Test(120 questions) CIS-525

profileimangaliyevaa
PreAssesment.docx

Question 1

Value stream analysis can be best described as a ________.

a

product quality process

b

project estimating process

c

risk management process

d

continuous improvement process

Question 2

A member of an Agile team has activated an alarm to tell her colleagues that a problem has been detected. The team then gathers at the site of the problem to quickly correct them problem and allow work to continue. This problem-resolution activity is known as ________.

a

a pre-mortem

b

fishbone diagram analysis

c

kaizen

d

variance analysis

Question 3

Ideal time can be defined as ________.

a

a prediction of work duration that does not compensate for interruptions that may occur

b

a prediction of work duration that takes into account interruptions that may occur

c

the amount of time that the team agrees it should take to complete an average story point given the team's velocity

d

the budgeted amount of time that the team adjusts to reflect updates made to the story board

Question 4

Diamond Software is conducting an Agile project and wants to use a metric to determine how many unfinished tasks it has at the end of its iterations. Which metric would be best to track?

a

cycle time

b

work in progress

c

defect rate

d

velocity

Question 5

When does an Agile project leader not need to hold a final project retrospective to close out the project?

a

when there has been a retrospective following each iteration

b

when team members have urgent priorities and all project issues have been previously addressed

c

if senior management prefers to have documented feedback instead

d

None of the above are reasons to skip the project retrospective.

Question 6

How does the Agile Declaration of Interdependence suggest that practitioners can boost performance?

a

through the acquisition of skills by individual team members

b

through an increased return on investment

c

through the accountability and shared responsibility of the entire group

d

through the mentoring of inexperienced team members by those with more experience

Question 7

Developing estimates based on effort hours can be very subjective–an experienced team member may be able to complete work much faster than an inexperienced worker performing the same task. How can an Agile team establish a common measure to estimate work?

a

The team could develop its own story point scale to measure the relative size of user stories.

b

The team could use a story point scale based on industry standards to estimate the relative difficulty of the user stories.

c

The team could apply the story point scale from another team to its work.

d

The team could assign only experienced workers to tasks.

Question 8

Customer-valued prioritization places greater emphasis on customer value and less emphasis on __________.

a

cost, compliance, or market conditions

b

expenses and product users

c

cost and end users

d

marketing, promotion, and end users

Question 9

Marvin has just sent an email to a teammate, to ask for clarification on a project issue. This is a form of ________.

a

asynchronous one-way communication

b

coincident one-way communication

c

asynchronous two-way communication

d

coincident two-way communication

Question 10

Which of the following statements is true?

a

Because Agile teams implement working products in much shorter increments, they can apply verification and validation techniques on a less-frequent basis.

b

Verification is a quality-testing process that relies on external stakeholders to test products.

c

Validation enlists end users and customers to test the product to see that it works as they envision it to.

d

Validation is a quality-testing process that relies on the project team to test products.

Question 11

Brenna is reviewing her team's burn charts and cumulative flow diagrams to uncover any differences in what they expected to achieve and what they actually achieved. What is Brenna doing?

a

creating a timebox

b

performing variance analysis

c

playing Planning Poker

d

completing a MoSCoW analysis

Question 12

Why is it that an Agile team leader can monitor project work with a "light touch" rather than with a "heavy hand"?

a

because the members of an Agile team understand their roles and how iterations will progress

b

because the role of an Agile team leader is not to direct team members

c

because short iterations don't allow an Agile team leader enough time to monitor a project

d

because project work should not be micro-monitored since the processes used differ from one iteration to the next

Question 13

Which of the following is one of the six Agile management principles?

a

Unleash creativity and innovation by recognizing that team members are the ultimate source of value, creating an environment where they can make a difference.

b

Improve effectiveness and reliability through documented strategies, processes, and practices.

c

Increase return on investment by making continuous flow of value the focus.

d

Deliver reliable results by engaging customers only when necessary.

Question 14

Which of the following statements regarding interpersonal skills is true?

a

Doing Agile requires understanding Agile practices; being Agile involves implementing Agile practices.

b

In adaptive leadership, the leader acts as a facilitator to the team, rather than as a manager or director of the team.

c

Empathy is the ability to work together to reach a common goal.

d

On highly collaborative Agile teams, the aim of negotiation should be ensure that team members voice their opinion but concede to the party with the most valid argument.

