Project Plan for Extension on the Gates House

2. Project Description

2.1 Project Scope

2.1.1 Scope Statement: Our contracting agency will add an addition room to your house be either building out or up. The goal is to add square footage to the building efficiently and correctly. These additions add style and extra room that the consumer has always wanted. The spare room will increase the value of the home. Project plans will be written and then documented for the consumer’s record. Foundation workers, drywall technicians and roofers will collaborate to ensure a solid addition. Licensed electricians will come manage the electrical components of the job, ensuring a safely wired environment as well as following building codes. Dimensions and cost vary from what the customer requests and the location of the project, but the average costs for the physical structure runs between $80 to $200 per square foot excluding labor. This includes adding supports, roof trusses and integrating them to the existing building. Masonry work and roofing will be observed in order to assimilate to the design of the home. This project will be completed when the structure is built, implemented for the desired purpose and the customer is satisfied with the results.

2.1.2 WBS and Index

1.0 Design

1.1 Order Materials

|

2.0 Foundation

|

2.0 Depth 2.1 Block 2.2 Rebar

2.0.1 specs 2.1.1 specs 2.2.1 specs

3.0 Frame and Subfloor

|

3.1 Frame 3.2 headers 3.3 Subfloor

3.1.1 Walls 3.2.1 cut to size 3.3.1 cut to size

3.4 Ceiling 3.2.2 place brackets 3.3.2 nail into studs

3.2.3 screw into place

4.0 Electrical

|

4.1 Wire 4.2 Light Fixtures 4.3 Outlets and outlet boxes

4.1.1 Gauge 4.2.1 Led Lights 4.3.1 wire

4.1.2 run wire 4.2.2 Wire up 4.3.2 install

4.1.3 merge into system 4.2.3 install

4.4 Switches

4.4.1 wire

4.4.2 install 4.5 Projector and Screen

4.5.1 wire projector

4.5.2 wire screen

4.5.3 install projector and screen

|

5.0 drywall

|

5.1 Sheets 5.2 Screws 5.3 Mud and tape

5.1.1 Specs 5.2.1 Specs 5.3.1 Tape seams together

5.1.2 cut to size 5.2.2 Screw into studs 5.3.2 Mud over tape

5.4 Insulation

5.4.1 install before drywall

6.0 flooring

|

6.1 Carpet

6.1.1 cut to size

6.1.2 roll into place

6.1.3 staple into place

7.0 brickwork and roof

7.1 Roof 7.2 Brickwork

7.1.1 Weather Barrier 7.2.1 mortar

7.1.2 Stapler into place 7.2.2 place next row

7.1.3 Shingles 7.2.3 repeat

7.1.4 Nail into place

2.2 Project Deliverables

2.2.1 Site

2.2.1.1 From behind the house a 10ftX10ft square will be prepared for the structure. Grass will be removed to avoid decomposable materials underneath foundation. The ground will be leveled across to assure a flat surface. Vapor barrier will be laid down prior to concrete pouring to avoid moisture from the ground causing impurities. Lumber will be used in the form of 2X4 boards to outline the square for concrete pouring. Concrete will be poured and leveled.

2.2.2 Building

2.2.2.1 After site is complete framework will begin by anchoring long 2X4s into the concrete to begin walls. The walls will measure to 7ft in height. Plywood will attach to the framed walls. Next the trusses for the roof will begin. Plywood will then be applied to the trusses. Once the structure is standing and codes set by the International Building Code are satisfied the project will proceed. All measurements and procedures will be documented and shared within the confines of the contract with the customer.

2.2.3 Electrical

2.2.3.1 Contractors with CE classifications will add wires to the existing electrical panel in the home. The wires will be ran to the addition in order to supply the room will lights, switches and electrical outlets.

2.2.4 Interior

2.2.4.1 Professional drywall installers will begin to insulate the walls. After the walls have been insulated the dry wall will be installed to complete the ceiling and walls for the addition. Next the painting process will begin. Carpenters will begin to build sub levels in the room in order to obtain the theater appeal that the customers have requested. Carpet will then be laid out and crown molding as well as base boards will complete the room.

2.2.5 Exterior

2.2.5.1 Masonries will match the existing brick design of the home to ensure an equal match. Roofers will lay down tar paper then proceed to install the matching shingles.

2.3 Constraints and Assumptions

.......................................................

