Project Control

profilenagreene4
PRJ695_GreeneWK5Assignment.docx

2

Lake House Project Part 5

Herbert Greene

Week 5 Assignment

Dr. Cuffe

August 23, 2021

Part 1

Resource Costing

Cost estimates include the cost and assumptions underlying each cost. The assumptions cover all the cost inclusions and exclusions which are important for the project stakeholders to interpret project costs and to understand how and where actual cost might differ from approximated costs. In this section we are concentrating on labor cost. This is the cost of human effort expended towards project objectives. The method to use for cost estimate is the preliminary estimates. This will use detailed scope information to incorporate unit cost. The work breakdown has been prepared together with the project Gantt chart. This is important in the cost estimation part.

The table below shows the human resource that will be used in the project that include the person, position title and pay rate. The workers will be required to work for 40 hours a week from Monday to Friday where there will be no overtime awarded.

Person Name

Position

Pay rate per hour

James Robert

Project Manager (PM)

$55

Grace Addison

General Contractor (GC)

$100

Simon Kant

Site Excavation contractor (SEC)

$ 65

Mercy Willow

Electric contractor (EC)

$ 65

Boniface Hamid

Plumbing contractor (PC)

$ 65

Peter Jonathan

Concrete contractor (CC)

$ 65

Wilson Alan

Framing contractor (FC)

$ 65

Stanley Kay

Roofing contractor (RC)

$ 75

Jeremiah Buster

Masonry contractor (MC)

$ 50

Hannah Aubrey

HVAC contractor (HC)

$ 75

Keats John

Insulation contractor (IC)

$ 65

Charles Keillor

Painting contractor (PAC)

$ 50

Kelly Walt

Finish carpentry contractor (FCC)

$ 50

Alex Kennan

Flooring contractor (FLC)

$ 50

Kepa Robert

Fencing contractor (FEC)

$ 50

Kesey John

Landscape contractor (LC)

$ 65

Table 1showing human resource data sheet in the project

The resource loading list consists of the task, the resource assigned and the percent of time allocated for each task.

Task

Planning and estimates development

20% PM

35% GC

Permits acquiring

65% PM

Clear and grub lot

85% SEC

Install temporary power

85% EC

5% PC

Install underground utilities

35% EC

20% PC

Excavation for foundation

75% SEC

Erect basement walls

55% CC

Backfill foundation

75% SEC

Framing work

80% FC

Exterior finishing

35% MC

20% FC

Utility installation

20% PC

10% EC

5% HC

Interior finishing

10% IC

35% PAC

20% FCC

15% PC

20% EC

5% HC

Flooring, carpeting and tiles

45% FLC

Landscaping and ground works

5% CC

10% FEC

20% LC

Table 2showing resource loading list

Formal letter to the Supervisor

Herbert Greene

Antietam Dr

Locust Grove, VA

(Dr. Cuffee), Designation

Dear Sir

I hereby write to inform on the project resource allocation and costing for the project. The project resources will consist construction materials, human labor and construction equipment. Application timeline for the material will go hand-in-hand as the Gantt chart where the activities will be scheduled and time allocation for each resource stated. The resource allocation has been done using preliminary estimates where each activity has been considered separately. The Gantt chart shows all the project activities where from previous experience and the house size the architect was able to provide an estimate of the required resources. This have been compared to the resources used in similar projects conducted in the area to increase accuracy.

The ground condition from study and observation has good stable foundation soil which will favor the construction and reduce foundation in terms of cost and time. The area has good infrastructure in terms of roads where the required materials and equipment will access the site with ease. The site construction has also come at a favorable time with conducive weather with no rains except for the high temperature which will affect workers productivity. The foundation will require more of excavation contractor for excavating and backfilling where the concrete contractor will come in to erect the walls. The plumbing contractor will also lay the foundation plumbing work.

The ground floor will follow together with the building columns as per the design. This part requires many temporary laborers under the masonry and concrete contractors as it is labor intensive. The general contractor’s work here is supervision and inspection. The laborers for this section will be obtained from the area who will be hired and paid weekly. To ensure smooth flow of work the workers will be required to guarantee availability for the whole week and in case of absence to report one day earlier. The roofing, exterior and interior finish will then be done as per the work schedule. This will involve the roofing contractor for the roofing work while for the finishes, the painting, HVAC, carpentry, electrical and plumbing contractor will be involved. The general contractor will ensure quality of work is maintained and all the resources are used correctly.

The resource cost list and the resource loading list have been provided.

Yours sincerely

(Student Name), Project Manager