Question 15

Scrum is one of the most popular and widely used Agile methodologies. How does the Scrum approach differ from many other forms of Agile?

a

Scrum projects contain guidelines to help reduce confusion and distraction that could derail progress.

b

Scrum projects employ cycles of frequent testing and feedback.

c

Scrum projects establish customer requirement up front and then monitor and control the project until completion.

d

Scrum projects do not use sprints in the product development cycle, in favor of less rigorous framework.

Question 16

In which type of brainstorming do all members participate sequentially until everyone has exhausted their ideas?

a

popcorn

b

freewheeling

c

card deck

d

round robin

Question 17

A user story that was selected but not completed by the end of an iteration is ________.

a

a defect rate

b

a spike

c

an escaped defect

d

a corrective action

Question 18

What may happen if an Agile team is distributed, rather than being co-located?

a

The team must accept that product cost and time-to-market will be greater.

b

Success will require more effort and focus on better communication and information distribution techniques.

c

Agile will not be the best approach for accomplishing the project.

d

The product owner must develop additional management processes.

Question 19

An Agile team wants to estimate the amount of effort and complexity of its user stories but doesn't want a complicated process that assigns numerical values to the stories. What tool should they use?

a

Planning Poker

b

the Five Whys

c

t-shirt sizing

d

internal rate of return

Question 20

Kyra and her team are following the Agile development cycle and have just created a product vision and product backlog. What is their next step?

a

execute the work

b

create timeboxes

c

perform a daily standup

d

plan an iteration

Question 21

How does the process of progressive elaboration work in an Agile project?

a

Progressive elaboration provides detailed plans of story boards that lead to specific insight as to how iterations should be planned.

b

Progressive elaboration organizes a project at a high-level and lets the details of the project evolve over time.

c

Progressive elaboration communicates ideas, verifies design assumptions, and validates project concepts, which minimizes uncertainty by allowing users to "see" what the product will do.

d

Progressive elaboration adds requirements to the product backlog as the project nears the release date to prepare for subsequent releases.

Question 22

Agile uses incremental and iterative development cycles to create new products or to modify existing products. Which of the following is a benefit of this approach?

a

It creates complete, innovative, and reliable products that can be released to the market sooner.

b

It ensures that the product meets the team's needs.

c

It limits new ideas from stakeholders to ensure product consistency.

d

It helps establish project requirements up front.

Question 23

Which of the following statements is false?

a

Scrum teams should include no fewer than five members and no more than nine members.

b

Daily scrums provide status updates to team members.

c

The Scrum process begins with a product vision and detailed customers requirements.

d

Sprint planning meetings are open forums in which any interested party can participate.

Question 24

Which of the following would be least helpful in recognizing project trends and variation?

a

story maps

b

earned value management

c

burn charts

d

cumulative flow diagrams

Question 25

Requirements in a product backlog may be incorrect or misleading due to several common causes. Which of the following is not a common cause of an inaccurate product backlog?

a

The product owner may be overworked.

b

The organization may have too many ways of collecting requirements.

c

The requirements may be incorrectly prioritized.

d

The requirement descriptions may be too vague or too descriptive.

Question 26

Piotr wants to use rolling wave planning on an upcoming Scrum project but his superior has suggested that he use progressive elaboration. What should Piotr do?

a

Insist that rolling wave planning would be a better fit for a Scrum project.

b

Agree to use progressive elaboration but secretly use rolling wave planning instead.

c

Agree with his superior as rolling wave planning is a form of progressive elaboration.

d

Ask his superior to consider rolling wave planning but abide by whatever decision his superior insists on.