2.4 Potential Risks and Categories

2.4.1 Technical

2.4.1.1 The possibility that there is a heavy raining that may stops the work for many days.

2.4.1.2 Possibility of tools not working properly

2.4.2 Project Management

2.4.2.1 The project manager get many tasks which prevent him from controlling ` the work.

2.4.3 Organizational

2.4.3.1 The staff get involved in more them one project which makes them not available on time.

2.4.4 External

2.4.4.1 Key team members get sick or gets in any other emergency situations that prevent them from continue working.

2.4.4.2 A strong wind came and cause the tree next to the room to fall down which will damage many parties of the room if it’s not finished.

2.4.4.2 The Materials and resources are not available on the assigned time for whatever reason.

2.5 Integrated Project Reviews

……………………………………….

2.6 Interdependence with other projects

……………………………………………

3. Key Resource Requirements

3.1 Stakeholder Listing

3.1.1 Dr. David Hatfield – Project Manager

3.1.2 Middle Tennessee State University – Sponsor

3.1.3 John Gates – Customer

3.1.4 Construction Management Department (MTSU) – Performing Organization

3.1.5 Jerod Goff – Team Member

3.1.6 Austin Larkins – Team Member

3.1.7 Zakaria Alyami – Team Member

3.1.8 Rimonda Aziz – Team Member

3.2 Team Structure

3.2.1 Organizational Roles/Responsibility

3.2.1.1 Dr. David Hatfield

3.2.1.1.1 Project Manager

3.2.1.2 Jerod Goff

3.2.1.2.1 Team Member

3.2.1.3 Austin Larkins

3.2.1.3.1 Team Member

3.2.1.4 Zakaria Alyami

3.2.1.4.1 Team Member

3.2.1.5 Rimonda Aziz

3.2.1.5.1 Team Member

3.3 Equipment and Facilities

3.3.1 Tools

Power Drill, bits

Paint Roller, brush, spreader, mixer

Air compressor, nail gun, staple gun

Hand tools

Drywall stilts, tape, mud, drywall saw

Portable Generator

Table saw

Level

Measuring tape

3.4 Materials/Component Parts

Wire 12-2 gauge, 3 roll

10 Outlets,

10 Outlet box,

2 Switches,

6 Light Fixtures,

1 Projector,

1 Projector screen,

Theater seating, 6 double seats

Wood board 2 in. x 12 in. x10ft.

Wood board, 2 in. x 4 in. x 10ft.

12 Plywood

14 Drywall, 625 in. x 4in. x 8 in.

Carpet, 70 sq. ft.

Paint, 6 gal for 3 coats

3 Molding, 12 ft.

Insulation, 6 rolls

3 Shingles, 33 sq. ft. packages

1 Gutters,

1 Weather sealant,

8000 Bricks,

Wood screws

3.5 Vendors

3.5.1 Lowes

3.5.2 Home Depot

3.6 Constraints and Assumptions

3.6.1 Constraints

3.6.1.1 Some tasks limited to trained professionals

3.6.1.2 Weather can cause delays in project

3.6.2 Assumptions

3.6.2.1 Materials can be locally found and bought if needed

3.6.2.2 No medical emergencies

4.0 Budged Cost

4.1 Non -Recurring

4.1.1 Labor

4.1.1.1 Electrician $400

4.1.1.2 Roofers $1368

4.1.1.3 Masons $4256

4.1.1.6 Drywall/Painters $288

4.1.2 Materials

Wood $911

Drywall $180

Shingles $90

Brick $1184

Paint $100

Insulation $180

Electrical $1544

Lights $300

Mortar $329

Theater seating $3,000

Miscellaneous $1000

4.2 Recurring

4.2.1 Project Manager $ 10,830

4.3 Total Cost $15,131

5.0 Project Schedule

5.1 Master Schedule

Task Duration (days) Start Finish

-------------------------------------------------------------------------------------

Foundation 12 5/26/18 6/08/18

Frame & subfloor 14 6/08/18 6/22/18

Room closed in 4 6/22/18 6/26/18

Electrical 2 6/26/18 6/28/18

Drywall 1 6/28/18 6/29/18

Weather Sealant 0.5 6/29/18 6/29/18

Flooring 1 6/29/18 6/30/18

Roof 4 6/29/18 7/02/18

Brickwork 14 6/29/18 7/12/18

Paint 1 6/29/18 6/30/18

Install Seating 0.5 6/30/18 6/30/18

Install Projector 0.2 6/30/18 6/30/18

5.2 Major Milestones

5.3 Constraints and Assumptions

5.3.1 Constraints

5.3.2 Assumptions

6.0 Supporting Plans

6.1 Risk Management Plan

6.1.1 Risk identification

6.1.2 Risk management

6.1.3 Risk Budget

6.1.4 Risk Analysis

6.2 Cost Management Plan

6.3 Test Plan

6.4 Vendor Management Plan

6.5 Quality Plan

-----------------------------------------------------------------------------------------------------------------

