a

student

to

fail

a

final

examination

in

a

university

course.

Problem set Week

7

:

1.

Descri

be

the

general

processes

that

should

be

followed

in

managing

risks

throughout

a

project.

Be

sure

to

include

the

general

sequence

in

which

these

processes

are

carried

out.

2.

Prepare

a

sample

risk

register

for

a

project

to

put

humans

on

Mars

(four

or

five

r

isks).

3.

What

is

the

difference

between

qualitative

and

quantitative

risk

analysis?

Which

one

is

always

done?

Why

is

the

other

one

not

always

done

for

every

project?

Problem set Week

8

:

Question

1

Your

team

has

been

asked

to

test

and

document

enhancements

to

a

web

application

that

allows

buyers

to

purchase

custom

-

printed

canvas

shoes.

The

tasks

and

dependencies

are

as

follows:

·

Create

a

testing

plan

Once

the

testing

plan

is

ready,

your

team

can:

·

Test

the

user

interfaces

·

Test

the

database

·

Test

the

network

·

Write

the

documentation

first

draft

Problem set Week 6:

1. In addition to cost, what factors should be considered in selecting a building

contractor? What can go wrong if the lowest bid is selected and nothing else is

considered? (Answer in your own words, maximum 70 words.)

2. What is the difference between an RFP and an RFQ? Give two specific examples

where an RFQ could be used and two specific examples where it is more likely that

the organization will go with an RFP. (Use examples NOT from your textbook.)

3. Prepare a Pareto chart of the possible causes for a student to fail a final examination

in a university course.

Problem set Week 7:

1. Describe the general processes that should be followed in managing risks

throughout a project. Be sure to include the general sequence in which these processes

are carried out.

2. Prepare a sample risk register for a project to put humans on Mars (four or five

risks).

3. What is the difference between qualitative and quantitative risk analysis? Which

one is always done? Why is the other one not always done for every project?

Problem set Week 8:

Question 1

Your team has been asked to test and document enhancements to a web application

that allows buyers to purchase custom-printed canvas shoes. The tasks and

dependencies are as follows:

 Create a testing plan

Once the testing plan is ready, your team can:

 Test the user interfaces

 Test the database

 Test the network

 Write the documentation first draft