ID Task Name Duration Start Finish Predecessors
1 Project Timeline Template 592 days Mon 1/20/14 Tue 4/26/16
2 Kick-off meeting with ACC 1 day Wed 1/8/14 Wed 1/8/14
3 Scope Development 19 days Thu 1/9/14 Tue 2/4/14
4 Investigation 16 days Thu 1/9/14 Thu 1/30/14 2
5 Asbestos 15 days Fri 1/10/14 Thu 1/30/14 4FS-15 days
6 Utilities 10 days Fri 1/17/14 Thu 1/30/14 4FS-10 days
7 Meeting with Users 0 days Thu 1/30/14 Thu 1/30/14 4,5,6
8 Budget Prep 7 days Fri 1/31/14 Mon 2/10/14 7
9 CPA Prep/Approval 10 days Tue 2/11/14 Mon 2/24/14 8
10 CPA Approved 0 days Mon 2/24/14 Mon 2/24/14 9
11
12 Procurement 46 days Mon 1/20/14 Mon 3/24/14
13 Contracts by ACC 15 days Mon 1/20/14 Fri 2/7/14 2
14 DP 15 days Mon 1/20/14 Fri 2/7/14 2
15 General Contractor 15 days Mon 1/20/14 Fri 2/7/14 2
16 Surveyor 15 days Mon 1/20/14 Fri 2/7/14 2
17 Geotech 15 days Mon 1/20/14 Fri 2/7/14 2
18 Hazmat Testing 15 days Mon 1/20/14 Fri 2/7/14 2
19 LEED Consultant 15 days Mon 1/20/14 Fri 2/7/14 2
20 Contracts by NAU 20 days Tue 2/25/14 Mon 3/24/14 10
21 3rd Party Estimate 20 days Tue 2/25/14 Mon 3/24/14 10
22 Commissioning Agent 20 days Tue 2/25/14 Mon 3/24/14 10
23
24 Design 141 days Fri 1/31/14 Fri 8/15/14
25 Conceptual Design 21 days Fri 1/31/14 Fri 2/28/14
26 Conceptual 10 days Fri 1/31/14 Thu 2/13/14 7
27 Site Survey 10 days Fri 1/31/14 Thu 2/13/14 7
28 Site Geotech Report 10 days Fri 1/31/14 Thu 2/13/14 7
29 Conceptual estimate 5 days Fri 2/14/14 Thu 2/20/14 26,27,28
30 Conceptual Design Package Delivered to NAU 0 days Fri 2/21/14 Fri 2/21/14 29FS+1 day
31 Conceptual Plan Review by NAU 5 days Mon 2/24/14 Fri 2/28/14 30
32 Schematic Design Development 35 days Mon 3/3/14 Fri 4/18/14
33 Schematic Design Development 15 days Mon 3/3/14 Fri 3/21/14 31
34 SD Estimate 10 days Mon 3/24/14 Fri 4/4/14 33
35 SD Documents Package Delivered to NAU 0 days Fri 4/4/14 Fri 4/4/14 34
36 Schematic Plan Review by NAU 10 days Mon 4/7/14 Fri 4/18/14 35
37 Design development 35 days Mon 4/7/14 Fri 5/23/14
38 Design Documents Development 15 days Mon 4/7/14 Fri 4/25/14 36FS-10 days
39 DD Estimate 10 days Mon 4/28/14 Fri 5/9/14 38
40 DD Package Delivered to NAU 0 days Fri 5/9/14 Fri 5/9/14 39
41 DD Plan Review by NAU 10 days Mon 5/12/14 Fri 5/23/14 40
42 ABOR Project Approval 19 days Mon 5/12/14 Thu 6/5/14
43 ABOR PA (Project Approval) doc' preparation 5 days Mon 5/12/14 Fri 5/16/14 40
44 Board materials due 5/16/2014 0 days Fri 5/16/14 Fri 5/16/14 43
45 ABOR Meeting on June 5-6, 2014 0 days Thu 6/5/14 Thu 6/5/14 44FS+14 days,41
46 Construction Documents 65 days Mon 5/19/14 Fri 8/15/14
47 100% CD set for Foundation & Site Work scope 20 days Mon 5/19/14 Fri 6/13/14 41FS-5 days
48 100% CD set for Foundation & Site Work scope Estimate
10 days Mon 6/16/14 Fri 6/27/14 47
49 100% CD set for Foundation & Site Work Package delivered to NAU
0 days Fri 6/27/14 Fri 6/27/14 48
50 50% CD Development 20 days Mon 5/26/14 Fri 6/20/14 41
51 50% CD Estimate 10 days Mon 6/23/14 Fri 7/4/14 50
1/30
2/24
NAU/DP
3rd Party/DP/CMAR
2/21
4/4
5/9
5/16
6/5
6/27
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Students & Academic Services building
Page 1 of 2 Prepared on 1/26/2014