Question 27

An iteration can be of whatever length a team designs it to be but is generally ________.

a

one month in length

b

one to four weeks in length

c

four to eight weeks in length

d

five to ten days in length

Question 28

Agile methods primarily approach accomplishing work through ________.

a

processes

b

people

c

plans

d

technology

Question 29

When an Agile team continually combines completed work into the customer solution, it is practicing _________.

a

test-driven development

b

continuous integration

c

frequent verification

d

six sigma

Question 30

Large displays of critical team information that are continuously updated and located where teams can see them constantly are called _________.

a

information sinks

b

information radiators

c

information boards

d

common rooms

Question 31

The document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply project resources to project activities is the _________.

a

product roadmap

b

sponsorship document

c

project charter

d

product budget

Question 32

Why do teams hold daily stand-up meetings?

a

to specifically solve team member problems

b

to encourage each team member to provide an accurate in-depth progress report

c

to limit the need for visual displays or story boards

d

to make sure communication is among the team, not to the product owner

Question 33

_________ is a facilitation technique that Agile leaders may use to improve interaction among practitioners.

a

Emotional intelligence

b

The planning game

c

Refactoring

d

Brainwriting

Question 34

The bottom of a value stream map looks like this:

The graphic above shows a value stream map with process steps taking 7 days, 2 days, 8 days, and 5 days, totaling 22 days, and waiting times of 7 days, 7 days, 7 days, and 7 days, totaling 28 days.

How much of the work in the process is value-added?

a

22 days

b

28 days

c

6 days

d

50 days

Question 35

If Lee wants to be a good active listener, which of the following should he avoid doing?

a

taking notes to ensure he has heard correctly

b

listening without thinking about a response

c

maintaining eye contact

d

asking clarifying questions

Question 36

What is an architectural spike?

a

a dramatic increase or decrease on a burndown chart

b

a graphic representation of the product backlog that shows interdependencies of risks

c

a section of the project charter that lists potential problems that could occur

d

an experiment that looks for potential risks or issues in the structural, foundational, or technical aspects of a project

Question 37

In addition to strong technical skills, Agile team members must possess robust interpersonal skills such as the ability to resolve conflicts. Which of the following statements about conflict resolution is false?

a

A collaborative environment and good negotiating skills can eliminate the potential for conflict between stakeholders.

b

Conflicts will inevitably arise whenever individuals work as closely together as Agile practitioners do.

c

Agile teams must create an environment where conflicts can be identified and resolved quickly.

d

Conflict resolution is an interpersonal skill.

Question 38

What is value-based prioritization?

a

the ordering of the stories in a product backlog based on the value that they bring to the project

b

the ordering of iterations that ensures project phases are executed in order of importance

c

the arrangement of Agile project requirements to satisfy the product owner

d

a method for developing useful user stories

Question 39

As her team is clarifying its definition of "done" in an initial meeting, Penelope realizes that the definition seems incomplete because it doesn't specify whether "done" means that the product is ready to ship–the definition ends by stating that the product is "ready to move on to the next phase of its cycle." Penelope realizes that this ambiguity could be used as an excuse at a later date if the team fails to meet an organizational deadline. When asked if she had anything to add to the definition, Penelope replies by saying that the definition "did a good job clarifying the terms it used." By hiding behind this half-truth, Penelope is failing to abide by elements of which of the following documents?

a

PMI®'s Code of Ethics and Professional Conduct

b

the project charter

c

The Agile Manifesto

d

the project release plan

Question 40

Actions undertaken to ensure that all relevant specifications, regulations, policies, or laws are followed and satisfied are referred to as _________.

a

customer-valued prioritization

b

financial regulation

c

compliance

d

legal prioritization

Question 41

For Agile teams to build trust, team members should do which of the following?

a

Team members should select tasks from the tasks list that will be most easy and enjoyable for them to complete.

b

Team members should try to resolve conflicts themselves before engaging an Agile team leader.

c

Team members with experience handling difficult tasks should assume responsibility for all of these tasks to help the team complete iterations on time.

d

Team members that are effective at handling long or difficult tasks should be assigned to handle these types of issues.

Question 42

Which of the following statements regarding risk management is false?

a

Teams may choose to use a technique called fail late in which they get highly risky stories out of the way first so that any problems that might happen will occur late in the process when the team has time to fix them.

b

To prioritize user stories based on risk, a team may develop a risk score for each iteration.

c

Calculating risk scores is a highly subjective process that should yield results that provide "close-enough" approximations for prioritization.

d

Managing risk is a core project management process.

