PJM6025 TEAMWORK PART 1.3
PJM6025:
Project Scheduling & Cost Plan
Mimi Y. Wan, PhD, PMP
Instructor
Estimating Costs & Durations
• What does estimating involve? Numerous Knowledge Areas
Scope Management
Time Management
Cost Management
Quality Management
Human Resource Management
Communications Management
Risk Management
Procurement Management
Estimation Lifecycle
• Prepare estimates
• Create estimates
• Manage estimates
• Improving estimating methods
Estimating & the Project Lifecycle
Prepare to Estimate
• Gather necessary documents
• Choose estimating method(s)
• Assign responsibilities
Estimating Methods
• Top-down estimate
• Bottom-up estimate
• Parametric estimate
• 3-point estimate (PERT)
Top Down Estimation
• Used with indeterminate activities (IT Project)
• Early method
• Analogous (compare to past projects)
• Learning curve
Bottom-up Estimation
• Start with most detailed activity
• Aggregate costs and durations as we move up theWBS
• More accurate method
• May require SMEs
Parametric Estimation
• Ratio method
• Uses historical data & variables to calculate estimate
• Accuracy depends on underlying data
• Ex. Price per Square Foot
Three Point Estimation (PERT)
Project Evaluation and Review Techniques
• 3 Points Optimistic (3 days)
Most likely (4 days)
Pessimistic (7 days)
Expected Time (ET) = (O + 4M + P) / 6
ET = (3 + 4(4) + 7) / 6 = 4.33
• Can be used to estimate duration and costs
What is the Best Method?
It depends!
• Which estimating method is most helpful for accomplishing this project successfully?
• So, which is most helpful?
• Many times a combination of methods.
• Apply team’s collective experience and judgment to your project
Create the Estimates
• Create estimating schedule
• Collect & review estimates
• Aggregate estimates
• Approve estimates
• Create draft schedule baseline
Final Steps
• Manage the Estimates
• Improve the Estimate Methods
Specific Estimating Considerations
• Managing uncertainty
• Effort & duration
• Realistic estimates
• What is good enough?
Managing Uncertainty in Estimating
• Poor methods Re-baselining
Over-estimating
Padding & slack
• Better methods Contingency
Tolerance
Estimating Terms & Concepts
• Duration – elapsed time between start and finish
• Effort – actual amount of time to complete the task
• Easily confused
Duration & Effort in MS Project
• Example Activity: Submit Permit Application
• Duration: 5 days
• Effort: 8 hours
• Solution: Insert ‘Type’ & ‘Work’ field into Gantt Chart
• Change ‘Type’ to Fixed Duration
• Change ‘Work’ to 8 hours
MS Project Example
• Launch MS Project
• Copy in these rows
• Add in Work and
• Type
Realistic Duration Estimates
• Don’t succumb to pressure
• Use realistic estimates
• Unrealistic estimates usually means longer durations
• Avoid padding
• Create reserves
• Provide a tolerance
What is Good Enough?
• Consider importance of cost, project complexity
• Too much detail is costly
• Too little detail is costly
An Example
• Overview process for estimating a construction project
• Start with high level estimate
• Develop Bottom-up estimate where necessary
• Provide Example of PERT
The Sample Project
Estimation Process
• Initiation Phase: Phase 1: High level commitment from sponsor
Phase 2: Develop detailed scope document & top down estimate
• Planning Phase: Develop detailed blueprints & spec sheets
Create detailed project estimate using a combination of parametric, bottom-up & PERT
High Level Commitment
• Overview of proposed project • Style of home
• Major features
• Proposed location
• Business case • Supports company’s objective
• Market analysis data
• Estimated ROI
Detailed Charter or Scope
• Statement of Purpose
• Deliverables
• Milestones
• Market projections
• Constraints & assumptions
• Resource requirements (i.e. funding estimate)
Phase 2: Planning
• Blueprints created / amended
• Detailed spec sheet created / amended
• Detailed estimate created Parametric method
Bottom up
PERT Analysis
Building the House—Details
• Overview 4 beds
4.5 baths
2 gas fireplaces
1 wet bar
3,600 heated sq. ft.
Engineered septic system
Engineered foundation walls due to elevation
Building the House—Details
• Features Granite countertops
Tile showers
Hardwoods or tile throughout (no carpet)
800 sq. ft. covered deck
600 sq. ft. uncovered deck
Custom kitchen cabinets
Custom entertainment center
Parametric Estimating
• Average project features 3 bed 2.5 baths
Custom cabinets
Granite counters
Combo of hardwood, tile, & carpet
1 fireplace
500 sq. ft. decking
$120 / sq. ft.
• Current project
3,600 sq. ft.
$120 / sq. ft.
Estimated Cost = $432,000
• Base Estimate: $432,000
Parametric Estimating
• Average project features 3 bed 2.5 baths
Custom cabinets
Granite counters
Combo of hardwood, tile, & carpet
1 fireplace
500 sq. ft. decking
$120 / sq. ft.
• Current project
3,600 sq. ft.
$120 / sq. ft.
Estimated Cost = $432,000
Base Estimate: $432,000
Bottom Up Estimating
Additional Features
1. +1 fireplace
2. Wet bar
3. Entertainment center
4. All hardwoods & tile
5. Engineered septic system
6. Engineered foundation
7. 800 sq. ft. covered deck
8. +2 bathrooms
Estimated cost $76,200
1. $5,200
2. $3,500
3. $2,500
4. $8,600
5. $12,000
6. $8,200
7. $14,000
8. $22,200
Total Estimate
Base estimate: $432,000
Additional features: $76,200
Total Project Estimate: $508,200
PERT Analysis
Formulae: PERT Mean = (O + 4M + P)/6
Std. Dev = (P – O)/6
Variance = (Std. Dev)2
Compute Probability of Final Cost being less than $515,000
(Desired Outcome – Sum of PERT Mean)/SQRT(Var) = Z
(515000 – 509350)/SQRT(19,578,611) = 1.27
Lookup Z value: 1.27
www.vassarstats.net/tabs.html#z
Probability = 79.6% Probability Cost is less than $522,500? 99.7%
PERT Analysis—Critical Path
Formulae: PERT Mean = (O + 4M + P)/6
Std. Dev = (P – O)/6
Variance = (Std. Dev)2
Probability less than 155 days
(Desired Outcome – Sum of PERT Mean)/SQRT(Var) = Z
(155 – 148)/SQRT(7.58) =2.54
Lookup Z value: 2.54
www.vassarstats.net/tabs.html#z
Probability = 98.9%
PERT Analysis Informs Reserves
Time Buffer
• 8 days
• 99.6% certain
Cost Buffer
• $13,000
• 99.7% certain