3 discussions - 2 Project Sets
Problem Set # 10 - Project for Planning
Chapter 11: Resource Planning.
Earned-value analysis. A project budget calls for the following expenditures:
|
Task |
Date |
Budgeted Amount |
|
Build forms |
1-Apr |
$10,000 |
|
Pour foundation |
1-Apr |
$50,000 |
|
|
1-May |
$100,000 |
|
Frame walls |
1-May |
$30,000 |
|
|
1-Jun |
$30,000 |
|
Remaining tasks |
July 1 and beyond |
$500,000 |
Define each term in your own words, calculate these values for the above project, and show your work:
· Budgeted cost baseline (make a graph illustrating this one)
· Budget at completion (BAC)
· Planned value (PV) as of May 1
· Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
· SV as of May 1.
· Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
· Schedule performance index (SPI)
· Cost performance index (CPI)
· Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
· Estimate at completion (EAC)
Reference:
Watt, A. (2019). Project Management, 2nd Edition. BCcampus Open Education.
https://opentextbc.ca/projectmanagement/