Question 43

Mark is a member of a newly formed Agile team and is having trouble understanding and implementing Agile principles. He is also not clear about his role on the team. Who would be the best person to help Mark?

a

an Agile coach

b

the product sponsor

c

the team leader

d

his department manager

Question 44

On an Agile project, what does "done" mean?

a

The team can begin work on the next product increment.

b

The increment is ready for implementation.

c

The product is ready for customer use.

d

whatever team members and stakeholders collectively decide

Question 45

According to the Agile Manifesto, Agile does not value ________.

a

working products over comprehensive documentation

b

individuals and interactions over processes and tools

c

customer collaboration over contract negotiation

d

following a plan over responding to change

Question 46

Which of the following statements is false?

a

Agile metrics should be simple, easy to collect, and easy to analyze.

b

Every metric should have a target to show what success looks like.

c

A team should establish a target before they begin collecting any data.

d

Metrics should lead to obvious conclusions and drive appropriate behavior.

Question 47

John is a senior manager who occasionally drops in on Agile team meetings. During meetings, he suggests ways to improve the product. Recently he has gained support for a number of his additions. What risk does the Agile team run if it informally adopts too many of John's changes?

a

The scope creep could have a negative effect on other project parameters.

b

John will override the role of the product owner, disrupting authority and communication.

c

The customer will not like the final product when it is released.

d

Daily stand-ups will not be effective forums of communication.

Question 48

A visual mock-up of a product that developers use to verify design concepts and test functionality with users is called a __________.

a

story map

b

wireframe

c

model

d

persona

Question 49

Following completion of an iteration, an Agile team holds an informal meeting with stakeholders to demonstrate the products completed during the iteration. This meeting is referred to as ___________.

a

a daily standup

b

an iteration retrospective

c

an iteration review

d

a wrap-up

Question 50

Ingrid has begun planning an upcoming project. She is collecting customer requirements and developing a document that the team has to follow to sequentially complete the project. She has several monitoring processes planned to help her control the processes and correct any missteps or deviations that occur. What Agile methodology is she employing?

a

Ingrid is using Scrum.

b

Ingrid is using Lean Software Development.

c

Ingrid is using a combination of XP and Scrum.

d

Ingrid is not employing an Agile methodology.

Question 51

An effective Agile environment ________.

a

thoroughly outlines plans and processes, allowing team members to focus on tasks

b

uses frequent stakeholder feedback to achieve cost and time savings

c

supports innovation through individual team member work

d

fosters continuous innovation and adaptation

Question 52

What are story points?

a

an estimate of the effort required to satisfy customer requirements

b

time-delineated development cycles

c

a list of prioritized customer requirements that the team and product owner choose from to determine which customer needs will be met in an iteration

d

the amount of work that a team can complete in a given amount of time (usually one iteration)

Question 53

When planning an iteration, an Agile team must consider its velocity to ensure the team does not exhaust itself. The calculation of a team's velocity includes which of the following?

a

only completed work

b

completed and partially completed work

c

complete, partially completed, and incomplete work

d

all remaining story points

Question 54

Which of the following is not a goal of the daily stand-up meeting?

a

give team members a forum to discuss problems in depth

b

recommit team members to the project as a team

c

communicate the project status and discuss any obstacles

d

set the day's direction

Question 55

The line chart that tracks the amount of work remaining in an iteration or release where the line intersects the x-axis at the probable completion date is known as a ___________.

a

burndown chart

b

burn-up chart

c

story board

d

Kanban board

Question 56

An Agile coach ________.

a

solves problems for the team

b

sets the project direction

c

describes and delineates roles on Agile projects

d

prevents scope creep on projects

Question 57

When presented with the following information regarding items in the product backlog, which one is most valuable and therefore most important to include in the next iteration?

a

a user story with an internal rate of return IRR of 10%

b

a user story with an internal rate of return IRR of 0%

c

a user story with an internal rate of return IRR of 20%

d

a user story with an uncertain IRR

Question 58

When a team produces a risk-adjusted backlog it may use a risk score to __________.

a

determine the objective risk level associated with user stories

b

calculate how long high-risk user stories will take to implement

c

subjectively develop a close-enough approximation for prioritization

d

decide whether user stories are correct

Question 59

Which of the following statements regarding risk burndown graphs is false?

a

A risk burndown graph is used to visually track the amount of risk left in a project.

b

A risk burndown graph can be created after risk scores are calculated for each user story.

c

As user stories are implemented the associated risks are either resolved or avoided.

d

The expected downward trend of the chart illustrates that the number of risks resolved or avoided in an iteration increase as work progresses.