Project Charter

Project Name:

Extension on the

Gates house

Associated Projects:

CIM(Concrete Industry Management)

Sponsor:

MTSU

Executive Management

Authorization:

Dr. Walter Boles

Client Dept:

Construction Management

Client Contact:

Dr. Walter Boles

Project Lead:

Dr. David Hatfield

Dept:

Construction Management

Date Assigned:

05/26/18

Project Lead:

Dept:

Date Assigned:

Priority:

For Organization

High

X

Medium

Low

For Business Area

High

X

Medium

Low

Business Case:

(“WHY” should this project be done? Identify the specific current and future business needs that this project meets. State how the proposed project aligns with the strategic objectives of the business area and organization.)

The Gates are looking for an extension on their home that will provide them with extra space and also an area to provide a movie theater experience for themselves and or guests. This project will provide the family to be able to provide entertainment for up to 12 people at any point in time. This addition will approximately cost around $16,000 to complete in approximately 4-6 weeks to finish the addition.

Scope /Project Deliverables:

(“WHAT” will the project deliver? Scope answers the question “What will be done on this project, and what are the products or services that will be provided? Deliverable – What are the measurable products, components, and services produced by the project? How will you know when you are “DONE”)

Our contracting agency will add an addition room to your house be either building out or up. The goal is to add square footage to the building efficiently and correctly. These additions add style and extra room that the consumer has always wanted. The spare room will increase the value of the home. Project plans will be written and then documented for the consumer’s record. Foundation workers, drywall technicians and roofers will collaborate to ensure a solid addition. Licensed electricians will come manage the electrical components of the job, ensuring a safely wired environment as well as following building codes. Dimensions and cost vary from what the customer requests and the location of the project, but the average costs for the physical structure runs between $80 to $200 per square foot. This includes adding supports, roof trusses and integrating them to the existing building. Masonry work and roofing will be observed in order to assimilate to the design of the home. This project will be completed when the structure is built, implemented for the desired purpose and the customer is satisfied with the results.

Success Criteria:

(“HOW” will the output of the project be measured from an operational perspective? What tangible business value will result from doing this project? What must occur in the business area after delivery for us to say the project was a success??)

This extension to the home will add aesthetic appeal to the existing structure. It is deemed sufficient when homeowners are able to add square footage to the building as the end result will increase the value of the property. Lastly the guests of the property owners will be pleased in a room that offers entertainment.

Life Cycle Cost Ramifications:

(What are the long term savings and costs of the project to the business area and organization?)

Financially this will result in a high cost up front but a cheaper alternative to purchasing a new home. No other method adds more space to a home than an addition. Investment value can yield an increase in the value of the home that could potentially recover the costs of the addition based on the buyer’s market for houses.

Impacted Organizational Groups:

(What business areas will be impacted by the project?)

Homeowners will experience an emotional enjoyment factor. The same will apply to 3rd party visitors as they will feel this way as well.

Options Considered (Technical, Business Process, etc.)

(What other options or solutions were considered to solve the business problem or opportunity?)

Building on top of the existing structure was considered but ruled out due to added costs of cranes and lack of foundation strength. This approach was far less convenient than building beside the structure.

Project Assumptions:

(What assumptions or factors could interfere with the project work or compromise the contribution the project can make to the business area or organization?)

If the family get involve in other projects, it may not be able to provide the money needed on time. If the government decide to stop the work because the design does not match the design of the entire area. If the Environmental Beautification Organization likes the design and decided to support the project with money.

Constraints:

(What factors could negatively affect the performance of the project? Include factors that affect when an activity can be scheduled, or when a resource can be assigned, etc. )

The weather is not appropriate for the workers to start the building process (raining, snowing, or storms).

The Materials and resources are not available on the assigned time.

Key Project Issues:

(What are the barriers to project success?)

Limited resources that needed to build the room. The possibility that there is a heavy raining that may stops the work for many days. The possibility of increase the prices of the materials needed which will cause a budget imbalance.