Project: Preliminary schedule_09.600. Date: Tue 1/30/18
ID Task Name Duration Start Finish Predecessors
52 50% CD Package Delivered 0 days Fri 7/4/14 Fri 7/4/14 51
53 100% CD Development 30 days Mon 6/23/14 Fri 8/1/14 50
54 100% CD Estimate 10 days Mon 8/4/14 Fri 8/15/14 53
55 100% CD Package Delivered 0 days Fri 8/15/14 Fri 8/15/14 54
56
57 Developer Construction Contract 20 days Mon 7/7/14 Fri 8/1/14
58 Developer Contract based on 100% CD set for Foundation & Site Work and 50% CD set
5 days Mon 7/7/14 Fri 7/11/14 49,52
59 Contract Review/Negotiation 10 days Mon 7/14/14 Fri 7/25/14 58
60 Contract Finalization 5 days Mon 7/28/14 Fri 8/1/14 59,45
61 Contract Signed 0 days Fri 8/1/14 Fri 8/1/14 60
62
63 Misc. Contracts for Construction (by NAU?) 0 days Fri 8/1/14 Fri 8/1/14
64 Material Testing 0 days Fri 8/1/14 Fri 8/1/14 61
65 Special Inspection 0 days Fri 8/1/14 Fri 8/1/14 61
66
67 Permits 230 days Mon 6/30/14 Fri 5/15/15
68 ADEQ/EPA Notice of Intent 10 days Mon 7/28/14 Fri 8/8/14 59
69 100% CD Foundation & Site Work Plan Review by NAU
20 days Mon 6/30/14 Fri 7/25/14 49
70 Foundation & Site Work only permit 0 days Fri 7/25/14 Fri 7/25/14 69
71 100% CD Plan review by NAU 20 days Mon 8/18/14 Fri 9/12/14 55
72 Construction Permit 0 days Fri 9/12/14 Fri 9/12/14 71
73 NAU Fire Marshal Fire Sprinkler & Fire Alarm shop drgs review
30 days Mon 10/27/14 Fri 12/5/14 61,82
74 Fire Sprinkler & Fire Alarm permits issued 0 days Fri 12/5/14 Fri 12/5/14 73
75 Substantial Completion 0 days Fri 5/1/15 Fri 5/1/15 91
76 Certificate of Occupancy 0 days Fri 5/1/15 Fri 5/1/15 91
77 ADEQ/EPA Notice of Termination 0 days Fri 5/15/15 Fri 5/15/15 91FS+10 days
78
79 Construction 220 days Fri 8/8/14 Fri 6/12/15
80 Notice to Proceed 0 days Fri 8/8/14 Fri 8/8/14 61,68,70
81 Preconstruction Meeting 0 days Fri 8/8/14 Fri 8/8/14 80
82 Fire Sprinkler & Fire Alarm Shop Drawings 30 days Mon 9/15/14 Fri 10/24/14 61,72
83 Sitework 15 days Mon 8/11/14 Fri 8/29/14 81,64,65
84 Foundation 30 days Mon 9/1/14 Fri 10/10/14 83
85 Structure 40 days Mon 10/13/14 Fri 12/5/14 84,72
86 Building Enclosed 40 days Mon 12/8/14 Fri 1/30/15 85
87 Interior Construction 60 days Mon 1/12/15 Fri 4/3/15 86FS-15 days,74
88 Commissioning 15 days Mon 4/6/15 Fri 4/24/15 87
89 Punch List 15 days Mon 4/6/15 Fri 4/24/15 87
90 NAU Final Inspections 5 days Mon 4/27/15 Fri 5/1/15 89,88
91 Substantial Completion 0 days Fri 5/1/15 Fri 5/1/15 86,88,90
92 LEED Building Flushout 20 days Mon 5/4/15 Fri 5/29/15 91
93 FFE (Furniture & Computers) 20 days Mon 5/4/15 Fri 5/29/15 91
94 End User Move In Date 0 days Mon 6/1/15 Mon 6/1/15 93FS+1 day
95 Staff Training 5 days Tue 6/2/15 Mon 6/8/15 94
96 Building ready for Students 0 days Mon 6/8/15 Mon 6/8/15 95
97
98 Final Completion 0 days Fri 6/12/15 Fri 6/12/15 91FS+30 days
7/4
8/15
8/1
8/1
8/1
8/1
7/25
9/12
12/5
5/1
5/1
5/15
8/8
8/8
5/1
6/1
6/8
6/12
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Qtr 1, 2014 Qtr 2, 2014 Qtr 3, 2014 Qtr 4, 2014 Qtr 1, 2015 Qtr 2, 2015 Qtr 3, 2015
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Students & Academic Services building
Page 2 of 2 Prepared on 1/26/2014
Project: Preliminary schedule_09.600. Date: Tue 1/30/18