Question 60

An Agile team must adapt to situations as they arise. Variations occur because, although the iterations repeated throughout a project may be similar, they are never exactly the same. Which of the following is a result of the adaptive nature of an Agile team?

a

The Agile team will need to budget more time given the experimental nature of adapting to changes.

b

An Agile team can minimize planning and monitoring activities.

c

Adapting to variations helps to complete iterations but causes problems when the project to be done will change.

d

Adapting to variation results in a different product and less customer value.

Question 61

Which of the following statements is true?

a

A Kanban board shows the potential risks that could occur in each phase of a project.

b

A Kanban board is a type of story board that lists the user stories in each phase of a project.

c

The terms Kanban and task board are not interchangeable and have different meanings and uses.

d

Kanban boards show how much work will be involved in the current phase of the project but cannot show the work to be completed over the project lifecycle.

Question 62

________ involves discussions to explore options and reach an agreement.

a

Collaboration

b

Negotiation

c

Conflict resolution

d

Servant leadership

Question 63

For some projects, budgeting is easy; the budget is predefined and the _________ will include as many features as can be created within the budgeted total amount.

a

iteration

b

project

c

story board

d

release

Question 64

Which of the following statements concerning risk-based spikes is false?

a

Risk-based spikes should be used sparingly because they do not deliver customer value.

b

A spike is an experiment used to acquire information and understand complex issues.

c

Risk-based spikes should capture just enough information to resolve any uncertainty.

d

A risk-based spike allows a team to analyze the benefits associated with a user story.

Question 65

Eli is an Agile team leader who needs to conduct quality testing. Because it is inconvenient to access external stakeholders for quality testing, he is looking to have the project team authenticate requirements. To accomplish this, Eli should use _________.

a

incremental development

b

validation

c

verification

d

continuous integration

Question 66

Jules has convened a meeting at the beginning of an iteration to ask his teammates to envision a "perfect project", and then describe why the project exceeded all expectations. They would have to explain what could happen on the project, how it could affect the project, and what the team could do to enhance the chances that this perfect outcome will occur. What is this meeting better known as?

a

a wireframe

b

osmotic communication

c

a pre-mortem

d

exploratory testing

Question 67

Which of the following takes into account the relative value of benefits and costs over time?

a

internal rate of return

b

net present value

c

return on investment

d

relative benefit value

Question 68

Agile practices can be described with which of the following statements?

a

the ability to balance flexibility and stability

b

the ability to predictably operate and profit in a stable business environment

c

the practice of determining and executing team requirements

d

the ability to predict and act on user stories quickly and effectively

Question 69

What is a story map?

a

a rough sketch with text descriptions that explain how the product will function

b

a list of prioritized customer requirements

c

a graphic representation that shows how individual user stories are combined to create a solution

d

a two-to-five year vision that describes what you would like the product to do and when you would like it to be done

Question 70

The image below is most often used as part of ________.

a

earned value management

b

Kano analysis

c

fishbone diagram analysis

d

value stream mapping

Question 71

Graphic visual displays that present work status and team progress in quick, easy-to-understand formats are called _______.

a

information sinks

b

story boards

c

progress boards

d

product roadmaps

Question 72

Agile teams should always consider any important information and lessons learned from previous iterations as they plan upcoming work. What is the incorporation of such information into iteration or release plans called?

a

requirements review

b

the learning cycle

c

compliance

d

an intraspective

Question 73

Which of the following statements regarding affinity estimating is false?

a

It relies on the knowledge and experience of team members to rank-order the user stories in a project.

b

Once the team lays out the user stories of the product backlog, team members collectively discuss how best to re-order the stories so that there is consensus as to where each story belongs.

c

If there is disagreement during the ordering process, the team discusses the discrepancy to gain a common understanding, and then returns to the silent ordering process.

d

At the end of the affinity estimating process the team can quickly estimate the number of story points in each iteration.

