Problem set in Planning the project
Problem set Week 6:
1. In addition to cost, what factors should be considered in selecting a building contractor? What can go wrong if the lowest bid is selected and nothing else is considered? (Answer in your own words, maximum 70 words.)
2. What is the difference between an RFP and an RFQ? Give two specific examples where an RFQ could be used and two specific examples where it is more likely that the organization will go with an RFP. (Use examples NOT from your textbook.)
3. Prepare a Pareto chart of the possible causes for a student to fail a final examination in a university course.
Problem set Week 7:
1. Describe the general processes that should be followed in managing risks throughout a project. Be sure to include the general sequence in which these processes are carried out.
2. Prepare a sample risk register for a project to put humans on Mars (four or five risks).
3. What is the difference between qualitative and quantitative risk analysis? Which one is always done? Why is the other one not always done for every project?
Problem set Week 8:
Question 1
Your team has been asked to test and document enhancements to a web application that allows buyers to purchase custom-printed canvas shoes. The tasks and dependencies are as follows:
· Create a testing plan
Once the testing plan is ready, your team can:
· Test the user interfaces
· Test the database
· Test the network
· Write the documentation first draft
When the user interface tests are complete, you can:
· Perform user testing—enlist some users to test the user interface
When the database and network testing are complete, you can:
· Perform integration testing—network with the database
When the user testing of the user interface and the database testing are complete, you can:
· Perform integration testing—database, network, and user interface
When all integration testing and user testing are complete, you can:
· Perform system testing
Then you can:
· Review and revise documentation
After all other tasks are complete, you can:
· Obtain management approval
Duration estimates for the tasks:
|
a. |
3 days |
|
b. |
10 days |
|
c. |
6 days |
|
d. |
7 days |
|
e. |
20 days |
|
f. |
5 days |
|
g. |
3 days |
|
h. |
2 days |
|
i. |
8 days |
|
j. |
4 days |
|
k. |
5 days |
1. Create a network diagram and a Gantt chart for the project tasks. Ask your instructor if you are permitted to use software such as Microsoft Project to help you prepare your diagrams.
1. What is the planned duration for the testing project?
2. What is the critical path for the testing project?
3. For each task NOT on the critical path, calculate the amount of slack available.
4. If the user testing of the user interface takes 15 days, what will the impact be on the project duration?
Question 2
Wedding cost estimation: Given the following information, calculate the estimated costs for a wedding with 250 guests and a bridal party of six, using the methods indicated. Show your work. Note that members of the bridal party are already counted as guests, you don’t need to add them twice.
1. Parametric estimate
2. Bottom-up estimate
3. Analogous cost estimate
4. You will probably notice some differences in the estimated values. Are these differences significant? What might cause the differences? If you were estimating a significant project in the future, which method(s) would you use and why?
|
Wedding Cost Estimates |
|
|
Item |
Dollars |
|
Groom’s brother’s wedding, last year, 175 guests, similar venue and style |
$20,300 |
|
Catering |
$65 per person |
|
Photographer |
$1,500 |
|
Rental of hall |
$500 |
|
Clothing, bride |
$2,000 |
|
Clothing, groom |
$750 |
|
Flowers |
$800 |
|
Other décor items |
$500 |
|
Cake |
$500 |
|
Gifts for bridal party |
$80 each |
|
Wedding planner |
$2,000 |
|
Wedding planner’s estimate of typical cost for this kind of wedding |
$10,000 plus $75 per guest |
Question 3
Cost reimbursable contract calculation.
1. A contract calls for a total payment of $800,000 with a guarantee. Essentially the contractor is guaranteed to make at least $200,000 above his costs. If the contractor can demonstrate his costs exceed $600,000, the project will pay the difference, with a $50,000 ceiling on the overage. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?
2. Another option for the same contract has the contractor guaranteed to be paid his costs plus 20%, for costs that exceed $600,000. With the same initial assumption—guarantee of $800,000 gross payment (no requirement to itemize costs), but if the contractor can show that costs exceed $600,000, the project will pay $800,000 plus the costs that exceed $600,000, plus 20% of those excess costs, with a ceiling of $900,000 gross. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?
3. Under option 3.2, at what dollar amount of total costs would the contractor be assuming all of the excess costs beyond that point?
4. In which option did the project assume more of the risk of a cost overrun? Explain.
Problem set Week
6
:
1.
In
addition
to
cost,
what
factors
should
be
considered
in
selecting
a
building
contractor?
What
can
go
wrong
if
the
lowest
bid
is
selected
and
nothing
else
is
considered?
(Answer
in
your
own
words,
maximum
70
words.)
2.
What
is
the
difference
between
an
RFP
and
an
RFQ?
Give
two
specific
examples
where
an
RFQ
could
be
used
a
nd
two
specific
examples
where
it
is
more
likely
that
the
organization
will
go
with
an
RFP.
(Use
examples
NOT
from
your
textbook.)
3.
Prepare
a
Pareto
chart
of
the
possible
causes
for
a
student
to
fail
a
final
examination
in
a
university
course.
Problem set Week
7
:
1.
Descri
be
the
general
processes
that
should
be
followed
in
managing
risks
throughout
a
project.
Be
sure
to
include
the
general
sequence
in
which
these
processes
are
carried
out.
2.
Prepare
a
sample
risk
register
for
a
project
to
put
humans
on
Mars
(four
or
five
r
isks).
3.
What
is
the
difference
between
qualitative
and
quantitative
risk
analysis?
Which
one
is
always
done?
Why
is
the
other
one
not
always
done
for
every
project?
Problem set Week
8
:
Question
1
Your
team
has
been
asked
to
test
and
document
enhancements
to
a
web
application
that
allows
buyers
to
purchase
custom
-
printed
canvas
shoes.
The
tasks
and
dependencies
are
as
follows:
·
Create
a
testing
plan
Once
the
testing
plan
is
ready,
your
team
can:
·
Test
the
user
interfaces
·
Test
the
database
·
Test
the
network
·
Write
the
documentation
first
draft
Problem set Week 6:
1. In addition to cost, what factors should be considered in selecting a building
contractor? What can go wrong if the lowest bid is selected and nothing else is
considered? (Answer in your own words, maximum 70 words.)
2. What is the difference between an RFP and an RFQ? Give two specific examples
where an RFQ could be used and two specific examples where it is more likely that
the organization will go with an RFP. (Use examples NOT from your textbook.)
3. Prepare a Pareto chart of the possible causes for a student to fail a final examination
in a university course.
Problem set Week 7:
1. Describe the general processes that should be followed in managing risks
throughout a project. Be sure to include the general sequence in which these processes
are carried out.
2. Prepare a sample risk register for a project to put humans on Mars (four or five
risks).
3. What is the difference between qualitative and quantitative risk analysis? Which
one is always done? Why is the other one not always done for every project?
Problem set Week 8:
Question 1
Your team has been asked to test and document enhancements to a web application
that allows buyers to purchase custom-printed canvas shoes. The tasks and
dependencies are as follows:
Create a testing plan
Once the testing plan is ready, your team can:
Test the user interfaces
Test the database
Test the network
Write the documentation first draft