Risk Events:

(What events or conditions that, if it occurs, will impact the project objectives, deliverables, schedule, budget, etc.?)

The employees get sick or gets in any other emergency situations that prevent them from continue working. There is a tree right next to the room, if a strong wind came it may damage many parts of the home, especially if it cause a tree to fall.

Next Steps or Actions to Be Taken:

(What are the major steps or actions to be taken to proceed with this project?)

Get to know the project lifecycle.

List the roles and responsibilities matrices.

Find the ways to improve or make the project successful.

Find the schedule of materials to be included in the surveyors Report on tenders.

Look for the certificate of Undertaking.

Indicate the dates for delivery of financial motions to Treasury.

Schedule of documents to be submitted by departments when requesting Treasury approval.

Find the post contract cost control template.

Look for the means of evaluating the project

Look for the certificate of readiness.

Specimen Advertisement for list of the selected tenders

Form of tender.

RESPONSIBILITIES

Client Responsibilities

Performing Organization Responsibilities

Vendor Responsibilities

Framework contractors

The performing organization responsibilities the contractors are involved in identification, planning and development of the project in terms of client requirements, scope, in- service date and budget and also the preparation and submission of progress reports to the appropriate authority.

The vendor responsibility of framework contractors is determination of responsible or non- responsible vendor and to process upon finding of negative information.

Roofers

Performing organization responsibilities include, supplying or holding materials or tools and cleaning work area and equipment.

Vendor responsibility include, they affiliate.

Dry wall and paint

- performing organization responsibility include, painting by performing dry wall installation and repair services.

Vendor responsibility includes the determination and providing samples of vendor responsibility questionnaires and responsibility issues.

Electricians

- Performing organization responsibility includes routine electrical maintenance and repairs.

Vendor responsibility include to monitor vendor compliance with elevator contracts to ensure safe operation and maintain records and files on work performed.

Masonries

Performing organization responsibilities include building, altering and repairing brick, stone, tile or ceramic structures.

Vendor responsibility includes determination and providing samples of vendor responsibility questionnaires and responsibility issues.

RESOURCES REQUIRED

Enter as many lines as necessary to identify the number of and type of resources required for this project

Resource Type

# of Resources Needed

Wire 12-2 gauge, outlets, outlet box, switches, fixtures

3 rolls wire, 10 outlets,10 outlet boxes, 6 light fixtures, 2 switches.

Projector, projector screen

1 each for projector in theater room

Theater seating

6 double seats

2x12 wood board, 2x4x10 wood board, plywood.

16 2x12s, 24 2x4x10, 12 plywood for frame

drywall

14 .625x4x8 pieces to cover inside of the wall

Carpet

70 sq ft to cover floor

Paint

6 gal for 3 coats

Molding

3 12 ft pieces

insulation

6 rolls to insulate inside of room

Shingles, gutters, weather sealant, bricks

3 33 sq ft packages, 1 gutter, 1 weather sealent, 8000 bricks for roof and outside of room

Mason

3 20% of time

Electrician

1 10% of time

Drywall and painters

4 30% of time

Roofers

3 20 % of time

Manager and assistant manager

2 100% of time

Designers

2 10% of time

TRAINING PLANNED

Enter as many lines as necessary to identify all groups of people to be trained, the type of training they require and the number of people to be trained

Category Of People To Train

Type of Training

# Of People

Management team members.

-Management team requires training on ways to plan and manage the project services example building and communication channel in the project.

1 Manager and 1 assistant manager.

Vendors.

-Vendors require training on how to record files of the work done and how to manage the operation of the project.

6

Masonry.

-Masonry is trained on how to build using building materials such as bricks and tiles.

3

Electrician.

-Electrician is trained on how to repair damaged electrical materials and how to do it.

1

Drywall and paint.

-Dry wall and painters are trained on how to paint the walls efficiently.

4

Roofers.

-Roofers are trained on how to put roofing to the house.

3

MAJOR MILESTONES & DATES

Enter as many lines as necessary

Milestone

Milestone Date

design

5/25/18

foundation

6/8/18

Frame & subfloor

6/22/18

Room closed in from elements

6/26/18

electrical

6/28/18

drywall

6/29/18

flooring

6/30/18

Weather sealant, roofing, and brick work

6/30/18

Seating going in

7/1/18

Comments:

The project of extension on the gates house requires major steps that must be undertaken by skilled people for it to be successful.

Terminology Definitions:

Authorization:

This refers to a document giving official permission.

1