Question 74

When an Agile team creates a two-to-five-year plan that describes what they would like a product to do and when it should be done, the team is creating a _________.

a

retrospective

b

product roadmap

c

project charter

d

user story

Question 75

What is the difference between real time and ideal time?

a

Real time is used in Agile projects, while ideal time is used in Waterfall projects.

b

Ideal time accounts for interruptions; real time does not account for interruptions.

c

Ideal time does not account for interruptions; real time accounts for interruptions.

d

Ideal time is an estimate of how long a team thinks a task will take; real time measures the amount of time that a task actually took.

Question 76

Wideband Delphi can be defined as _________.

a

an estimation technique in which teams use pre-labeled cards to express work estimates

b

estimates of the effort required to satisfy customer requirements that are scaled in relation to other requirements

c

an estimation technique in which team members jointly discuss user stories, then individually estimate the amount of work needed to complete the stories

d

an estimating technique that asks team members to silently order user stories before estimating the amount of work they could complete in an iteration

Question 77

Before handing a project over to a production or operations department or to an external customer, effective Agile teams hold one last _________ to officially close the project.

a

retrospective

b

review

c

stand-up

d

iteration

Question 78

The technique that Agilists use to track work completed against the cost to complete that work at a specific point in time is called ________.

a

net present value

b

a cost-benefit ratio

c

an accounting benefit rate

d

earned value management

Question 79

Which of the following methodologies has five stages of development that include modeling, feature lists, planning, design, and software construction?

a

Extreme Programming

b

Feature-list Development

c

Crystal

d

Feature-driven Development

Question 80

What is Agile modeling?

a

a visual mock-up that developers use to verify design concepts and test functionality with users

b

fictional characters that represent the users of a product

c

the act of using models on projects to illustrate relationships among project elements

d

the process of making assumptions about how a role or model will interact with a product

Question 81

Agile development can be defined as which of the following?

a

traditional, sequential project management

b

a form of project management and product development based on a process of incremental and iterative improvements

c

an approach characterized by handling projects concurrently using product teams

d

a form of project management that establishes customer requirements up front and then monitors and controls the project plan until complete

Question 82

Which of the following statements is true?

a

Agile project teams should be staffed first with specialists to ensure that the team has all the necessary skills to complete the project.

b

Team members should refer to iteration planning when developing solutions as finding new ways of meeting goals inevitably decreases velocity.

c

Teams should clarify project boundaries but allow the definition of "done" to change and allow multitasking to increase team cohesion and velocity.

d

Organizations should encourage team members to explore options and make it clear that this exploration occurs without repercussions.

Question 83

Which of the following principles is one of the six key management principles in the Agile Declaration of Interdependence?

a

increase productivity

b

deliver predictable results

c

control creativity and innovation

d

improve effectiveness and reliability

Question 84

During _________ an XP team determines what subsequent product releases will entail by balancing business/customer priorities (from the product owner) and technical estimates to complete the project tasks (from the development team).

a

the planning game

b

continuous integration

c

pair planning

d

the kick-off

Question 85

An Agile team has a limited amount of time and needs to impose time constraints to force important prioritization decisions and pressure to complete activities. This preset period of time is referred to as __________.

a

an iteration

b

a burndown chart

c

a release

d

a timebox

Question 86

Which of the following statements is false?

a

Value stream maps show the amount of work completed and the duration of work in each project phase.

b

Burn charts show project trends over time but they don't provide a sense for how work is progressing within a life cycle.

c

Cumulative flow diagrams are area charts that show the progress of each part of a project life cycle.

d

Story maps show the interdependencies of user stories in a project.

Question 87

Which of the following statements regarding relative prioritization is true?

a

Relative prioritization ranks the product backlog into specific detailed categories.

b

Relative prioritization helps to rank the product backlog into simple high-level categories, which may be further refined as necessary.

c

Relative prioritization is a method of determining which user stories can be disregarded.

d

Relative prioritization is a method of prioritization that incorporates both customer-valued prioritization and financial prioritization techniques.

Question 88

A risk burndown graph demonstrates __________.

a

the amount of time remaining before an iteration will be completed

b

the amount of risk remaining in the product backlog

c

how much risk can be completed in one iteration

d

what will happen if the team fails to complete the project

Question 89

Which of the following best describes user stories?

a

iteration results

b

customer requirements

c

fictional representations of the users of a product

d

estimates of perceived value

Question 90

How does a risk-based spike help Agilists to identify, assess, and track risk?

a

Each spike looks at a segment of the burn chart to determine progress.

b

Risk-based spikes investigate benefits associated with user stories.

c

A risk-based spike uses timeboxed experiments to investigate risks associated with user stories to further discussions and make decisions.

d

A risk-based spike allows the team to discuss how well they worked together to create the product and what improvements they could make.

Question 91

Which of the following would be least helpful to teams implementing value-based prioritization?

a

MMFs

b

NPV

c

VOC

d

WIP

Question 92

Which of the following statements is true?

a

Affinity estimating allows teams to combine user stories into groups of similar size.

b

Affinity estimating often uses a Fibonacci sequence to estimate stories.

c

Affinity estimating allows team members to estimate stories they have an affinity for.

d

Affinity estimating is a specific form of Wideband Delphi.

Question 93

When do customers and stakeholders provide product feedback to the team?

a

during iteration retrospectives

b

during iteration reviews

c

during daily stand-ups

d

during iteration planning meetings

Question 94

Which of the following is not an advantage to using a value stream map?

a

It shows how much work is in each step of a process at any one point in time.

b

It shows all of the steps in a process as an integrated series.

c

It helps expose non-value-added work and inefficiencies.

d

It helps teams evaluate each task for customer value.

Question 95

Keith is watching a user interact with an unfinished product to see if the product increment will do things that it is not supposed to do. This activity is better known as ________.

a

progressive elaboration

b

exploratory testing

c

external rate of return

d

compliance

Question 96

What is the Scrum-specific term for the meeting that coordinates activities across teams in an organization?

a

an iteration review

b

a daily scrum

c

a scrum retrospective

d

a scrum of scrums

Question 97

Which of the following statements is false?

a

Personas describe generic roles for the prototypical users of a product.

b

The goal is to identify one persona to represent the perfect user of a product under development.

c

After creating and verifying personas, the team can then make decisions based on the persona rather than convening with individual users to validate work.

d

Persona descriptions allow the team to make certain decisions and assumptions about how a user will interact with a product.

Question 98

Business cases ________.

a

must be completed in detail before a project charter can be initiated

b

could be progressively elaborated as the Agile project continues

c

are not relevant to Agile projects because these projects adapt as needed

d

should specify how many iterations a project can include

Question 99

Why would a team create a minimal viable product?

a

to help a development team understand which parts of a product are working and which parts need to be modified

b

to provide a standard for use in relative prioritization

c

to enhance negotiation among team members

d

to demonstrate work-in-progress results to ensure continued funding of a project

Question 100

The larger product development process that includes multiple iterations and results in the transition of a finished product into production, operations, or the customer is a __________.

a

release cycle

b

product roadmap

c

iteration retrospective

d

burndown chart

Question 101

In their daily stand-up meeting, team members explain what they accomplished yesterday, what they are working on today, and what obstacles are impeding progress. How long should this meeting take?

a

thirty minutes

b

fifteen minutes

c

ten minutes

d

as much time as possible

Question 102

Which of the following would not be included in an Agile project charter?

a

a detailed description of deliverables

b

customer and stakeholder names

c

team member names

d

iteration lengths

Question 103

Cindy is an Agile team leader who works to eliminate as many barriers to success for her team as possible. She tries to facilitate and empower the team so it becomes a high-performing unit. Which of the following interpersonal skills is Cindy practicing?

a

adaptive leadership

b

servant leadership

c

collaboration

d

emotional intelligence

Question 104

Why is conflict resolution important for an Agile team?

a

Conflict resolution discourages conflicts from arising during collaboration.

b

Conflict resolution ensures that conflict is dealt with during iteration reviews and retrospectives.

c

Conflict resolution enables team members to understand their feelings and the feelings of others.

d

Conflict resolution skills allow conflicts to be identified and resolved quickly.

Question 105

Which of the following is a form of prototyping?

a

a burn chart

b

an information radiator

c

a wireframe

d

a risk-based spike

Question 106

An organization evaluated a value stream map and made adjustments to its processes to improve its development and delivery to customers. As a result, its value stream would now include ________ non-value-added work.

a

no

b

some

c

a lot of

d

only

Question 107

Which XP core practice involves compiling completed tasks into a completed product multiple times each day?

a

continuous testing

b

continuous integration

c

small releases

d

design refactoring

Question 108

The Agile product owner and team meet at the beginning of an iteration to determine which stories from the product backlog they will complete in the iteration. This process is referred to as _________.

a

backlog grooming

b

iteration planning

c

timeboxing

d

making a story board

Question 109

Juan is inspecting the product backlog for the Agile project he is working on. He needs to select one more item to include in the next iteration. Which of the follow should he pick?

a

the item with a NPV of $5000

b

the item with a NPV of $2000

c

the item with a NPV of - $1000

d

the item with a NPV of zero

Question 110

An assumption that nothing is built perfectly the first time and that a team's focus should be on delivering 80% of a product that can be deployed in 20% of the time are fundamental assertions of which of the following?

a

DSDM

b

FDD

c

AUP

d

XP

Question 111

One way that the product owner supports the project is by shaping the product vision. To achieve the vision the product owner creates and maintains a prioritized list of customer requirements called a __________.

a

product backlog

b

control sheet

c

scrum

d

burndown chart

Question 112

Beth is a member of an Agile team who wants to improve a portion of a product without changing its behavior or functionality. What product quality technique should she use?

a

refactoring

b

verification

c

continuous integration

d

validation

Question 113

A user story that provides $1500 in benefit will costs $1000 to implement; therefore, the return on investment (ROI) would be ________.

a

10%

b

30%

c

$500

d

50%

Question 114

At the end of an iteration, an Agile team has completed five user stories, partially completed two user stories, and did not begin one user story. What was the team's velocity?

a

five user stories per iteration

b

six user stories per iteration

c

eight user stories per iteration

d

seven user stories per iteration

Question 115

Once the project boundaries are set, who ultimately decides how the product will be built?

a

the team, stakeholders, and senior management

b

the team

c

the project manager

d

the product owner

Question 116

The process that Julia and her team are following to produce software includes designing the software, writing the code, initially testing the code, correcting any problems, testing the code again, and shipping to the customer. Which of the steps could be considered non-value-added work?

a

designing the code

b

initially testing the code

c

correcting problems

d

shipping to the customer

Question 117

When an Agile team works with customers or stakeholders to develop a contract for a project, the customer may set each of the following parameters except ________.

a

the project scope

b

the priorities for completing the work

c

the number of iterations used to complete the work

d

the project budget

Question 118

When leading an Agile team, an effective product owner should do all of the following except _________.

a

set project boundaries but allow the boundaries to fluctuate

b

maintain a constant flow of communication

c

provide accountability and team guidance

d

provide instructions and assign tasks

Question 119

Which of the following statements is true?

a

Agile projects are designed to be informal so additional communication tools and techniques should be developed to drive activities.

b

Agile tooling is helpful for reporting project progress to stakeholders and keeping the team integrated.

c

Information radiators should not include accomplishments from the previous day or week.

d

Team members not co-located cannot benefit from osmotic communication.

Question 120

Which of the following statements is true?

a

Agile teams do not move through the analysis and design phases quickly because they can only commit to as much work as they can complete in an iteration.

b

An Agile team spends a lot of time trying to analyze every possible scenario that could arise to prevent surprises as the project is progressively elaborated.

c

Each user story in an Agile product backlog is written with as much detail as possible so the team can move directly into executing project work.

d

The start of each iteration is the best time to analyze and design project solutions because that is when the project team revalidates requirements.